Line 22: | Line 22: |
== 2017-09-25 == | == 2017-10-30 == |
Line 25: | Line 25: |
* Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). * Fix #1 geophone adapter cable. * Fix broken pico adapter cable? * Debug all electronics, starting with IRM OSEMs. * Unlock IP; use jacks and FRs to center. * Check IP yaw. * Recheck centering of suspension in assembly frame. |
* Realign OL. * Design, install angular lock servo using OL. * Calibrate IP LVDT actuation against IP LVDT sensing. * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. * Modify IP LVDT damping filters to include set point. * Set all EQ stops to TBD clearance. |
Line 34: | Line 33: |
* LBB stuff (see below). * |
* TFs. |
Line 37: | Line 35: |
=== LBB Sequence * Unclamp LBB ring sandwich; fully suspend Cu ring. * Unscrew LBB from tank brackets. * Hook LBB. * Remove TBD amount of spacers from between LBB and tank brackets. * Set LBB blade stops to nominal height. * Extend foot screws on LBB to just barely support LBB. * Adjust height of LBB magnet ring to set proper gap (4 mm??). * Retract LBB foot screws. * Add temporary ballast to LBB until LBB blades just barely sink below stops. * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles. * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal. * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal. |
=== Etc === * Move stuff out of PR2 area. * Tidy/label parts. * Move safety bars from BS AF area to SR2 area. * Put up safety bars in SR3 area. * Close hole in floor above BS AF area. |
Line 51: | Line 42: |
=== In parallel, time permitting === | === Software === * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. * Add support for comments to SUMCON. * Create SUMCON model with values commented. * Publish matrices for IP FRs. === Design === * Finalize redesign of IP yaw adjuster. * Design better F0 FR adjuster. |
Line 56: | Line 58: |
* Wipe any rust from around IP LVDTs. * Update circuit diagram. * (Time permitting) Try adding mass to IP. |
|
Line 58: | Line 63: |
* Get pico drive screens fixed (Miyo-kun) | |
Line 63: | Line 67: |
* Get clean bag laundered. | |
Line 66: | Line 69: |
* Lock washers for LBB dampers | |
Line 68: | Line 70: |
* Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. | |
Line 71: | Line 72: |
* Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-30
Main Assembly Sequence
- Realign OL.
- Design, install angular lock servo using OL.
- Calibrate IP LVDT actuation against IP LVDT sensing.
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
- Modify IP LVDT damping filters to include set point.
- Set all EQ stops to TBD clearance.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- TFs.
Etc
- Move stuff out of PR2 area.
- Tidy/label parts.
- Move safety bars from BS AF area to SR2 area.
- Put up safety bars in SR3 area.
- Close hole in floor above BS AF area.
Software
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
- Add support for comments to SUMCON.
- Create SUMCON model with values commented.
- Publish matrices for IP FRs.
Design
- Finalize redesign of IP yaw adjuster.
- Design better F0 FR adjuster.
Tasks Not To Forget
Major Tasks
- Wipe any rust from around IP LVDTs.
- Update circuit diagram.
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Temporary ballast mass (dog clamps) in BF.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.