Line 3: | Line 3: |
2017-04-03 == Facilities (mostly full team) == |
== Every Week == === Facilities (mostly full team) === |
Line 11: | Line 10: |
== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) == * Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary. |
== 2017-04-03 == === SF/BF/... === * Trim BF to correct pitch/roll. * Install temporary ballast mass in SF. * Lift SF/BF/... and check SF pitch/roll balance and overall weight. === Continue PI Prep === * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender. * Install fishing rod. * Enlarge ring of crane adapter. * Find table, weights, etc for use with LBB blade bending jigs. * Set up LBB blade tensioning jig. * Install LLB blades. * Install LLB blade units in PI. === Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) === |
Line 15: | Line 29: |
* Debug TM-H4. | |
Line 16: | Line 31: |
== Electronics (mostly Enzo, Mark) == * Make more anti-feedthrough adapters. |
=== Electronics (mostly Enzo, Mark) === |
Line 26: | Line 40: |
== PI Prep == * Prepare PI for moving. * Remove accelerometers. * Remove large weights. * Remove arc weights (move some to second floor, wrap rest for storage). * Attach lifting plates. * Wrap with clingwrap, cover with spare cleanbag. * Clear path to remove PI with forklift. * Move worktables. * Move portable cleanroom. * Shutdown rack and move electrical cables. * Prepare second floor for receiving PI. * Clean and clingwrap pallet. * Double-check dimensions. * Disconnect fan cables, curtain. * Crane PI into clean booth. * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender. * Install fishing rod. * Find table, weights, etc for use with LBB blade bending jigs. * Install LLB blades. * Install LLB blade units in PI. |
|
Line 49: | Line 41: |
* Get Perry (and Enzo) set up with SUMCON. * Update SUMCON model of full BS. * Do cut-down SUMCON model of just payload hanging from fixed BS. * Compare measured TFs to cut-down model(s). |
VIS Type B Near Term To-Do List
Every Week
Facilities (mostly full team)
- Clean up after floor work.
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
2017-04-03
SF/BF/...
- Trim BF to correct pitch/roll.
- Install temporary ballast mass in SF.
- Lift SF/BF/... and check SF pitch/roll balance and overall weight.
Continue PI Prep
- Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender.
- Install fishing rod.
- Enlarge ring of crane adapter.
- Find table, weights, etc for use with LBB blade bending jigs.
- Set up LBB blade tensioning jig.
- Install LLB blades.
- Install LLB blade units in PI.
Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)
- Test SF LVDT.
- Test SF fishing rod stepper.
- Debug TM-H4.
Electronics (mostly Enzo, Mark)
- Add retaining screws to cables at feedthroughs (mostly done, needs finishing).
- Work with Miyo-kun to get pico drivers added to BS rack and screens
- Update E1503600 with DIO card for HPCDs, etc, etc.
- Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
- Send list of required in-vacuum cables to Takahashi-san
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)
Real-time and SUMCON models (mostly Perry, Mark)
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.