Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
2017-04-03 | [[../ToDoOldBS|Archived BS To-Do Items]] |
Line 5: | Line 5: |
== Facilities (mostly full team) == * Clean up after floor work. |
[[../ToDoSR|SR To-Do Items]] [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] <<Anchor(EveryWeek)>> == Every Week == === Facilities === |
Line 10: | Line 18: |
* Get stuff from [[../WishList]] | |
Line 11: | Line 20: |
== PI Move == * General prep * Decide if air shower needs to be moved. * Triple-check dimensions around second-floor parking spot for PI; decide best place for pallet. * Check for obstacles along path around -X side of cleanbooth. * Find/clean Saito-sensei's PI lifting adapter and any needed fasteners. * Check both crane remote controls (clean and dirty) are charged. * Prepare PI for moving. * Remove accelerometers and store safely. * Remove large weights. (How? With forklift at last minute? Where to?) * Remove arc weights (move some to second floor, wrap rest for storage). * Attach lifting plates. * Wrap with clingwrap, cover with spare cleanbag. * Remove old cabling from PI to rack. * Prepare second floor for receiving PI. * Clean and clingwrap pallet. * Find metal plates and/or duckboards for on top of pallets. * Move BS cables on -Y side of tank off top of beam. * Find shims (about 75 mm high) to put on beam where cables were, to help support pallet. * Clear path to remove PI with forklift. * Move any obstacles identified previously. * Shutdown BS/PR2 racks and move electrical cables. * Move any stored items on -Y side of portable cleanroom. * Move portable cleanroom towards -Y. * Move worktables from next to BS/PR2 racks. * Move PI * Disconnect fan cables, curtain (Miyoki-san). * Unzip ceiling panel. * Crane pallet into cleanbooth. * Lay foil on pallet. * Forklift PI to -X,+Y corner of cleanbooth * Crane PI into clean booth. * Cleanup * Zip up ceiling panel. * Reconnect fan cables, curtain (Miyoki-san). * Replace tables near BS/PR2 racks * Move portable cleanroom back to original spot. * Re-lay electrical cables. * Power up racks. |
<<Anchor(ComingWeeks)>> |
Line 51: | Line 22: |
== Continue PI Prep == * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender. * Install fishing rod. * Find table, weights, etc for use with LBB blade bending jigs. * Install LLB blades. * Install LLB blade units in PI. |
== 2017-10-10 == |
Line 58: | Line 24: |
== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) == * Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary. * Test SF LVDT. * Test SF fishing rod stepper. |
=== Main Assembly Sequence === * --(Account for second bubble level (might be on BF))--. * Borrow portable hard drive. * Clean up sticker residue and magic marker writing. * --(Remove LVDT modules; identify screws.)-- * --(Check that all in-air cables are labeled)--. * If possible, reroute cable to eliminate need for fifth feedthrough. * --(Debug all electronics, especially actuation.)-- * Measure IP period; adjust ballast mass. * Calibrate all LVDTs. --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * Set all EQ stops to TBD clearance. * --(Install small KOACH filters on LBB.)-- * --(Remove First Contact.)-- * --(Cable optical lever (Simon, Enzo))-- * --(Align optical lever (Simon))-- * Get ready for full TFs. |
Line 63: | Line 42: |
== Electronics (mostly Enzo, Mark) == * Make more anti-feedthrough adapters. * Add retaining screws to cables at feedthroughs (mostly done, needs finishing). * Work with Miyo-kun to get pico drivers added to BS rack and screens * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) * Send list of required in-vacuum cables to Takahashi-san |
=== Etc === * Move stuff out of PR2 area. * Tidy/label parts. * Move safety bars from BS AF area to SR2 area. * (Put up safety bars in SR3 area.) * Close hole in floor above BS AF area. === Software === * --(Enter new IP matrices and do safe.snap.)-- * Send stepper driver info to Miyo-kun. * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. * --(Add support for comments to SUMCON.)-- * Create SUMCON model with values commented. * Derive matrices for IP FRs. === Design === * Finalize redesign of IP yaw adjuster. * Design better F0 FR adjuster. <<Anchor(RealBSHang)>> == Tasks Not To Forget == === Major Tasks === * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Figure out how to make PI yaw adjustment reliable. === Minor Tasks === ==== Mechanical ==== * Put pointy-tipped screw in RM trolley for BS * Return/replace borrowed parts: * Temporary ballast mass (dog clamps) in BF. ==== Electrical ==== ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 71: | Line 83: |
* Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata) == Real-time and SUMCON models (mostly Perry, Mark) == * Get Perry (and Enzo) set up with SUMCON. * Update SUMCON model of full BS. * Do cut-down SUMCON model of just payload hanging from fixed BS. * Compare measured TFs to cut-down model(s). * Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. |
* Understand/document/debug Kokeyama-san's DIO stuff. * Measure LPCD and HPCD output filter response. * Design and install software compensation filters for LPCD and HPCD output filters. * Design and install GAS drift compensation filters. |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-10
Main Assembly Sequence
Account for second bubble level (might be on BF).
- Borrow portable hard drive.
- Clean up sticker residue and magic marker writing.
Remove LVDT modules; identify screws.
Check that all in-air cables are labeled.
- If possible, reroute cable to eliminate need for fifth feedthrough.
Debug all electronics, especially actuation.
- Measure IP period; adjust ballast mass.
Calibrate all LVDTs. BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Set all EQ stops to TBD clearance.
Install small KOACH filters on LBB.
Remove First Contact.
Cable optical lever (Simon, Enzo)
Align optical lever (Simon)
- Get ready for full TFs.
Etc
- Move stuff out of PR2 area.
- Tidy/label parts.
- Move safety bars from BS AF area to SR2 area.
- (Put up safety bars in SR3 area.)
- Close hole in floor above BS AF area.
Software
Enter new IP matrices and do safe.snap.
- Send stepper driver info to Miyo-kun.
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
Add support for comments to SUMCON.
- Create SUMCON model with values commented.
- Derive matrices for IP FRs.
Design
- Finalize redesign of IP yaw adjuster.
- Design better F0 FR adjuster.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Temporary ballast mass (dog clamps) in BF.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.