Differences between revisions 66 and 209 (spanning 143 versions)
Revision 66 as of 2017-06-21 11:43:49
Size: 5773
Editor: MarkBarton
Comment:
Revision 209 as of 2018-11-21 19:00:39
Size: 4208
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
[[../ToDoOld|Archived To-Do Items]] [[../ToDoOldBS|Archived BS To-Do Items]]

[[../ToDoSR|SR To-Do Items]]
Line 8: Line 10:

[[#RealBSHang|Preparation for Real BS Hang]]

[[#SRPrepTasks|Preparation for SR Installation]]
Line 22: Line 20:
== December 2018 vent ==
 * Look for cracks in F0 blades.
 * Install new yaw F0 stepper mechanism (if available).
 * Install new double-sided F0 fishing rod (have all parts except blades).
 * Add more mass to IP to get a lower frequency.
 * Service geophones (one has high noise, one has DC offset).
 * Re-calibrate F0 GAS LVDT.
 * Confirm the positions of the IP LVDTs and Actuators.
 * Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).
Line 23: Line 31:
== Coming Weeks (2017-06-19, 2017-06-26) ==
=== Facilities ===
 * --(Remove cling wrap from stuff.)--
 * --(Plug stuff back in (charging station, KOACH filters, OL etc).)--
 * --(Power up rack.)--
Line 29: Line 32:
=== Design/Documentation ===
 * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian).
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).
 * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).
== ASAP ==
 * --(Get picomotor drivers back on line.)--
 * --(Debug BS BIO connections, especially PI IP.)--
Line 35: Line 36:
=== Main Assembly ===
 * --(Remove crossbars below BF and SF.)--
 * --(Set SF damper to 4 mm clearance.)--
 * Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).
 * --(Adjust jacks to nominal height.)--
 * Unlock BF keystone and try running BF fishing rod to fix sag problem (Enzo, Mark).
 * --(Do up all EQ stops etc (except SF).)--
 * --(Remove geophones (temporarily, for craning).)--
 * --(Crane suspension into tank.)--
 * --(Hook LBB Cu ring.)--
 * Hook LBB.
 * Crane vacuum tank lid+ring back on.
 * Remove vacuum tank lid (only) and store on pallet.
 * Add ballast to LBB.
 * Replace geophones.
 * Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks.
 * Unlock IP and adjust to center with jacks.
 * Adjust pitch/yaw/vertical of dummy optic.
 * Start TFs.
=== Main Assembly Sequence ===
 * Necessary for phase-I★★★
  * --(Modify IP LVDT damping filters to include set point.)--
  * --(TFs.)--
  * '''''EXCHANGE YAW/VERT FRs at F0'''''
Line 55: Line 42:
=== Electronics ===
 * Get pico drive screens fixed (Miyo-kun)
 * Order final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
 * --(Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).)--
 * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
 * Reconnect in-vacuum cabling.
 * Adjust in-air cabling to match 135° rotation of BS.
 * Reconnect in-air cables.
 * Calibrate PI vertical LVDT.
 * Set yoke on PI vertical LVDT (if necessary).
 * Calibrate PI horizontal LVDTs.
 * Necessary for phase-II★★
  * Debug BS geophones.
  * Flip circuit boards in BS geophones to make them the same as SRx.
  * Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)
  * Design PI Sensor blending filter.
  * Tune the LVDT sensitivity
  * Measure IP period; adjust ballast mass.
Line 67: Line 50:
=== LSOL ===
 * Assist Simon with hardware installation of LSOL (week of 6/26?).
 * Assist Simon with modifications to realtime model for LSOL (week of 6/26?).
 * At some point (remotely)★
  * Improve OL offloading.
  * Improve GAS offloading.
  * Spectral analysis of Oplev.
  * Design, install angular lock servo using OL. (Almost done for phase-I)
  * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
  * Subtract DC level of Geophones.
  * Spectra analysis of PI sensors (PI LVDTs and Geophones).
  * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  * Set all EQ stops to TBD clearance.
  * Modify the model for IP coil driver control
Line 71: Line 62:
=== Real-time and SUMCON models ===
 * Derive and install PI LVDT matrices.
 * Check LSOL section of k1visbs model.
=== Documentation and Operation Manual ===
 * Add useful info from Enzo's notebook to BSData.
Line 76: Line 66:
== Real BS Hang Tasks == == Tasks Not To Forget ==
Line 78: Line 68:
 * Final ballast mass design/production for BF and SF (Fabian, Hirata-san).
 * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
 * Possible rebuild of BF and/or SF
  * Set up build/test stand for filters.
  * Get filter test weights.
  * Find spare BF blade(s).
 * Prepare real BS:
  * Coordinate with Hirose-san.
  * Book transport of mirror (Kashiwa to KAGRA)
  * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs.
  * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san).
  * Organize cleanroom gear for Kashiwa trip(s).
  * Put magnets in flags.
  * Glue flags/prisms at Kashiwa.
 * Reclean stuff:
  * PI (remove Kapton tape etc, etc).
  * LLB damper stuff, especially Cu segments.
 * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata).
 * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata).
 * --(Move safety bars from BS AF area to SR2 area.)--
 * Update circuit diagram.
 * (Time permitting) Try adding mass to IP.
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.
Line 100: Line 77:
 * Get clean bag laundered.
 * Swap out temporary ballast mass in BF, SF.
 * Return/replace borrowed parts:
  * Lock washers for LBB dampers
  * Temporary ballast mass (dog clamps) in BF.
  * Wide-mouth OSEMs from RM to Akutsu-san
 * Adjust height of crossbars below BF.
 * If possible, fix galled pole in BF level of EQ stop.
 * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
 * Check inside SF for lost ruler.
 * Tighten PI yaw return spring.
 * Get Cu O-rings for feedthroughs.
 * Put pointy-tipped screw in RM trolley for BS
 * --(Return/replace temporary ballast mass (dog clamps).)--
 * Characterize replacement F0.
 * --(Wipe/clean arc weights that were rained on.)--
Line 113: Line 82:
<<Anchor(elec)>>
Line 114: Line 84:
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark).
 * Remove cling wrap in BF and install vacuum-compatible heat shrink.
 * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
 * Rewire PI horizontal steppers with vacuum-compatible cable.
 * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
 * Update BS Circuit diagram, D1503600
  * --(Note removal of LED/PD on TM OSEMs.)--
  * Organize stepper reset system and watchdog BIO.
  * Include information on assignment of channels to feedthrough positions.
  * Reflect gender-changers and non-flipping feedthrough adapters.
  * Reflect actual cable lengths.
  * Include LVDT pin size (1 mm).
  * Include Stepper pin size (1.6 mm).
  * --(Undo renumbering of IP items.)--
  * --(Page 10: "DIO Card # 0" should be "DIO Card # 1")--
  * --(Include OutConfigBoards on OL page (Sheet 18).)--
  * --(Update HPCD section to reflect:)--
   * --(All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.)--
   * --(Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.)--
Line 128: Line 106:
 * Design and install GAS drift compensation filters.
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks ==
=== Design/Purchasing ===
 * Do rough mass budget for SR2/SR3/SRM.
 * Design SR assembly frame.
 * Design final SF ballast masses (Fabian).

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

December 2018 vent

  • Look for cracks in F0 blades.
  • Install new yaw F0 stepper mechanism (if available).
  • Install new double-sided F0 fishing rod (have all parts except blades).
  • Add more mass to IP to get a lower frequency.
  • Service geophones (one has high noise, one has DC offset).
  • Re-calibrate F0 GAS LVDT.
  • Confirm the positions of the IP LVDTs and Actuators.
  • Tune LBB (adjust table height, damper height) - DON'T BOTHER (unless there's an excuse to open the lower half of the tank).

ASAP

  • Get picomotor drivers back on line.

  • Debug BS BIO connections, especially PI IP.

Main Assembly Sequence

  • Necessary for phase-I★★★
    • Modify IP LVDT damping filters to include set point.

    • TFs.

    • EXCHANGE YAW/VERT FRs at F0

  • Necessary for phase-II★★
    • Debug BS geophones.
    • Flip circuit boards in BS geophones to make them the same as SRx.
    • Calibrate IP LVDT actuation against IP LVDT sensing. (Klog 3553? http://klog.icrr.u-tokyo.ac.jp/osl/?r=3553)

    • Design PI Sensor blending filter.
    • Tune the LVDT sensitivity
    • Measure IP period; adjust ballast mass.
  • At some point (remotely)★
    • Improve OL offloading.
    • Improve GAS offloading.
    • Spectral analysis of Oplev.
    • Design, install angular lock servo using OL. (Almost done for phase-I)
    • Adjust gains and debug damping for IM OSEMs and GAS LVDTs. (Almost done for phase-I)
    • Subtract DC level of Geophones.
    • Spectra analysis of PI sensors (PI LVDTs and Geophones).
    • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
    • Set all EQ stops to TBD clearance.
    • Modify the model for IP coil driver control

Documentation and Operation Manual

  • Add useful info from Enzo's notebook to BSData.

Tasks Not To Forget

Major Tasks

  • Move safety bars from BS AF area to SR2 area.

  • Update circuit diagram.
  • (Time permitting) Try adding mass to IP.
  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace temporary ballast mass (dog clamps).

  • Characterize replacement F0.
  • Wipe/clean arc weights that were rained on.

Electrical

  • Update BS Circuit diagram, D1503600
    • Note removal of LED/PD on TM OSEMs.

    • Organize stepper reset system and watchdog BIO.
    • Include information on assignment of channels to feedthrough positions.
    • Reflect gender-changers and non-flipping feedthrough adapters.
    • Reflect actual cable lengths.
    • Include LVDT pin size (1 mm).
    • Include Stepper pin size (1.6 mm).
    • Undo renumbering of IP items.

    • Page 10: "DIO Card # 0" should be "DIO Card # 1"

    • Include OutConfigBoards on OL page (Sheet 18).

    • Update HPCD section to reflect:

      • All three GAS channels are on HPCD #1 and DIO Card #2, CNB cables, Sheet 13.

      • Three IP channels are on HPCD #0 and DIO Card #2, CNA cables, Sheet 15.

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)