Line 1: Line 1:
= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
2017-04-03 [[../ToDoOldBS|Archived BS To-Do Items]]
Line 5: Line 5:
== Facilities (mostly full team) ==
 * Clean up after floor work.
[[../ToDoSR|SR To-Do Items]]

[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]

<<Anchor(EveryWeek)>>

== Every Week ==
=== Facilities ===
Line 10: Line 18:
 * Get stuff from [[../WishList]]
Line 11: Line 20:
== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) ==
 * Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary.
 * Test SF LVDT.
 * Test SF fishing rod stepper.
== December 2018 vent ==
 * Look for cracks in F0 blades.
 * Install new yaw F0 stepper mechanism (if available).
 * Install new double-sided F0 fishing rod (have all parts except blades).
 * Add more mass to IP to get a lower frequency.
 * Service geophones (one has high noise, one has DC offset).
 * Re-calibrate F0 GAS LVDT.
 * Confirm the positions of the IP LVDTs and Actuators.
 * Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
Line 16: Line 30:
== Electronics (mostly Enzo, Mark) ==
 * Make more anti-feedthrough adapters.
 * Add retaining screws to cables at feedthroughs (mostly done, needs finishing).
 * Work with Miyo-kun to get pico drivers added to BS rack and screens
 * Update E1503600 with DIO card for HPCDs, etc, etc.
 * Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
 * Send list of required in-vacuum cables to Takahashi-san
<<Anchor(ComingWeeks)>>

== ASAP ==
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--

=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''

 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control

=== Documentation and Operation Manual ===
 * Add useful info from Enzo's notebook to BSData.

<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * --(Move safety bars from BS AF area to SR2 area.)--
 * Update circuit diagram.
 * (Time permitting) Try adding mass to IP.
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.

=== Minor Tasks ===
==== Mechanical ====
 * Put pointy-tipped screw in RM trolley for BS
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--

<<Anchor(elec)>>
==== Electrical ====
 * Update BS Circuit diagram, D1503600
  * --(Note removal of LED/PD on TM OSEMs.)--
  * Organize stepper reset system and watchdog BIO.
  * Include information on assignment of channels to feedthrough positions.
  * Reflect gender-changers and non-flipping feedthrough adapters.
  * Reflect actual cable lengths.
  * Include LVDT pin size (1 mm).
  * Include Stepper pin size (1.6 mm).
  * --(Undo renumbering of IP items.)--
  * --(Page 10: "DIO Card # 0" should be "DIO Card # 1")--
  * --(Include OutConfigBoards on OL page (Sheet 18).)--
  * --(Update HPCD section to reflect:)--
   * --(All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.)--
   * --(Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.)--

==== Real-time and SUMCON models ====
 * Create SUMCON models for full BS and major installation milestones.
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
Line 24: Line 103:
 * Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)

== PI Prep ==
 * Prepare PI for moving.
  * Remove accelerometers.
  * Remove large weights.
  * Remove arc weights (move some to second floor, wrap rest for storage).
  * Attach lifting plates.
  * Wrap with clingwrap, cover with spare cleanbag.
 * Clear path to remove PI with forklift.
  * Move worktables.
  * Move portable cleanroom.
  * Shutdown rack and move electrical cables.
 * Prepare second floor for receiving PI.
  * Clean and clingwrap pallet.
  * Double-check dimensions.
  * Disconnect fan cables, curtain.
 * Crane PI into clean booth.
 * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender.
 * Install fishing rod.
 * Find table, weights, etc for use with LBB blade bending jigs.
 * Install LLB blades.
 * Install LLB blade units in PI.

== Real-time and SUMCON models (mostly Perry, Mark) ==
 * Get Perry (and Enzo) set up with SUMCON.
 * Update SUMCON model of full BS.
 * Do cut-down SUMCON model of just payload hanging from fixed BS.
 * Compare measured TFs to cut-down model(s).
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.
 * Understand/document/debug Kokeyama-san's DIO stuff.
 * Measure LPCD and HPCD output filter response.
 * Design and install software compensation filters for LPCD and HPCD output filters.

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

December 2018 vent

  • Look for cracks in F0 blades.
  • Install new yaw F0 stepper mechanism (if available).
  • Install new double-sided F0 fishing rod (have all parts except blades).
  • Add more mass to IP to get a lower frequency.
  • Service geophones (one has high noise, one has DC offset).
  • Re-calibrate F0 GAS LVDT.
  • Confirm the positions of the IP LVDTs and Actuators.
  • Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).

ASAP

  • Get picomotor drivers back on line.

  • Debug BS BIO connections, especially PI IP.

Main Assembly Sequence

  • Necessary for phase-I★★★
    • Modify IP LVDT damping filters to include set point.

    • TFs.

    • EXCHANGE YAW/VERT FRs at F0

  • Necessary for phase-II★★
    • Debug BS geophones.
    • Flip circuit boards in BS geophones to make them the same as SRx.
    • Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)

    • Design PI Sensor blending filter.
    • Tune the LVDT sensitivity
    • Measure IP period; adjust ballast mass.
  • At some point (remotely)★
    • Improve OL offloading.
    • Improve GAS offloading.
    • Spectral analysis of Oplev.
    • Design, install angular lock servo using OL. (Almost done for phase-I)
    • Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
    • Subtract DC level of Geophones.
    • Spectra analysis of PI sensors (PI LVDTs and Geophones).
    • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
    • Set all EQ stops to TBD clearance.
    • Modify the model for IP coil driver control

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.

  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace temporary ballast mass (dog clamps).

  • Characterize replacement F0.
  • Wipe/clean arc weights that were rained on.

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.