Line 22: Line 22:
== 2017-09-25 == == 2017-10-02 ==
Line 25: Line 25:
 * --(Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).)--
 * --(Fix #1 geophone adapter cable.)--
 * Tidy up and cover things to prepare for SR2 crane slot work.
 * Replace BS service port covers.
 * Check for bubble level and other tools in tank.
 * Remove stickers on IP and clean with ethanol (some were missed last time).
 * Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
 * Check that all in-air cables are labeled.
Line 28: Line 32:
 * Debug all electronics, starting with IRM OSEMs. (half done)
 * --(Unlock IP; use jacks and FRs to center.)--
 * If possible, reroute cable to eliminate need for with feedthrough.
 * Debug all electronics, especially actuation.
Line 33: Line 37:
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
Line 34: Line 39:
 * LBB stuff (see below).
 *
 * Set all EQ stops to proper clearance.
 * Get ready for full TFs.
Line 37: Line 42:
=== LBB Sequence ===
 * --(Unclamp LBB ring sandwich; fully suspend Cu ring.)--
 * --(Unscrew LBB from tank brackets.)--
 * --(Hook LBB.)--
 * --(Remove TBD amount of spacers from between LBB and tank brackets.)--
 * --(Set LBB blade stops to nominal height.)--
 * --(Extend foot screws on LBB to just barely support LBB.)--
 * --(Adjust height of LBB magnet ring to set proper gap (4 mm??).)--
 * --(Retract LBB foot screws.)--
 * --(Add temporary ballast to LBB until LBB blades just barely sink below stops.)--
 * --(Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.)--
 * --(Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.)--
 * --(Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.)--

=== In parallel, time permitting ===
=== Software ===
 * Enter new IP matrices and do safe.snap.
 * Get pico drive screens fixed (Miyo-kun)
 * Update real-time model to number channels from #0.
 * Remove old OL stuff; add link to new OL stuff.
 * Remove unused screens.
 * Sort out SVN.
Line 58: Line 55:
 * Get pico drive screens fixed (Miyo-kun)
Line 71: Line 67:
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-10-02

Main Assembly Sequence

  • Tidy up and cover things to prepare for SR2 crane slot work.
  • Replace BS service port covers.
  • Check for bubble level and other tools in tank.
  • Remove stickers on IP and clean with ethanol (some were missed last time).
  • Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
  • Check that all in-air cables are labeled.
  • Fix broken pico adapter cable?
  • If possible, reroute cable to eliminate need for with feedthrough.
  • Debug all electronics, especially actuation.
  • Check IP yaw.
  • Recheck centering of suspension in assembly frame.
  • Measure IP period; adjust ballast mass.
  • Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • Set all EQ stops to proper clearance.
  • Get ready for full TFs.

Software

  • Enter new IP matrices and do safe.snap.
  • Get pico drive screens fixed (Miyo-kun)
  • Update real-time model to number channels from #0.
  • Remove old OL stuff; add link to new OL stuff.
  • Remove unused screens.
  • Sort out SVN.

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Get clean bag laundered.
  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Lock washers for LBB dampers
    • Temporary ballast mass (dog clamps) in BF.
  • Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

Electrical

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.