= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
../ToDoOld [[../ToDoOldBS|Archived BS To-Do Items]]

[[../ToDoSR|SR To-Do Items]]

[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]

<<Anchor(EveryWeek)>>
Line 6: Line 14:
=== Facilities (mostly full team) ===
 * Clean up after floor work.
=== Facilities ===
Line 11: Line 18:
 * Get stuff from [[../WishList]]
Line 12: Line 20:
== 2017-04-24 == <<Anchor(ComingWeeks)>>
Line 14: Line 22:
=== Continue PI Prep ===
 * Install LLB blades.
 * Install LLB blade units in PI.
== 2017-10-10 ==
Line 18: Line 24:
=== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) ===
 * Crane in PI.
 * Connect up SF/... .
 * Measure overweight if any.
 * Try removing some/all Cu dampers.
 * Remove PI again.
 * Do final trim of SF, fix LVDT if needed.
 * Crane PI back in.
=== Main Assembly Sequence ===
 * --(Account for second bubble level (might be on BF))--.
 * Borrow portable hard drive.
 * Clean up sticker residue and magic marker writing.
 * --(Remove LVDT modules; identify screws.)--
 * --(Check that all in-air cables are labeled)--.
 * If possible, reroute cable to eliminate need for fifth feedthrough.
 * --(Debug all electronics, especially actuation.)--
 * Measure IP period; adjust ballast mass.
 * Calibrate all LVDTs. --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
 * Set all EQ stops to TBD clearance.
 * --(Install small KOACH filters on LBB.)--
 * --(Remove First Contact.)--
 * --(Cable optical lever (Simon, Enzo))--
 * --(Align optical lever (Simon))--
 * Get ready for full TFs.
Line 27: Line 42:
=== Electronics (mostly Enzo, Mark) ===
 * Debug SF LVDT.
 * Add retaining screws to cables at feedthroughs (mostly done, needs finishing).
 * Work with Miyo-kun to get pico drivers added to BS rack and screens
 * Update E1503600 with DIO card for HPCDs, etc, etc.
 * Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
 * Send list of required in-vacuum cables to Takahashi-san
=== Etc ===
 * Move stuff out of PR2 area.
 * Tidy/label parts.
 * Move safety bars from BS AF area to SR2 area.
 * (Put up safety bars in SR3 area.)
 * Close hole in floor above BS AF area.

=== Software ===
 * --(Enter new IP matrices and do safe.snap.)--
 * Send stepper driver info to Miyo-kun.
 * Update real-time model to number channels from #0.
 * Remove old OL stuff; add link to new OL stuff.
 * Remove unused screens.
 * Sort out SVN.
 * --(Add support for comments to SUMCON.)--
 * Create SUMCON model with values commented.
 * Derive matrices for IP FRs.

=== Design ===
 * Finalize redesign of IP yaw adjuster.
 * Design better F0 FR adjuster.

<<Anchor(RealBSHang)>>
== Tasks Not To Forget ==
=== Major Tasks ===
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.

=== Minor Tasks ===
==== Mechanical ====
 * Put pointy-tipped screw in RM trolley for BS
 * Return/replace borrowed parts:
  * Temporary ballast mass (dog clamps) in BF.

==== Electrical ====

==== Real-time and SUMCON models ====
 * Create SUMCON models for full BS and major installation milestones.
 * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]).
Line 35: Line 83:
 * Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)
 * Count used, unused and broken in-vac cables and send data to Sato-san.

== Real-time and SUMCON models (mostly Perry, Mark) ==
Line 42: Line 86:
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.
 * Design and install GAS drift compensation filters.

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-10-10

Main Assembly Sequence

  • Account for second bubble level (might be on BF).

  • Borrow portable hard drive.
  • Clean up sticker residue and magic marker writing.
  • Remove LVDT modules; identify screws.

  • Check that all in-air cables are labeled.

  • If possible, reroute cable to eliminate need for fifth feedthrough.
  • Debug all electronics, especially actuation.

  • Measure IP period; adjust ballast mass.
  • Calibrate all LVDTs. BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • Set all EQ stops to TBD clearance.
  • Install small KOACH filters on LBB.

  • Remove First Contact.

  • Cable optical lever (Simon, Enzo)

  • Align optical lever (Simon)

  • Get ready for full TFs.

Etc

  • Move stuff out of PR2 area.
  • Tidy/label parts.
  • Move safety bars from BS AF area to SR2 area.
  • (Put up safety bars in SR3 area.)
  • Close hole in floor above BS AF area.

Software

  • Enter new IP matrices and do safe.snap.

  • Send stepper driver info to Miyo-kun.
  • Update real-time model to number channels from #0.
  • Remove old OL stuff; add link to new OL stuff.
  • Remove unused screens.
  • Sort out SVN.
  • Add support for comments to SUMCON.

  • Create SUMCON model with values commented.
  • Derive matrices for IP FRs.

Design

  • Finalize redesign of IP yaw adjuster.
  • Design better F0 FR adjuster.

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Temporary ballast mass (dog clamps) in BF.

Electrical

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.