1967
Comment:
|
3462
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
../ToDoOld | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] <<Anchor(EveryWeek)>> |
Line 10: | Line 18: |
* Get stuff from [[../WishList]] | |
Line 11: | Line 20: |
== 2017-05-15 == | <<Anchor(ComingWeeks)>> |
Line 13: | Line 22: |
== Facilities == * Clear spaces for PR2 bellows work and SR2 ladder installation on 5/15. * Fix safety bar on -X side of assembly frame (move to other side of pillars and attach more securely). |
== ASAP == * Get picomotor drivers back on line. * Debug BS BIO connections, especially PI IP. |
Line 17: | Line 26: |
== Design/Purchasing == * Order longer threaded rods for arc weights on PI. * Design, order modifications to LBB blade springs. |
=== Main Assembly Sequence === * Necessary for phase-I★★★ * --(Modify IP LVDT damping filters to include set point.)-- * --(TFs.)-- * '''''EXCHANGE YAW/VERT FRs at F0''''' |
Line 21: | Line 32: |
=== Main Assembly === * Remove PI. * Fix jammed PI-SF rod. * Remove SF cap. * Remove blades from LBB blade units and send off for rework. * Install remaining cable clamps on PI. * Remove one Cu damper segment from SF cap and reconfigure remaining two to be symmetrical. * Decide pattern of SF damper ring magnets (72 pieces in 2/3 of the original ring). * Install magnets on SF damper ring. * Lift PI and hang LBB damper ring. * Crane PI back in. * Install rod, this time with hex cable clamp. * Re-hook SF/... section. * Install geophones. |
* Necessary for phase-II★★ * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553) * Design PI Sensor blending filter. * Re-calibrate F0 GAS LVDT * Tune the LVDT sensitivity * Measure IP period; adjust ballast mass. |
Line 36: | Line 39: |
=== Electronics === * Debug and calibrate SF LVDT. * Put connector on PI vertical LVDT wires per E1503600-v13 Sheet 5. * Make PI vertical/yaw stepper in-air adapter cable per E1503600-v13 Sheet 7. * Make (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8. * Complete cabling of PI stuff (steppers, LVDTs, geophones) through to rack and test. |
* At some point (remotely)★ * Improve OL offloading. * Improve GAS offloading. * Spectral analysis of Oplev. * Design, install angular lock servo using OL. (Almost done for phase-I) * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I) * Subtract DC level of Geophones. * Spectra analysis of PI sensors (PI LVDTs and Geophones). * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * Set all EQ stops to TBD clearance. * Modify the model for IP coil driver control |
Line 43: | Line 51: |
* Decide final length for BS OSEM cables. | === Documentation and Operation Manual === * Add useful info from Enzo's notebook to BSData. <<Anchor(RealBSHang)>> == Tasks Not To Forget == === Major Tasks === * Move safety bars from BS AF area to SR2 area. * Update circuit diagram. * (Time permitting) Try adding mass to IP. * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Figure out how to make PI yaw adjustment reliable. === Minor Tasks === ==== Mechanical ==== * Put pointy-tipped screw in RM trolley for BS * Return/replace borrowed parts: * Temporary ballast mass (dog clamps) in BF. <<Anchor(elec)>> ==== Electrical ==== * Update BS Circuit diagram, D1503600 * --(Note removal of LED/PD on TM OSEMs.)-- * Include information on assignment of channels to feedthrough positions. * Reflect gender-changers and non-flipping feedthrough adapters. * Reflect actual cable lengths. * Include LVDT pin size (1 mm). * Include Stepper pin size (1.6 mm). * --(Undo renumbering of IP items.)-- * --(Page 10: "DIO Card # 0" should be "DIO Card # 1")-- * --(Include OutConfigBoards on OL page (Sheet 18).)-- * Update HPCD section to reflect: * All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13. * Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15. ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 45: | Line 90: |
== Real-time and SUMCON models == |
|
Line 50: | Line 93: |
* Design and install GAS drift compensation filters. * Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
ASAP
- Get picomotor drivers back on line.
- Debug BS BIO connections, especially PI IP.
Main Assembly Sequence
- Necessary for phase-I★★★
Modify IP LVDT damping filters to include set point.
TFs.
EXCHANGE YAW/VERT FRs at F0
- Necessary for phase-II★★
Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
- Design PI Sensor blending filter.
- Re-calibrate F0 GAS LVDT
- Tune the LVDT sensitivity
- Measure IP period; adjust ballast mass.
- At some point (remotely)★
- Improve OL offloading.
- Improve GAS offloading.
- Spectral analysis of Oplev.
- Design, install angular lock servo using OL. (Almost done for phase-I)
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
- Subtract DC level of Geophones.
- Spectra analysis of PI sensors (PI LVDTs and Geophones).
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- Set all EQ stops to TBD clearance.
- Modify the model for IP coil driver control
Documentation and Operation Manual
- Add useful info from Enzo's notebook to BSData.
Tasks Not To Forget
Major Tasks
- Move safety bars from BS AF area to SR2 area.
- Update circuit diagram.
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Temporary ballast mass (dog clamps) in BF.
Electrical
- Update BS Circuit diagram, D1503600
Note removal of LED/PD on TM OSEMs.
- Include information on assignment of channels to feedthrough positions.
- Reflect gender-changers and non-flipping feedthrough adapters.
- Reflect actual cable lengths.
- Include LVDT pin size (1 mm).
- Include Stepper pin size (1.6 mm).
Undo renumbering of IP items.
Page 10: "DIO Card # 0" should be "DIO Card # 1"
Include OutConfigBoards on OL page (Sheet 18).
- Update HPCD section to reflect:
- All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.
- Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.