1519
Comment:
|
5826
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
../ToDoOld | [[../ToDoOld|Archived To-Do Items]] [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] [[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] <<Anchor(EveryWeek)>> |
Line 10: | Line 20: |
* Get stuff from [[../WishList]] | |
Line 11: | Line 22: |
== 2017-05-29 == | <<Anchor(ComingWeeks)>> == 2017-08-16 == === Facilities === * --(Move cardboard box with old BF to storage.)-- * --(Tidy up Hirata-san's stuff in genkan of cleanbooth.)-- |
Line 13: | Line 28: |
== Facilities == | === Design/Documentation/Planning === * LBB ballast mass. * Research real payload. * Do improved mass budget. * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. |
Line 15: | Line 34: |
== Design/Purchasing == * Order longer threaded rods for arc weights on PI. * Get more cable ties. * Get another D-Sub breakout. |
=== Electronics === * --(Return spare two Type5-2.2 cables to Sato-san's store.)-- * Recable/test BF LVDT. * --(Rip out remaining old in-air cabling.)-- * Lay new in-air cabling. * Reinstall LVDT chassis. |
Line 21: | Line 42: |
=== Electronics === * Route BF/... cabling up past SF to PI. * Route SF cabling up to PI. * Add Type 3 extensions to SF/... cables. * Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame). * Move in-air cabling to match flange positions. * Cable and test PI vertical LVDT. |
* Do final trim of IM/RM/TM. * Remove LBB blade assemblies from PI. * Remove LBB blades from holders. * Remove LBB rings. * Send rings for recleaning. === Time permitting === <<Anchor(RealBSHang)>> == Real BS Hang Tasks == === Major Tasks === * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. |
Line 30: | Line 66: |
* Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. |
|
Line 36: | Line 68: |
== Real-time and SUMCON models == * Check PI section of k1visbs model. |
=== Minor Tasks === ==== Mechanical ==== * Get clean bag laundered. * Put pointy-tipped screw in RM trolley for BS * --(Swap out temporary ballast mass in BF)--, SF. * Return/replace borrowed parts: * Lock washers for LBB dampers * Temporary ballast mass (dog clamps) in BF. * Wide-mouth OSEMs from RM to Akutsu-san * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. * --(Check inside SF for lost ruler.)-- * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. ==== Electrical ==== * Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). ==== Real-time and SUMCON models ==== * Create SUMCON models for full BS and major installation milestones. * Create controls design description (cf [[https://dcc.ligo.org/LIGO-T1100378/public|LIGO-T1100378]]). |
Line 45: | Line 102: |
<<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). ==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-08-16
Facilities
Move cardboard box with old BF to storage.
Tidy up Hirata-san's stuff in genkan of cleanbooth.
Design/Documentation/Planning
- LBB ballast mass.
- Research real payload.
- Do improved mass budget.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
Electronics
Return spare two Type5-2.2 cables to Sato-san's store.
- Recable/test BF LVDT.
Rip out remaining old in-air cabling.
- Lay new in-air cabling.
- Reinstall LVDT chassis.
Main Assembly
- Do final trim of IM/RM/TM.
- Remove LBB blade assemblies from PI.
- Remove LBB blades from holders.
- Remove LBB rings.
- Send rings for recleaning.
Time permitting
Real BS Hang Tasks
Major Tasks
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Final ballast mass production for BF and SF (Hirata-san). (have quotes)
- Design of receptacles for rods with 8 mm heads.
- Possible rebuild of BF and/or SF
- Set up build/test stand for filters.
- Get filter test weights.
- Find spare BF blade(s).
- Reclean stuff:
- PI (remove Kapton tape etc, etc).
- LLB damper stuff, especially Cu segments.
- Calibrate PI vertical LVDT.
- Set yoke on PI vertical LVDT (if necessary).
- Calibrate PI horizontal LVDTs.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
Swap out temporary ballast mass in BF, SF.
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Wide-mouth OSEMs from RM to Akutsu-san
Adjust height of crossbars below BF.
If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Check inside SF for lost ruler.
- Tighten PI yaw return spring.
- Get Cu O-rings for feedthroughs.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
- Calibrate all LVDTs (Enzo, Mark).
- Remove cling wrap in BF and install vacuum-compatible heat shrink.
- Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
- Rewire PI horizontal steppers with vacuum-compatible cable.
- Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.
SR Prep Tasks
Design/Purchasing
- Do rough mass budget for SR2/SR3/SRM.
- Design SR assembly frame.
- Design final SF ballast masses (Fabian).
Order now
Bread boards for SR -> すぐ見積り依頼
- Include installation work in the contract
- Total budget = 5MJPY
PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼
Need simple design changes
- SUS wires(3 types) for the LBB
Change the length -> すぐ見積り依頼
- Receptacles for Bread board damper
- There is a mistake in the PROMEC drawing.
- Hirata-san will make a new 2D drawing
- IM wire clamps for SR
- Need to change the height
SR assembly frame -> 月曜日に見積り依頼
- Mark is checking the design from Fabian
- We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame
Need Fabian's input
Cable clamps for BF,SF and PI -> 方式を決める
- Design change for the PI clamps, because the SR PIs are NIKHEF ones.
- Ballast masses for BF and SF
- 製作に2週間程度
- 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
測定に必要な物品の準備 -> 月曜日に高橋さんと相談
Need more discussion/checks
- Blade spring assembly for LBB
- Check the load of the LBB and decide the design load of the springs
- Correct the length
Scale the width of the current blades to design the new blades -> 高橋さんと相談
- SR用LBBの重さを確認
- Bread board damper rings
Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認
Electronics
- Get cables/cards for SR3:
- 5 DSub-37 cables (tent)
- 5 DSub-15M to DSub-9M adapter cables (tent)
- 3 DIO cards (tent)
- 2 DSub-9 FF gender benders (for LVDTs)
- extra ADC card(s)?
- extra DAC card(s)?
- BNC-LEMO adapter (for LVDTs)
- etc