Line 1: Line 1:
= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
../ToDoOld [[../ToDoOldBS|Archived BS To-Do Items]]

[[../ToDoSR|SR To-Do Items]]

[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]

<<Anchor(EveryWeek)>>
Line 6: Line 14:
=== Facilities (mostly full team) ===
 * Clean up after floor work.
=== Facilities ===
Line 11: Line 18:
 * Get stuff from [[../WishList]]
Line 12: Line 20:
== 2017-04-24 == <<Anchor(ComingWeeks)>>
Line 14: Line 22:
=== Continue PI Prep ===
 * Install LLB blades.
 * Install LLB blade units in PI.
== 2017-10-02 ==
Line 18: Line 24:
=== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) ===
 * Crane in PI.
 * Connect up SF/... .
 * Measure overweight if any.
 * Try removing some/all Cu dampers.
 * Remove PI again.
 * Do final trim of SF, fix LVDT if needed.
 * Crane PI back in.
=== SR2 stuff ===
 * Replace BS service port covers, or reinforce foil with tape.
 * Cling-wrap or move:
  * White plastic table
  * Writing table
  * Tall metal table
Line 27: Line 31:
=== Electronics (mostly Enzo, Mark) ===
 * Debug SF LVDT.
 * Add retaining screws to cables at feedthroughs (mostly done, needs finishing).
 * Work with Miyo-kun to get pico drivers added to BS rack and screens
 * Update E1503600 with DIO card for HPCDs, etc, etc.
 * Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
 * Send list of required in-vacuum cables to Takahashi-san

=== Main Assembly Sequence ===
 * Check for bubble level and other tools in tank.
 * Remove stickers on IP and clean with ethanol (some were missed last time).
 * Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
 * Check that all in-air cables are labeled.
 * Fix broken pico adapter cable?
 * If possible, reroute cable to eliminate need for with feedthrough.
 * Debug all electronics, especially actuation.
 * Check IP yaw.
 * Recheck centering of suspension in assembly frame.
 * Measure IP period; adjust ballast mass.
 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
 * Get ready for full TFs.

=== Software ===
 * Enter new IP matrices and do safe.snap.
 * Get pico drive screens fixed (Miyo-kun)
 * Update real-time model to number channels from #0.

<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.

=== Minor Tasks ===
==== Mechanical ====
 * Get clean bag laundered.
 * Put pointy-tipped screw in RM trolley for BS
 * Return/replace borrowed parts:
  * Lock washers for LBB dampers
  * Temporary ballast mass (dog clamps) in BF.
 * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

==== Electrical ====
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

==== Real-time and SUMCON models ====
 * Create SUMCON models for full BS and major installation milestones.
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
Line 35: Line 76:
 * Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)
 * Count used, unused and broken in-vac cables and send data to Sato-san.

== Real-time and SUMCON models (mostly Perry, Mark) ==
Line 42: Line 79:
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.
 * Design and install GAS drift compensation filters.

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-10-02

SR2 stuff

  • Replace BS service port covers, or reinforce foil with tape.
  • Cling-wrap or move:
    • White plastic table
    • Writing table
    • Tall metal table

Main Assembly Sequence

  • Check for bubble level and other tools in tank.
  • Remove stickers on IP and clean with ethanol (some were missed last time).
  • Wipe rusty screws on IP LVDTs and surrounding area with ethanol-soaked wipe.
  • Check that all in-air cables are labeled.
  • Fix broken pico adapter cable?
  • If possible, reroute cable to eliminate need for with feedthrough.
  • Debug all electronics, especially actuation.
  • Check IP yaw.
  • Recheck centering of suspension in assembly frame.
  • Measure IP period; adjust ballast mass.
  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • Get ready for full TFs.

Software

  • Enter new IP matrices and do safe.snap.
  • Get pico drive screens fixed (Miyo-kun)
  • Update real-time model to number channels from #0.

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Get clean bag laundered.
  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Lock washers for LBB dampers
    • Temporary ballast mass (dog clamps) in BF.
  • Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

Electrical

  • Decide final in-vacuum and in-air cable routing (Enzo).
  • Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.