5844
Comment:
|
3346
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== Coming Weeks (2017-06-19, 2017-06-26) == === Facilities === * --(Remove cling wrap from stuff.)-- * --(Plug stuff back in (charging station, KOACH filters, OL etc).)-- * --(Power up rack.)-- |
|
Line 29: | Line 22: |
=== Design/Documentation === * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). |
== 2017-09-25 == |
Line 35: | Line 24: |
=== Main Assembly === * --(Remove crossbars below BF and SF.)-- * --(Set SF damper to 4 mm clearance.)-- * --(Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).)-- * --(Adjust jacks to nominal height.)-- * --(Do up all EQ stops etc (except SF).)-- * --(Remove geophones (temporarily, for craning).)-- * --(Crane suspension into tank.)-- * --(Hook LBB Cu ring.)-- |
=== Main Assembly Sequence === * --(Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).)-- * --(Fix #1 geophone adapter cable.)-- * Fix broken pico adapter cable? * Debug all electronics, starting with IRM OSEMs. (half done) * --(Unlock IP; use jacks and FRs to center.)-- * Check IP yaw. * Recheck centering of suspension in assembly frame. * Measure IP period; adjust ballast mass. * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * LBB stuff (see below). * === LBB Sequence === * --(Unclamp LBB ring sandwich; fully suspend Cu ring.)-- * --(Unscrew LBB from tank brackets.)-- |
Line 45: | Line 41: |
* --(Crane vacuum tank lid+ring back on.)-- * --(Remove vacuum tank lid (only) and store on pallet.)-- * --(Add ballast to LBB.)-- * --(Replace geophones.)-- * --(Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks. )-- * --(Unlock IP and adjust to center with jacks.)-- * Unlock BF keystone and try running BF fishing rod to fix sag problem. * Adjust pitch/yaw/vertical of dummy optic. * Start TFs. |
* --(Remove TBD amount of spacers from between LBB and tank brackets.)-- * --(Set LBB blade stops to nominal height.)-- * --(Extend foot screws on LBB to just barely support LBB.)-- * --(Adjust height of LBB magnet ring to set proper gap (4 mm??).)-- * --(Retract LBB foot screws.)-- * --(Add temporary ballast to LBB until LBB blades just barely sink below stops.)-- * --(Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.)-- * --(Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.)-- * --(Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.)-- |
Line 55: | Line 51: |
=== Electronics === * Get pico drive screens fixed (Miyo-kun) * Order final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * --(Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).)-- * --(Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.)-- * --(Reconnect in-vacuum cabling.)-- * --(Adjust in-air cabling to match 135° rotation of BS.)-- * --(Reconnect in-air cables.)-- (all but 4) * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. === LSOL === * Assist Simon with hardware installation of LSOL (week of 6/26?). * Assist Simon with modifications to realtime model for LSOL (week of 6/26?). === Real-time and SUMCON models === * Derive and install PI LVDT matrices. * Check LSOL section of k1visbs model. |
=== In parallel, time permitting === |
Line 76: | Line 54: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 78: | Line 56: |
* Final ballast mass design/production for BF and SF (Fabian, Hirata-san). * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Prepare real BS: * Coordinate with Hirose-san. * Book transport of mirror (Kashiwa to KAGRA) * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs. * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san). * Organize cleanroom gear for Kashiwa trip(s). * Put magnets in flags. * Glue flags/prisms at Kashiwa. * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata). * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata). |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) * Figure out how to make PI yaw adjustment reliable. |
Line 101: | Line 64: |
* Swap out temporary ballast mass in BF, SF. | * Put pointy-tipped screw in RM trolley for BS |
Line 105: | Line 68: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. |
|
Line 109: | Line 69: |
* Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 115: | Line 72: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 129: | Line 83: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-25
Main Assembly Sequence
Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
Fix #1 geophone adapter cable.
- Fix broken pico adapter cable?
- Debug all electronics, starting with IRM OSEMs. (half done)
Unlock IP; use jacks and FRs to center.
- Check IP yaw.
- Recheck centering of suspension in assembly frame.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- LBB stuff (see below).
LBB Sequence
Unclamp LBB ring sandwich; fully suspend Cu ring.
Unscrew LBB from tank brackets.
Hook LBB.
Remove TBD amount of spacers from between LBB and tank brackets.
Set LBB blade stops to nominal height.
Extend foot screws on LBB to just barely support LBB.
Adjust height of LBB magnet ring to set proper gap (4 mm??).
Retract LBB foot screws.
Add temporary ballast to LBB until LBB blades just barely sink below stops.
Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.
In parallel, time permitting
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.