Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] |
Line 5: | Line 5: |
[[#RealBSHang|Preparation for Real BS Hang]] | [[../ToDoSR|SR To-Do Items]] |
Line 7: | Line 7: |
[[#SRPrepTasks|Preparation for SR Installation]] | [[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] <<Anchor(EveryWeek)>> |
Line 14: | Line 18: |
* Get stuff from [[../WishList]] | |
Line 15: | Line 20: |
== Coming Week (2017-06-19) == === Facilities === * Remove cling wrap from stuff. * Plug stuff back in (charging station, KOACH filters, OL etc). * Power up rack. |
<<Anchor(ComingWeeks)>> |
Line 21: | Line 22: |
=== Main Assembly === * Unlock BF keystone and try running BF fishing rod to fix sag problem (Enzo, Mark). * Do up all EQ stops etc (except SF). * Remove geophones (temporarily, for craning). * Crane suspension into tank. * Hook LBB Cu ring. * Hook LBB. * Crane vacuum tank lid+ring black on. * Remove vacuum tank lid (only). * Add ballast to LBB. |
== 2017-10-16 == |
Line 32: | Line 24: |
=== Electronics === * Disconnect in-vacuum and in-air cabling from feedthroughs. * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring. * Adjust in-air cabling to match 135° rotation of BS. * Reconnect in-air cables. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
=== Main Assembly Sequence === * --(Borrow portable hard drive.)-- * --(Remove sticker residue and permanent marker writing on PI.)-- * --(Fix broken and unreliable connections on IP LVDTs.)-- * --(Reconfigure the stepper motor cables for Miyo-kun.)-- * Wipe any rust from around IP LVDTs. * (If Enzo thinks it necessary and there's time) adjust IP LVDT mechanical offsets to maximize usable range and recalibrate. * --(Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.)-- * Calibrate IP LVDT actuation against IP LVDT sensing. * --(Install damping filters for IP LVDTs.)-- * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. * Modify IP LVDT damping filters to include set point. * --(Install and debug IP LVDT and geophone diagonalization matrices.)-- * (Time permitting) Try adding mass to IP. * Work with alignment team. * Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed) * Work with Miyo-kun to get user interface for stepper motors. * --(Calibrate IP FR actuation against IP LVDT sensing.)-- * SR procurement. * --(Lower LBB by 17.5 mm; suspend and rebalance after removing table KOACH filters.)-- * --(Reroute cable to eliminate need for fifth feedthrough.)-- * Set all EQ stops to TBD clearance. * Measure IP period; adjust ballast mass. * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * TFs. |
Line 41: | Line 50: |
=== Real-time and SUMCON models === * Derive and install PI LVDT matrices. * Check LSOL section of k1visbs model. |
=== Etc === * Move stuff out of PR2 area. * Tidy/label parts. * Move safety bars from BS AF area to SR2 area. * (Put up safety bars in SR3 area.) * Close hole in floor above BS AF area. === Software === * --(Enter new IP matrices and do safe.snap.)-- * --(Send stepper driver info to Miyo-kun)--. * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. * --(Add support for comments to SUMCON.)-- * Create SUMCON model with values commented. * --(Derive matrices for IP FRs.)-- === Design === * Finalize redesign of IP yaw adjuster. * Design better F0 FR adjuster. |
Line 46: | Line 73: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 48: | Line 75: |
* Final ballast mass design/production for BF and SF (Fabian, Hirata-san). * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * Possible rebuild of BF and/or SF * Set up filter build/test stand. * Get filter test weights. * Find spare BF blade(s). * Prepare real BS: * Coordinate with Hirose-san. * Book transport of mirror (Kashiwa to KAGRA) * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs. * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san). * Organize cleanroom gear for Kashiwa trip(s). * Put magnets in flags. * Glue flags/prisms at Kashiwa. * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Figure out how to make PI yaw adjustment reliable. |
Line 68: | Line 81: |
* Swap out temporary ballast mass in BF, SF. | * Put pointy-tipped screw in RM trolley for BS |
Line 70: | Line 83: |
* Lock washers for LBB dampers | |
Line 72: | Line 84: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. * Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 82: | Line 86: |
* Get pico drive screens fixed (Miyo-kun) * Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
|
Line 98: | Line 95: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Get another D-Sub breakout (Hirata). * Design final SF ballast masses (Fabian). * Finish/post assembly drawing for LBB and LBB damper ring (Hirata). * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata). * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-16
Main Assembly Sequence
Borrow portable hard drive.
Remove sticker residue and permanent marker writing on PI.
Fix broken and unreliable connections on IP LVDTs.
Reconfigure the stepper motor cables for Miyo-kun.
- Wipe any rust from around IP LVDTs.
- (If Enzo thinks it necessary and there's time) adjust IP LVDT mechanical offsets to maximize usable range and recalibrate.
Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.
- Calibrate IP LVDT actuation against IP LVDT sensing.
Install damping filters for IP LVDTs.
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
- Modify IP LVDT damping filters to include set point.
Install and debug IP LVDT and geophone diagonalization matrices.
- (Time permitting) Try adding mass to IP.
- Work with alignment team.
- Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed)
- Work with Miyo-kun to get user interface for stepper motors.
Calibrate IP FR actuation against IP LVDT sensing.
- SR procurement.
Lower LBB by 17.5 mm; suspend and rebalance after removing table KOACH filters.
Reroute cable to eliminate need for fifth feedthrough.
- Set all EQ stops to TBD clearance.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- TFs.
Etc
- Move stuff out of PR2 area.
- Tidy/label parts.
- Move safety bars from BS AF area to SR2 area.
- (Put up safety bars in SR3 area.)
- Close hole in floor above BS AF area.
Software
Enter new IP matrices and do safe.snap.
Send stepper driver info to Miyo-kun.
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
Add support for comments to SUMCON.
- Create SUMCON model with values commented.
Derive matrices for IP FRs.
Design
- Finalize redesign of IP yaw adjuster.
- Design better F0 FR adjuster.
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Temporary ballast mass (dog clamps) in BF.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.