Differences between revisions 68 and 149 (spanning 81 versions)
Revision 68 as of 2017-06-23 13:34:52
Size: 5844
Editor: MarkBarton
Comment:
Revision 149 as of 2017-09-25 08:14:23
Size: 3240
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
[[../ToDoOld|Archived To-Do Items]] [[../ToDoOldBS|Archived BS To-Do Items]]

[[../ToDoSR|SR To-Do Items]]
Line 8: Line 10:

[[#RealBSHang|Preparation for Real BS Hang]]

[[#SRPrepTasks|Preparation for SR Installation]]
Line 23: Line 21:
== Coming Weeks (2017-06-19, 2017-06-26) ==
=== Facilities ===
 * --(Remove cling wrap from stuff.)--
 * --(Plug stuff back in (charging station, KOACH filters, OL etc).)--
 * --(Power up rack.)--
Line 29: Line 22:
=== Design/Documentation ===
 * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian).
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).
 * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).
== 2017-09-25 ==
Line 35: Line 24:
=== Main Assembly ===
 * --(Remove crossbars below BF and SF.)--
 * --(Set SF damper to 4 mm clearance.)--
 * --(Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).)--
 * --(Adjust jacks to nominal height.)--
 * --(Do up all EQ stops etc (except SF).)--
 * --(Remove geophones (temporarily, for craning).)--
 * --(Crane suspension into tank.)--
 * --(Hook LBB Cu ring.)--
 * --(Hook LBB.)--
 * --(Crane vacuum tank lid+ring back on.)--
 * --(Remove vacuum tank lid (only) and store on pallet.)--
 * --(Add ballast to LBB.)--
 * --(Replace geophones.)--
 * --(Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks. )--
 * --(Unlock IP and adjust to center with jacks.)--
 * Unlock BF keystone and try running BF fishing rod to fix sag problem.
 * Adjust pitch/yaw/vertical of dummy optic.
 * Start TFs.
=== Main Assembly Sequence ===
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Fix #1 geophone adapter cable.
 * Fix broken pico adapter cable?
 * Debug all electronics, starting with IRM OSEMs.
 * Unlock IP; use jacks and FRs to center.
 * Check IP yaw.
 * Recheck centering of suspension in assembly frame.
 * Measure IP period; adjust ballast mass.
 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
 * LBB stuff (see below).
 *
Line 55: Line 37:
=== Electronics ===
 * Get pico drive screens fixed (Miyo-kun)
 * Order final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
 * --(Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).)--
 * --(Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.)--
 * --(Reconnect in-vacuum cabling.)--
 * --(Adjust in-air cabling to match 135° rotation of BS.)--
 * --(Reconnect in-air cables.)-- (all but 4)
 * Calibrate PI vertical LVDT.
 * Set yoke on PI vertical LVDT (if necessary).
 * Calibrate PI horizontal LVDTs.
=== LBB Sequence
 * Unclamp LBB ring sandwich; fully suspend Cu ring.
 * Unscrew LBB from tank brackets.
 * Hook LBB.
 * Remove TBD amount of spacers from between LBB and tank brackets.
 * Set LBB blade stops to nominal height.
 * Extend foot screws on LBB to just barely support LBB.
 * Adjust height of LBB magnet ring to set proper gap (4 mm??).
 * Retract LBB foot screws.
 * Add temporary ballast to LBB until LBB blades just barely sink below stops.
 * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
 * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
 * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.
Line 67: Line 51:
=== LSOL ===
 * Assist Simon with hardware installation of LSOL (week of 6/26?).
 * Assist Simon with modifications to realtime model for LSOL (week of 6/26?).

=== Real-time and SUMCON models ===
 * Derive and install PI LVDT matrices.
 * Check LSOL section of k1visbs model.
=== In parallel, time permitting ===
Line 76: Line 54:
== Real BS Hang Tasks == == Tasks Not To Forget ==
Line 78: Line 56:
 * Final ballast mass design/production for BF and SF (Fabian, Hirata-san).
 * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
 * Possible rebuild of BF and/or SF
  * Set up build/test stand for filters.
  * Get filter test weights.
  * Find spare BF blade(s).
 * Prepare real BS:
  * Coordinate with Hirose-san.
  * Book transport of mirror (Kashiwa to KAGRA)
  * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs.
  * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san).
  * Organize cleanroom gear for Kashiwa trip(s).
  * Put magnets in flags.
  * Glue flags/prisms at Kashiwa.
 * Reclean stuff:
  * PI (remove Kapton tape etc, etc).
  * LLB damper stuff, especially Cu segments.
 * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata).
 * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata).
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Get pico drive screens fixed (Miyo-kun)
 * Figure out how to make PI yaw adjustment reliable.
Line 101: Line 64:
 * Swap out temporary ballast mass in BF, SF.  * Put pointy-tipped screw in RM trolley for BS
Line 105: Line 68:
  * Wide-mouth OSEMs from RM to Akutsu-san
 * Adjust height of crossbars below BF.
 * If possible, fix galled pole in BF level of EQ stop.
Line 109: Line 69:
 * Check inside SF for lost ruler.
 * Tighten PI yaw return spring.
 * Get Cu O-rings for feedthroughs.
Line 115: Line 72:
 * Calibrate all LVDTs (Enzo, Mark).
 * Remove cling wrap in BF and install vacuum-compatible heat shrink.
 * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
 * Rewire PI horizontal steppers with vacuum-compatible cable.
 * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
 * Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Line 129: Line 83:
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks ==
=== Design/Purchasing ===
 * Do rough mass budget for SR2/SR3/SRM.
 * Design SR assembly frame.
 * Design final SF ballast masses (Fabian).

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-09-25

Main Assembly Sequence

  • Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Fix #1 geophone adapter cable.
  • Fix broken pico adapter cable?
  • Debug all electronics, starting with IRM OSEMs.
  • Unlock IP; use jacks and FRs to center.
  • Check IP yaw.
  • Recheck centering of suspension in assembly frame.
  • Measure IP period; adjust ballast mass.
  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • LBB stuff (see below).

=== LBB Sequence

  • Unclamp LBB ring sandwich; fully suspend Cu ring.
  • Unscrew LBB from tank brackets.
  • Hook LBB.
  • Remove TBD amount of spacers from between LBB and tank brackets.
  • Set LBB blade stops to nominal height.
  • Extend foot screws on LBB to just barely support LBB.
  • Adjust height of LBB magnet ring to set proper gap (4 mm??).
  • Retract LBB foot screws.
  • Add temporary ballast to LBB until LBB blades just barely sink below stops.
  • Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
  • Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
  • Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.

In parallel, time permitting

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Get pico drive screens fixed (Miyo-kun)
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Get clean bag laundered.
  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Lock washers for LBB dampers
    • Temporary ballast mass (dog clamps) in BF.
  • Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.

Electrical

  • Decide final in-vacuum and in-air cable routing (Enzo).
  • Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)