== 2017-04-24 == | == 2017-05-09 == |
Line 15: | Line 15: |
* Install LLB blades. * Install LLB blade units in PI. |
* Find, install and wire up PI yaw stepper and bracket. * Decide pattern of LBB damper ring magnets. * Install magnets on LBB damper ring. * Wire up PI vertical fishing rod stepper. * Wire up PI horizontal fishing rod steppers. * Install and wire up geophones. |
Line 18: | Line 22: |
=== Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) === * Crane in PI. * Connect up SF/... . * Measure overweight if any. * Try removing some/all Cu dampers. |
=== Hanging SF/BF/IRM/IM/RM/BS === |
Line 24: | Line 24: |
* Install hex cable clamp on rod. | |
Line 25: | Line 26: |
* Remove Cu damper segment if necessary. * Lift PI and hang LBB damper ring. |
|
Line 26: | Line 29: |
* Re-hook SF/... section. | |
Line 27: | Line 31: |
=== Electronics (mostly Enzo, Mark) === | === Electronics === * Count used, unused, broken and needed in-vacuum cables and send data to Sato-san. |
Line 29: | Line 34: |
* Add retaining screws to cables at feedthroughs (mostly done, needs finishing). * Work with Miyo-kun to get pico drivers added to BS rack and screens * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) * Send list of required in-vacuum cables to Takahashi-san |
* Finish adding retaining screws to cables at feedthroughs. * Check connections in new geophone adapters and make unscrambler cables if necessary. * Decide final length for BS OSEM cables. |
Line 35: | Line 38: |
* Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata) * Count used, unused and broken in-vac cables and send data to Sato-san. |
|
Line 38: | Line 39: |
== Real-time and SUMCON models (mostly Perry, Mark) == | == Real-time and SUMCON models == |
Line 42: | Line 43: |
* Design and install GAS drift compensation filters. |
VIS Type B Near Term To-Do List
Every Week
Facilities (mostly full team)
- Clean up after floor work.
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
2017-05-09
Continue PI Prep
- Find, install and wire up PI yaw stepper and bracket.
- Decide pattern of LBB damper ring magnets.
- Install magnets on LBB damper ring.
- Wire up PI vertical fishing rod stepper.
- Wire up PI horizontal fishing rod steppers.
- Install and wire up geophones.
Hanging SF/BF/IRM/IM/RM/BS
- Remove PI again.
- Install hex cable clamp on rod.
- Do final trim of SF, fix LVDT if needed.
- Remove Cu damper segment if necessary.
- Lift PI and hang LBB damper ring.
- Crane PI back in.
- Re-hook SF/... section.
Electronics
- Count used, unused, broken and needed in-vacuum cables and send data to Sato-san.
- Debug SF LVDT.
- Finish adding retaining screws to cables at feedthroughs.
- Check connections in new geophone adapters and make unscrambler cables if necessary.
- Decide final length for BS OSEM cables.
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
Real-time and SUMCON models
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.