Differences between revisions 143 and 210 (spanning 67 versions)
Revision 143 as of 2017-09-20 12:18:04
Size: 4235
Editor: EnzoTapia
Comment:
Revision 210 as of 2019-01-04 15:21:23
Size: 155
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
This list has been merged into the common Type B list: [[../ToDo]].
Line 4: Line 6:

[[../ToDoSR|SR To-Do Items]]

[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]

<<Anchor(EveryWeek)>>

== Every Week ==
=== Facilities ===
 * Vacuum and roll floor.
 * Wipe ladders.
 * Tidy tools, parts.
 * Get stuff from [[../WishList]]

<<Anchor(ComingWeeks)>>

== 2017-09-19 ==
(No work Monday 9/18)
=== Main Assembly Sequence ===
 * --(Debug BF LVDT actuation)--.
 * --(Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate))-- 36mm.
 * Test all PI items:
  * Yaw stepper (tested, not clearly working).
  * --(F0 LVDT sensing)--
  * --(F0 LVDT actuation)--
  * Calibrate F0 LVDT.
  * Horizontal LVDT sensing
  * Horizontal LVDT actuation
  * --(Geophones (issues with driver, cables, descramblers))--
 * --(Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS)-- 2 Measurements: f1=0.443 Hz, f2=0.454 Hz.
 * --(Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS)-- 2 Measurements: f1=0.208 Hz, f2=0.210 Hz.
 * --(Double check BS pitch with OL.)--
 * --(Adjust SF damper ring to correct gap.)--
 * --(Install lock nuts on F0 GAS FR at TBD positions.)--
 * Lock BF and F0 keystones (but ''not'' SF keystone).
 * Lock RM to BS and IRM to IM.
 * Lock RM, IRM and BF (but not SF) to security structure.
 * Lock IP.
 * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
 * Attach lifting fixture.


 * Remove BF- and SF-level crossbars.
 * Remove geophones for craning.
 * Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
 * --(Attach lifting plates.)--
=== Tank Preparation Sequence ===
 * Attach Cu segments to LBB damper ring.
 * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
 * Crane tank lid off.
 * Crane LBB damper rings to top of tank and suspend.
 * Crane suspension out of assembly frame.
 * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
 * Crane suspension into tank and connect upper rods to LBB Cu ring.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Measure required ballast for LBB.
 * Unlock suspension and readjust.
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).

=== In parallel, time permitting ===
 * --(Fix issue with geophone distributor.)--
 * Fix #1 geophone adapter cable (and replace borrowed one).
 * Fix broken pico adapter cable.
 * Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable.

<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Get pico drive screens fixed (Miyo-kun)

=== Minor Tasks ===
==== Mechanical ====
 * Get clean bag laundered.
 * Put pointy-tipped screw in RM trolley for BS
 * Return/replace borrowed parts:
  * Lock washers for LBB dampers
  * Temporary ballast mass (dog clamps) in BF.
 * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

==== Electrical ====
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

==== Real-time and SUMCON models ====
 * Create SUMCON models for full BS and major installation milestones.
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
 * Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
 * Understand/document/debug Kokeyama-san's DIO stuff.
 * Measure LPCD and HPCD output filter response.
 * Design and install software compensation filters for LPCD and HPCD output filters.
 * Design and install GAS drift compensation filters.

VIS Type B BS Near Term To-Do List

This list has been merged into the common Type B list: ../ToDo.

Archived BS To-Do Items

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)