2160
Comment:
|
3905
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
../ToDoOld | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] <<Anchor(EveryWeek)>> |
Line 10: | Line 18: |
* Get stuff from [[../WishList]] | |
Line 11: | Line 20: |
== 2017-05-15 == | <<Anchor(ComingWeeks)>> == 2017-09-04 == |
Line 13: | Line 23: |
== Facilities == * --(Clear spaces for PR2 bellows work and SR2 ladder installation on 5/15.)-- * --(Fix safety bar on -X side of assembly frame (move to other side of pillars and attach more securely).)-- |
=== Main Assembly Sequence === * Crane out SF. * Raise BF cap and retrieve lost hex cable clamp PEEK piece. * Crane in SF. * Install SF-BF rod with hex cable clamp. * Route cables via hex cable clamp up to below SF. * Adjust BF ballast mass for total weight and pitch/roll. * Look for missing screw from SF damper Cu segment in washed screws bag and reinstall. * Calibrate SF LVDT. * Install SF main ballast mass. * Cable and test SF fishing rod stepper. * Add SF cap. * Lift and weigh SF/... section. |
Line 17: | Line 38: |
== Design/Purchasing == * Order longer threaded rods for arc weights on PI. * Design, order modifications to LBB blade springs. * Get more UHV foil. * Get more cable ties. * Get more duckboards. |
=== In parallel, time permitting === * Rearrange arc weights on PI to allow installation of magic wand. * Check that we still have all LBB parts (there was an issue with borrowed lock nuts). * Rearrange magnets on SF damper magnet ring for full three Cu segments. * Find Ni-plated rods for SF damper magnet ring and do fit check. * Find PI-SF rod with 8 mm heads and matching receptacles and do fit check. * Lay more new in-air cabling. * Wipe LLB damper parts with ethanol. * Get Cu O-rings for feedthroughs. * Figure out how to tighten PI yaw return spring. |
Line 24: | Line 49: |
=== Main Assembly === * --(Secure arc weights with M8 nuts.)-- * --(Remove PI.)-- * --(Unjam PI-SF rod.)-- * --(Remove SF cap.)-- * --(Remove blades from LBB blade units)-- and send off for rework. * Install remaining cable clamps on PI. * --(Remove one Cu damper segment from SF cap and reconfigure remaining two to be symmetrical.)-- * --(Decide pattern of SF damper ring magnets (72 pieces in 2/3 of the original ring).)-- * --(Install magnets on SF damper ring.)-- * Lift PI and hang LBB damper ring. * Crane PI back in. * Install rod, this time with hex cable clamp. * Re-hook SF/... section. * Install geophones. |
<<Anchor(RealBSHang)>> == Tasks Not To Forget == === Major Tasks === * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
Line 40: | Line 59: |
=== Electronics === * Debug and calibrate SF LVDT. * Debug stepper motors. * Put connector on PI vertical LVDT wires per E1503600-v13 Sheet 5. * Make PI vertical/yaw stepper in-air adapter cable per E1503600-v13 Sheet 7. * Make (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8. * Complete cabling of PI stuff (steppers, LVDTs, geophones) through to rack and test. * Review cable spreadsheet; send to Sato-san. |
=== Minor Tasks === ==== Mechanical ==== * Get clean bag laundered. * Put pointy-tipped screw in RM trolley for BS * Return/replace borrowed parts: * Lock washers for LBB dampers * Temporary ballast mass (dog clamps) in BF. * --(Wide-mouth OSEMs from RM to Akutsu-san)-- * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. ==== Electrical ==== * Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). --(BF)--, SF, PI-GAS, PI-H1, PI-H2, PI-H3 * --(Remove cling wrap in BF and install vacuum-compatible heat shrink.)-- * --(Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).)-- * --(Rewire PI horizontal steppers with vacuum-compatible cable)--. * --(Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).)-- * Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 49: | Line 85: |
== Real-time and SUMCON models == |
|
Line 55: | Line 89: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. |
* --(Create a proper DAC Monitor MEDM screen.)-- * --(Improve ADC Monitor MEDM screen.)-- |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-04
Main Assembly Sequence
- Crane out SF.
- Raise BF cap and retrieve lost hex cable clamp PEEK piece.
- Crane in SF.
- Install SF-BF rod with hex cable clamp.
- Route cables via hex cable clamp up to below SF.
- Adjust BF ballast mass for total weight and pitch/roll.
- Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.
- Calibrate SF LVDT.
- Install SF main ballast mass.
- Cable and test SF fishing rod stepper.
- Add SF cap.
- Lift and weigh SF/... section.
In parallel, time permitting
- Rearrange arc weights on PI to allow installation of magic wand.
- Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
- Rearrange magnets on SF damper magnet ring for full three Cu segments.
- Find Ni-plated rods for SF damper magnet ring and do fit check.
- Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.
- Lay more new in-air cabling.
- Wipe LLB damper parts with ethanol.
- Get Cu O-rings for feedthroughs.
- Figure out how to tighten PI yaw return spring.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Calibrate PI vertical LVDT.
- Set yoke on PI vertical LVDT (if necessary).
- Calibrate PI horizontal LVDTs.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
Wide-mouth OSEMs from RM to Akutsu-san
Adjust height of crossbars below BF.
If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
Remove cling wrap in BF and install vacuum-compatible heat shrink.
Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
Rewire PI horizontal steppers with vacuum-compatible cable.
Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).
- Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
Create a proper DAC Monitor MEDM screen.
Improve ADC Monitor MEDM screen.