5844
Comment:
|
4832
|
Deletions are marked like this. | Additions are marked like this. |
Line 25: | Line 25: |
* --(Remove cling wrap from stuff.)-- * --(Plug stuff back in (charging station, KOACH filters, OL etc).)-- |
|
Line 36: | Line 34: |
* --(Remove crossbars below BF and SF.)-- * --(Set SF damper to 4 mm clearance.)-- * --(Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).)-- * --(Adjust jacks to nominal height.)-- * --(Do up all EQ stops etc (except SF).)-- * --(Remove geophones (temporarily, for craning).)-- * --(Crane suspension into tank.)-- * --(Hook LBB Cu ring.)-- * --(Hook LBB.)-- * --(Crane vacuum tank lid+ring back on.)-- * --(Remove vacuum tank lid (only) and store on pallet.)-- * --(Add ballast to LBB.)-- * --(Replace geophones.)-- * --(Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks. )-- * --(Unlock IP and adjust to center with jacks.)-- * Unlock BF keystone and try running BF fishing rod to fix sag problem. |
* ''Unlock BF keystone and try running BF fishing rod to fix sag problem.'''' |
Line 53: | Line 36: |
* Crane tank lid on. | |
Line 56: | Line 40: |
* Wash extra F-F gender benders. * Fix broken picomotor cable. * Install new LVDT driver and set gains. * Document LVDT driver rebuild and other changes. * Debug all cabling! |
|
Line 57: | Line 46: |
* Order final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * --(Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).)-- * --(Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.)-- * --(Reconnect in-vacuum cabling.)-- * --(Adjust in-air cabling to match 135° rotation of BS.)-- * --(Reconnect in-air cables.)-- (all but 4) * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
* Sort out naming convention for PI LVDTs, geophones and horizontal steppers. |
Line 68: | Line 49: |
* Assist Simon with hardware installation of LSOL (week of 6/26?). * Assist Simon with modifications to realtime model for LSOL (week of 6/26?). |
* Assist Simon with hardware installation of LSOL. * Assist Simon with modifications to realtime model for LSOL. |
Line 97: | Line 78: |
* Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. |
VIS Type B Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks (2017-06-19, 2017-06-26)
Facilities
Power up rack.
Design/Documentation
- Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian).
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).
- Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).
Main Assembly
Unlock BF keystone and try running BF fishing rod to fix sag problem.'
- Adjust pitch/yaw/vertical of dummy optic.
- Crane tank lid on.
- Start TFs.
Electronics
- Wash extra F-F gender benders.
- Fix broken picomotor cable.
- Install new LVDT driver and set gains.
- Document LVDT driver rebuild and other changes.
- Debug all cabling!
- Get pico drive screens fixed (Miyo-kun)
- Sort out naming convention for PI LVDTs, geophones and horizontal steppers.
LSOL
- Assist Simon with hardware installation of LSOL.
- Assist Simon with modifications to realtime model for LSOL.
Real-time and SUMCON models
- Derive and install PI LVDT matrices.
- Check LSOL section of k1visbs model.
Real BS Hang Tasks
Major Tasks
- Final ballast mass design/production for BF and SF (Fabian, Hirata-san).
- Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
- Possible rebuild of BF and/or SF
- Set up build/test stand for filters.
- Get filter test weights.
- Find spare BF blade(s).
- Prepare real BS:
- Coordinate with Hirose-san.
- Book transport of mirror (Kashiwa to KAGRA)
- Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs.
- Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san).
- Organize cleanroom gear for Kashiwa trip(s).
- Put magnets in flags.
- Glue flags/prisms at Kashiwa.
- Reclean stuff:
- PI (remove Kapton tape etc, etc).
- LLB damper stuff, especially Cu segments.
- Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata).
- If needed based on previous, order longer threaded rods for arc weights on PI (Hirata).
- Calibrate PI vertical LVDT.
- Set yoke on PI vertical LVDT (if necessary).
- Calibrate PI horizontal LVDTs.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Swap out temporary ballast mass in BF, SF.
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Wide-mouth OSEMs from RM to Akutsu-san
- Adjust height of crossbars below BF.
- If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
- Check inside SF for lost ruler.
- Tighten PI yaw return spring.
- Get Cu O-rings for feedthroughs.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
- Calibrate all LVDTs (Enzo, Mark).
- Remove cling wrap in BF and install vacuum-compatible heat shrink.
- Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
- Rewire PI horizontal steppers with vacuum-compatible cable.
- Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
- Create a proper DAC Monitor MEDM screen.
- Improve ADC Monitor MEDM screen.
SR Prep Tasks
Design/Purchasing
- Do rough mass budget for SR2/SR3/SRM.
- Design SR assembly frame.
- Design final SF ballast masses (Fabian).