Differences between revisions 131 and 183 (spanning 52 versions)
Revision 131 as of 2017-09-14 12:15:31
Size: 3754
Editor: MarkBarton
Comment:
Revision 183 as of 2017-12-15 15:40:59
Size: 3409
Editor: AyakaShoda
Comment:
Deletions are marked like this. Additions are marked like this.
Line 21: Line 21:
== 2017-09-11 ==
== ASAP ==
Line 24: Line 25:
 * Debug BF LVDT actuation.
 * --(Debug other actuation.)--
 * --(Remove F-0 rod and reinstall with hex cable clamp.)--
 * --(Route cables up past hex cable clamps.)--
 * --(Adjust SF trim mass for pitch/roll/vertical.)--
 * --(Route all SF/... cables through to the flange and test.)--
 * --(Cable all PI items through to the flange.)--
 * --(Disconnect the SS from the AF.)--
 * --(Roughly level the PI so as to make the SS vertical.)--
 * --(Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.)--
 * Test all PI items:
  * Yaw stepper.
  * F0 LVDT sensing
  * F0 LVDT actuation
  * --(Horizontal steppers)--
  * Horizontal LVDT sensing
  * Horizontal LVDT actuation
  * --(Geophones)-- (except one cable broken: #1)
 * Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS.
 * --(Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS.)-- 425 mHz
 * Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS.
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * Check IP BIO is working or not.

 * Necessary for phase-II★★
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Re-calibrate F0 GAS LVDT
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.

 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control
Line 47: Line 50:
=== In parallel, time permitting ===
 * --(Fix links to ADC_MONITOR screens.)--
 * --(Check that all Take/Restore Safe.snap buttons work.)--
 * --(Check that we still have all LBB parts (there was an issue with borrowed lock nuts).)--
 * --(Wipe LLB damper parts with ethanol.)--
 * Figure out how to tighten PI yaw return spring.
 * --(Install LBB Cu damper ring in tank (less Cu for now).)--
 * Fix #1 geophone adapter cable.
 * Fix broken pico adapter cable
=== Software ===
 * Update real-time model to number channels from #0.
 * Do better interface to IP steppers (make a wrapper for Miyo-kun's driver which includes geometry matrix; adapt Shoda-san's version).
 * --(Write a guardian.)--
 * Sort out SVN.
 * Create SUMCON model with values commented.
Line 57: Line 57:
== 2017-09-11 == === Medm screens ===
 * Remove unused screens.
Line 59: Line 60:
=== Main Assembly Sequence === === Documentation and Operation Manual ===
 * Publish matrices for IP FRs.
 * Publish matrices for BS PI sensors v4.
 * Finish Foton Operation Manual page.
 * Complete MEDM Operation Manual page.
 * Pico Motor Operation Manual page.
 * Add useful info from Enzo's notebook to BSData.
Line 61: Line 68:
== Dates ==
 * BUMAX countersunk screws for LBB Cu (by 9/20)
 * SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup)
 * LBB Cu segments: 9/19-20
=== Design ===
 * Finalize redesign of IP yaw adjuster.
 * Design better F0 FR adjuster.
 * Design LBB ballast mass.
Line 69: Line 76:
 * Move safety bars from BS AF area to SR2 area.
 * Close hole in floor above BS AF area.
 * Wipe any rust from around IP LVDTs.
 * Update circuit diagram.
 * (Time permitting) Try adding mass to IP.
Line 71: Line 83:
 * Get pico drive screens fixed (Miyo-kun)
 * Calibrate PI vertical LVDT.
 * Set yoke on PI vertical LVDT (if necessary).
 * Calibrate PI horizontal LVDTs.
 * Figure out how to make PI yaw adjustment reliable.
Line 78: Line 87:
 * Get clean bag laundered.
Line 81: Line 89:
  * Lock washers for LBB dampers
Line 83: Line 90:
 * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Line 86: Line 92:
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3
 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Line 97: Line 100:
 * Design and install GAS drift compensation filters.

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

ASAP

Main Assembly Sequence

  • Necessary for phase-I★★★
    • Modify IP LVDT damping filters to include set point.

    • TFs.

    • Check IP BIO is working or not.
  • Necessary for phase-II★★
    • Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)

    • Design PI Sensor blending filter.
    • Re-calibrate F0 GAS LVDT
    • Tune the LVDT sensitivity
    • Measure IP period; adjust ballast mass.
  • At some point (remotely)★
    • Improve OL offloading.
    • Improve GAS offloading.
    • Spectral analysis of Oplev.
    • Design, install angular lock servo using OL. (Almost done for phase-I)
    • Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
    • Subtract DC level of Geophones.
    • Spectra analysis of PI sensors (PI LVDTs and Geophones).
    • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
    • Set all EQ stops to TBD clearance.
    • Modify the model for IP coil driver control

Software

  • Update real-time model to number channels from #0.
  • Do better interface to IP steppers (make a wrapper for Miyo-kun's driver which includes geometry matrix; adapt Shoda-san's version).
  • Write a guardian.

  • Sort out SVN.
  • Create SUMCON model with values commented.

Medm screens

  • Remove unused screens.

Documentation and Operation Manual

  • Publish matrices for IP FRs.
  • Publish matrices for BS PI sensors v4.
  • Finish Foton Operation Manual page.
  • Complete MEDM Operation Manual page.
  • Pico Motor Operation Manual page.
  • Add useful info from Enzo's notebook to BSData.

Design

  • Finalize redesign of IP yaw adjuster.
  • Design better F0 FR adjuster.
  • Design LBB ballast mass.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.
  • Close hole in floor above BS AF area.
  • Wipe any rust from around IP LVDTs.
  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Temporary ballast mass (dog clamps) in BF.

Electrical

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)