VIS Type B Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
2017-05-22
Facilities
Design/Purchasing
- Order longer threaded rods for arc weights on PI.
- Design, order modifications to LBB blade springs.
- Get more cable ties.
- Get more duckboards.
Main Assembly
- Lift PI and hang LBB damper ring.
- Crane PI back in.
- Install rod, this time with hex cable clamp.
- Re-hook SF/... section.
- Install geophones.
Electronics
- Debug and calibrate SF LVDT.
- Debug stepper motors.
- Put connector on PI vertical LVDT wires per E1503600-v13 Sheet 5.
- Make two more (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8.
- Complete cabling of PI stuff (steppers, LVDTs, geophones) through to rack and test.
- Send cable spreadsheet to Sato-san.
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
Real-time and SUMCON models
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.