Line 21: | Line 21: |
== 2017-09-11 == | == 2017-10-02 == === SR2 stuff === * Replace BS service port covers, or reinforce foil with tape. * Cling-wrap or move: * White plastic table * Writing table * Tall metal table |
Line 24: | Line 33: |
* Debug BF LVDT actuation. * Debug other actuation. * Remove F-0 rod and reinstall with hex cable clamp. * Route cables up past hex cable clamps. * Adjust SF trim mass for pitch/roll/vertical. * |
* Check for bubble level and other tools in tank. * Remove stickers on IP and clean with ethanol (some were missed last time). * Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe. * Check that all in-air cables are labeled. * Fix broken pico adapter cable? * If possible, reroute cable to eliminate need for with feedthrough. * Debug all electronics, especially actuation. * Check IP yaw. * Recheck centering of suspension in assembly frame. * Measure IP period; adjust ballast mass. * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * Get ready for full TFs. |
Line 31: | Line 47: |
=== In parallel, time permitting === * Fix links to ADC_MONITOR screens. * Check that all Take/Restore Safe.snap buttons work. * Check that we still have all LBB parts (there was an issue with borrowed lock nuts). * Wipe LLB damper parts with ethanol. * Figure out how to tighten PI yaw return spring. == Dates == * BUMAX countersunk screws for LBB Cu * SDC screws for LBB half rings: 9/15 (Fri) * LBB Cu segments: 9/19-20 |
=== Software === * Enter new IP matrices and do safe.snap. * Get pico drive screens fixed (Miyo-kun) * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. |
Line 48: | Line 60: |
* Get pico drive screens fixed (Miyo-kun) * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
* Figure out how to make PI yaw adjustment reliable. |
Line 63: | Line 72: |
* Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-02
SR2 stuff
- Replace BS service port covers, or reinforce foil with tape.
- Cling-wrap or move:
- White plastic table
- Writing table
- Tall metal table
Main Assembly Sequence
- Check for bubble level and other tools in tank.
- Remove stickers on IP and clean with ethanol (some were missed last time).
- Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
- Check that all in-air cables are labeled.
- Fix broken pico adapter cable?
- If possible, reroute cable to eliminate need for with feedthrough.
- Debug all electronics, especially actuation.
- Check IP yaw.
- Recheck centering of suspension in assembly frame.
- Measure IP period; adjust ballast mass.
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Get ready for full TFs.
Software
- Enter new IP matrices and do safe.snap.
- Get pico drive screens fixed (Miyo-kun)
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.