= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 10: | Line 12: |
[[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 23: |
== Coming Weeks 2017-06-26 == === Facilities === |
== 2017-08-28 == |
Line 26: | Line 25: |
=== Design/Documentation/Planning === * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). |
=== Main Assembly Sequence === * Crane out SF. * Remove BF cap and retrieve lost hex cable clamp PEEK piece. * Crane in SF. * Install SF-BF rod with hex cable clamp. * Route cables via hex cable clamp up to below SF. * Adjust BF ballast mass for total weight and pitch/roll. * Look for missing screw from SF damper Cu segment in washed screws bag and reinstall. * Calibrate SF LVDT. * Measure bounce frequency of BF/... from SF with BF locked. |
Line 33: | Line 36: |
== BS Prism/Flag gluing == * Push Hirose-san to set exact date. * Organize transport company for Kashiwa->Kamioka * Organize NAOJ vehicle for Mitaka->Kashiwa * Akabou Yoshihara Delivery Service (赤帽よしはら運送) yoshihara@akabou.ne.jp (吉原様) * Collect all items required. * Mirror box. * Prisms. * Stub flags. * Magnets: SmCo, 2 mm diameter, 3 mm long * Prism jigs * Flag jigs * Glue magnets to flags, 2 N, 2 S. * Organize clean suits. * Make a list of people's sizes: * Mark: LL, 29 cm * Fabian: L, 26.5 or 27 cm * Hirata: M, 25.5 cm * Enzo: ?? * Get ones at Mitaka laundered? * Get Mark/Enzo to bring from Kamioka? === Main Assembly === * Adjust pitch/yaw/vertical of dummy optic. * Crane tank lid on. * Start TFs. === Electronics === * Wash extra F-F gender benders. * Fix broken picomotor cable. * Install new LVDT driver and set gains. * Document LVDT driver rebuild and other changes. * Debug all cabling! * Get pico drive screens fixed (Miyo-kun) * Sort out naming convention for PI LVDTs, geophones and horizontal steppers. === LSOL === * Assist Simon with hardware installation of LSOL. * Assist Simon with modifications to realtime model for LSOL. === Real-time and SUMCON models === * Derive and install PI LVDT matrices. * Check LSOL section of k1visbs model. |
=== In parallel, time permitting === * Rearrange arc weights on PI to allow installation of magic wand. * Check that we have all LBB parts (there was an issue with borrowed lock nuts). * Rearrange magnets on SF damper magnet ring for full three Cu segments. * Find Ni-plated rods for SF damper magnet ring and do fit check. * Find PI-SF rod with 8 mm heads and matching receptacles and do fit check. * Lay more new in-air cabling. * Wipe LLB damper parts with ethanol. * Get Cu O-rings for feedthroughs. * Figure out how to tighten PI yaw return spring. |
Line 80: | Line 50: |
* Final ballast mass design/production for BF and SF (Fabian, Hirata-san). * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Prepare real BS: * Coordinate with Hirose-san. * Book transport of mirror (Kashiwa to KAGRA) * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs. * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san). * Organize cleanroom gear for Kashiwa trip(s). * Put magnets in flags. * Glue flags/prisms at Kashiwa. * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata). * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata). |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) |
Line 102: | Line 56: |
* Unlock BF keystone and try running BF fishing rod to fix sag problem. | |
Line 107: | Line 60: |
* Swap out temporary ballast mass in BF, SF. | * Put pointy-tipped screw in RM trolley for BS |
Line 111: | Line 64: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. |
* --(Wide-mouth OSEMs from RM to Akutsu-san)-- * --(Adjust height of crossbars below BF.)-- * --(If possible, fix galled pole in BF level of EQ stop.)-- |
Line 115: | Line 68: |
* Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 121: | Line 71: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, SF, PI-GAS, PI-H1, PI-H2, PI-H3 * --(Remove cling wrap in BF and install vacuum-compatible heat shrink.)-- * --(Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).)-- * --(Rewire PI horizontal steppers with vacuum-compatible cable)--. * --(Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).)-- * Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 135: | Line 87: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
* --(Create a proper DAC Monitor MEDM screen.)-- * --(Improve ADC Monitor MEDM screen.)-- |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-08-28
Main Assembly Sequence
- Crane out SF.
- Remove BF cap and retrieve lost hex cable clamp PEEK piece.
- Crane in SF.
- Install SF-BF rod with hex cable clamp.
- Route cables via hex cable clamp up to below SF.
- Adjust BF ballast mass for total weight and pitch/roll.
- Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.
- Calibrate SF LVDT.
- Measure bounce frequency of BF/... from SF with BF locked.
In parallel, time permitting
- Rearrange arc weights on PI to allow installation of magic wand.
- Check that we have all LBB parts (there was an issue with borrowed lock nuts).
- Rearrange magnets on SF damper magnet ring for full three Cu segments.
- Find Ni-plated rods for SF damper magnet ring and do fit check.
- Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.
- Lay more new in-air cabling.
- Wipe LLB damper parts with ethanol.
- Get Cu O-rings for feedthroughs.
- Figure out how to tighten PI yaw return spring.
Real BS Hang Tasks
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Calibrate PI vertical LVDT.
- Set yoke on PI vertical LVDT (if necessary).
- Calibrate PI horizontal LVDTs.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
Wide-mouth OSEMs from RM to Akutsu-san
Adjust height of crossbars below BF.
If possible, fix galled pole in BF level of EQ stop.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
Remove cling wrap in BF and install vacuum-compatible heat shrink.
Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
Rewire PI horizontal steppers with vacuum-compatible cable.
Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).
- Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.
Create a proper DAC Monitor MEDM screen.
Improve ADC Monitor MEDM screen.