Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
../ToDoOld | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] <<Anchor(EveryWeek)>> |
Line 6: | Line 14: |
=== Facilities (mostly full team) === * Clean up after floor work. |
=== Facilities === |
Line 11: | Line 18: |
* Get stuff from [[../WishList]] | |
Line 12: | Line 20: |
== 2017-04-24 == | <<Anchor(ComingWeeks)>> == 2017-09-11 == |
Line 14: | Line 23: |
=== Continue PI Prep === * Install LLB blades. * Install LLB blade units in PI. |
=== Main Assembly Sequence === * Debug BF LVDT actuation. * --(Debug other actuation.)-- * --(Remove F0-SF rod and reinstall with hex cable clamp.)-- * --(Route cables up past hex cable clamps.)-- * --(Adjust SF trim mass for pitch/roll/vertical.)-- * --(Route all SF/... cables through to the flange and test.)-- * --(Cable all PI items through to the flange.)-- * --(Disconnect the SS from the AF.)-- * --(Recheck/adjust SF/... yaw.)-- * --(Roughly level the PI so as to make the SS vertical.)-- * --(Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.)-- * Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate). * Test all PI items: * Yaw stepper. * F0 LVDT sensing * F0 LVDT actuation * --(Horizontal steppers)-- * Horizontal LVDT sensing * Horizontal LVDT actuation * --(Geophones)-- * Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS. * --(Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS.)-- 425 mHz * Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS. |
Line 18: | Line 48: |
=== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) === * Crane in PI. * Connect up SF/... . * Measure overweight if any. * Try removing some/all Cu dampers. * Remove PI again. * Do final trim of SF, fix LVDT if needed. * Crane PI back in. |
=== In parallel, time permitting === * --(Fix links to ADC_MONITOR screens.)-- * --(Check that all Take/Restore Safe.snap buttons work.)-- * --(Check that we still have all LBB parts (there was an issue with borrowed lock nuts).)-- * --(Wipe LLB damper parts with ethanol.)-- * --(Install LBB Cu damper ring in tank (less Cu for now).)-- * --(Apply magnets to LBB Magnet rings.)-- * --(Clean rust from screw holes in LBB magnet ring.)-- * Fix issue with geophone distributor. * Fix #1 geophone adapter cable (and replace borrowed one). * Fix broken pico adapter cable. * Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable. |
Line 27: | Line 61: |
=== Electronics (mostly Enzo, Mark) === * Debug SF LVDT. * Add retaining screws to cables at feedthroughs (mostly done, needs finishing). * Work with Miyo-kun to get pico drivers added to BS rack and screens * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) * Send list of required in-vacuum cables to Takahashi-san |
== 2017-09-19 == (No work Monday 9/18) === Main Assembly Sequence === * Double check BS pitch with OL. * Adjust SF damper ring to correct gap. * Install lock nuts on F0 GAS FR at TBD positions. * Lock BF and F0 keystones (but ''not'' SF keystone). * Lock RM to BS and IRM to IM. * Lock RM, IRM and BF (but not SF) to security structure. * Lock IP. * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw. * Attach lifting fixture. * Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * Attach lifting plates. * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20). * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Unlock suspension and readjust. * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). == Dates == * BUMAX countersunk screws for LBB Cu (by 9/20) * SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup) * LBB Cu segments: 9/19-20 <<Anchor(RealBSHang)>> == Tasks Not To Forget == === Major Tasks === * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) === Minor Tasks === ==== Mechanical ==== * Get clean bag laundered. * Put pointy-tipped screw in RM trolley for BS * Return/replace borrowed parts: * Lock washers for LBB dampers * Temporary ballast mass (dog clamps) in BF. * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. ==== Electrical ==== * Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 35: | Line 120: |
* Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata) * Count used, unused and broken in-vac cables and send data to Sato-san. == Real-time and SUMCON models (mostly Perry, Mark) == |
|
Line 42: | Line 123: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. |
* Design and install GAS drift compensation filters. |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-11
Main Assembly Sequence
- Debug BF LVDT actuation.
Debug other actuation.
Remove F0-SF rod and reinstall with hex cable clamp.
Route cables up past hex cable clamps.
Adjust SF trim mass for pitch/roll/vertical.
Route all SF/... cables through to the flange and test.
Cable all PI items through to the flange.
Disconnect the SS from the AF.
Recheck/adjust SF/... yaw.
Roughly level the PI so as to make the SS vertical.
Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.
- Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate).
- Test all PI items:
- Yaw stepper.
- F0 LVDT sensing
- F0 LVDT actuation
Horizontal steppers
- Horizontal LVDT sensing
- Horizontal LVDT actuation
Geophones
- Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS.
Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS. 425 mHz
- Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS.
In parallel, time permitting
Fix links to ADC_MONITOR screens.
Check that all Take/Restore Safe.snap buttons work.
Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
Wipe LLB damper parts with ethanol.
Install LBB Cu damper ring in tank (less Cu for now).
Apply magnets to LBB Magnet rings.
Clean rust from screw holes in LBB magnet ring.
- Fix issue with geophone distributor.
- Fix #1 geophone adapter cable (and replace borrowed one).
- Fix broken pico adapter cable.
- Figure out how to tighten PI yaw return spring or otherwise make yaw adjustment reliable.
2017-09-19
(No work Monday 9/18)
Main Assembly Sequence
- Double check BS pitch with OL.
- Adjust SF damper ring to correct gap.
- Install lock nuts on F0 GAS FR at TBD positions.
Lock BF and F0 keystones (but not SF keystone).
- Lock RM to BS and IRM to IM.
- Lock RM, IRM and BF (but not SF) to security structure.
- Lock IP.
- Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
- Attach lifting fixture.
- Remove BF- and SF-level crossbars.
- Remove geophones for craning.
- Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
- Attach lifting plates.
- Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
- Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
- Crane tank lid off.
- Crane LBB damper rings to top of tank and suspend.
- Crane suspension out of assembly frame.
- Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
- Crane suspension into tank and connect upper rods to LBB Cu ring.
- Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
- Install LBB lower rods and hook LBB.
- Measure required ballast for LBB.
- Unlock suspension and readjust.
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
Dates
- BUMAX countersunk screws for LBB Cu (by 9/20)
- SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup)
- LBB Cu segments: 9/19-20
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.