Line 21: Line 21:
== 2017-09-04 ==
== 2017-09-25 ==
Line 24: Line 25:
 * --(Crane out SF.)--
 * --(Raise BF cap and retrieve lost hex cable clamp PEEK piece.)--
 * --(Crane in SF.)--
 * --(Install SF-BF rod with hex cable clamp.)--
 * --(Route cables via hex cable clamp up to below SF.)--
 * --(Adjust BF ballast mass for total weight and pitch/roll.)--
 * --(Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.)--
 * --(Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).)--
 * --(Calibrate SF LVDT.)--
 * --(Install SF main ballast mass.)--
 * --(Cable and test SF fishing rod stepper.)--
 * --(Add SF cap.)--
 * Lift and weigh SF/... section.
 
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Fix #1 geophone adapter cable.
 * Fix broken pico adapter cable?
 * Debug all electronics, starting with IRM OSEMs.
 * Unlock IP; use jacks and FRs to center.
 * Check IP yaw.
 * Recheck centering of suspension in assembly frame.
 * Measure IP period; adjust ballast mass.
 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
 * LBB stuff (see below).
 *

=== LBB Sequence
 * Unclamp LBB ring sandwich; fully suspend Cu ring.
 * Unscrew LBB from tank brackets.
 * Hook LBB.
 * Remove TBD amount of spacers from between LBB and tank brackets.
 * Set LBB blade stops to nominal height.
 * Extend foot screws on LBB to just barely support LBB.
 * Adjust height of LBB magnet ring to set proper gap (4 mm??).
 * Retract LBB foot screws.
 * Add temporary ballast to LBB until LBB blades just barely sink below stops.
 * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
 * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
 * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.
Line 40: Line 52:
 * --(Rearrange arc weights on PI to allow installation of magic wand.)--
 * --(Install magic wand on PI.)--
 * Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
 * --(Rearrange magnets on SF damper magnet ring for full three Cu segments.)--
 * --(Find Ni-plated rods for SF damper magnet ring and do fit check.)--
 * --(Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.)--
 * Wipe LLB damper parts with ethanol.
 * --(Get Cu O-rings for feedthroughs.)--
 * Figure out how to tighten PI yaw return spring.
 * --(Recalibrate remachined LBB springs and choose best three.)--

== Dates ==
 * Repaired LBB half ring is returned: 9/11 (Mon, lunchtime)
 * BUMAX countersunk screws for LBB Cu
 * SDC screws for LBB half rings: 9/15 (Fri)
 * LBB Cu segments: 9/19-20
Line 63: Line 59:
 * Calibrate PI vertical LVDT.
 * Set yoke on PI vertical LVDT (if necessary).
 * Calibrate PI horizontal LVDTs.
 * Figure out how to make PI yaw adjustment reliable.
Line 78: Line 72:
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3  * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
Line 89: Line 83:
 * --(Create a proper DAC Monitor MEDM screen.)--
 * --(Improve ADC Monitor MEDM screen.)--

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-09-25

Main Assembly Sequence

  • Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Fix #1 geophone adapter cable.
  • Fix broken pico adapter cable?
  • Debug all electronics, starting with IRM OSEMs.
  • Unlock IP; use jacks and FRs to center.
  • Check IP yaw.
  • Recheck centering of suspension in assembly frame.
  • Measure IP period; adjust ballast mass.
  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • LBB stuff (see below).

=== LBB Sequence

  • Unclamp LBB ring sandwich; fully suspend Cu ring.
  • Unscrew LBB from tank brackets.
  • Hook LBB.
  • Remove TBD amount of spacers from between LBB and tank brackets.
  • Set LBB blade stops to nominal height.
  • Extend foot screws on LBB to just barely support LBB.
  • Adjust height of LBB magnet ring to set proper gap (4 mm??).
  • Retract LBB foot screws.
  • Add temporary ballast to LBB until LBB blades just barely sink below stops.
  • Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
  • Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
  • Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.

In parallel, time permitting

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Get pico drive screens fixed (Miyo-kun)
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Get clean bag laundered.
  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Lock washers for LBB dampers
    • Temporary ballast mass (dog clamps) in BF.
  • Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

Electrical

  • Decide final in-vacuum and in-air cable routing (Enzo).
  • Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.