Differences between revisions 78 and 157 (spanning 79 versions)
Revision 78 as of 2017-06-30 11:44:00
Size: 5588
Editor: MarkBarton
Comment:
Revision 157 as of 2017-10-10 08:59:50
Size: 2829
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= VIS Type B Near Term To-Do List = = VIS Type B BS Near Term To-Do List =
Line 3: Line 3:
[[../ToDoOld|Archived To-Do Items]] [[../ToDoOldBS|Archived BS To-Do Items]]

[[../ToDoSR|SR To-Do Items]]
Line 8: Line 10:

[[#RealBSHang|Preparation for Real BS Hang]]

[[#SRPrepTasks|Preparation for SR Installation]]
Line 23: Line 21:
== Coming Weeks 2017-06-26 ==
=== Facilities ===
Line 26: Line 22:
=== Design/Documentation/Planning ===
  
 * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian).
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).
 * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).
== 2017-10-10 ==
Line 33: Line 24:
== BS Prism/Flag gluing ==
 * Push Hirose-san to set exact date.
 * Organize transport company for Kashiwa->Kamioka
 * Organize NAOJ vehicle for Mitaka->Kashiwa
  * Akabou Yoshihara Delivery Service (赤帽よしはら運送) yoshihara@akabou.ne.jp (吉原様)
 * Collect all items required.
  * Mirror box.
  * Prisms.
  * Stub flags.
  * Magnets: SmCo, 2 mm diameter, 3 mm long
  * Prism jigs
  * Flag jigs
 * Glue magnets to flags, 2 N, 2 S.
 * Organize clean suits.
  * Make a list of people's sizes:
   * Mark: LL, 29 cm
   * Fabian: LL, 26.5 or 27 cm
   * Hirata: M, 25.5 cm
   * Enzo: L, 27 or 28 cm
  * Get ones at Mitaka laundered?
  * Get Mark/Enzo to bring from Kamioka?
=== Main Assembly Sequence ===
 * Account for second bubble level (might be on BF).
 * Borrow portable hard drive.
 * Clean up sticker residue and magic marker writing.
 * Remove LVDT modules; identify and replace screws.
 * Check that all in-air cables are labeled.
 * If possible, reroute cable to eliminate need for fifth feedthrough.
 * Debug all electronics, especially actuation.
 * Measure IP period; adjust ballast mass.
 * Calibrate all LVDTs. --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3
 * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
 * Set all EQ stops to TBD clearance.
 * Install small KOACH filters on LBB.
 * Remove First Contact.
 * Cable optical lever (Simon, Enzo)
 * Align optical lever (Simon)
 * Get ready for full TFs.
Line 55: Line 42:
=== Main Assembly ===
 * Adjust pitch/yaw/vertical of dummy optic.
 * Crane tank lid on.
 * Start TFs.
=== Etc ===
 * Move stuff out of PR2 area.
 * Tidy/label parts.
 * Move safety bars from BS AF area to SR2 area.
 * (Put up safety bars in SR3 area.)
 * Close hole in floor above BS AF area.
Line 60: Line 49:
=== Electronics ===
 * --(Wash extra F-F gender benders.)--
 * --(Fix broken picomotor cable.)--
 * Install new LVDT driver and set gains.
 * Document LVDT driver rebuild and other changes.
 * Debug all cabling!
 * Get pico drive screens fixed (Miyo-kun)
 * Sort out naming convention for PI LVDTs, geophones and horizontal steppers.

BS PI Geo #0 ~ #2 ;
BS PI LVDT #0 ~ #2 ;
BS PI Stepper #0 ~ #2 ?

=== LSOL ===
 * Assist Simon with hardware installation of LSOL.
 * Assist Simon with modifications to realtime model for LSOL.

=== Real-time and SUMCON models ===
 * Derive and install PI LVDT matrices.
 * Check LSOL section of k1visbs model.
=== Software ===
 * Enter new IP matrices and do safe.snap.
 * Send stepper driver info to Miyo-kun.
 * Update real-time model to number channels from #0.
 * Remove old OL stuff; add link to new OL stuff.
 * Remove unused screens.
 * Sort out SVN.
 * Add support for comments to SUMCON.
 * Create SUMCON model with values commented.
 * Derive matrices for IP FRs.
Line 82: Line 61:
== Real BS Hang Tasks == == Tasks Not To Forget ==
Line 84: Line 63:
 * Final ballast mass design/production for BF and SF (Fabian, Hirata-san).
 * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).
 * Possible rebuild of BF and/or SF
  * Set up build/test stand for filters.
  * Get filter test weights.
  * Find spare BF blade(s).
 * Prepare real BS:
  * Coordinate with Hirose-san.
  * Book transport of mirror (Kashiwa to KAGRA)
  * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs.
  * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san).
  * Organize cleanroom gear for Kashiwa trip(s).
  * Put magnets in flags.
  * Glue flags/prisms at Kashiwa.
 * Reclean stuff:
  * PI (remove Kapton tape etc, etc).
  * LLB damper stuff, especially Cu segments.
 * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata).
 * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata).
 * Calibrate PI vertical LVDT.
 * Set yoke on PI vertical LVDT (if necessary).
 * Calibrate PI horizontal LVDTs.
 * Unlock BF keystone and try running BF fishing rod to fix sag problem.
 * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
 * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
 * Figure out how to make PI yaw adjustment reliable.
Line 110: Line 69:
 * Get clean bag laundered.
 * Swap out temporary ballast mass in BF, SF.
 * Put pointy-tipped screw in RM trolley for BS
Line 113: Line 71:
  * Lock washers for LBB dampers
Line 115: Line 72:
  * Wide-mouth OSEMs from RM to Akutsu-san
 * Adjust height of crossbars below BF.
 * If possible, fix galled pole in BF level of EQ stop.
 * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
 * Check inside SF for lost ruler.
 * Tighten PI yaw return spring.
 * Get Cu O-rings for feedthroughs.
Line 124: Line 74:
 * Decide final in-vacuum and in-air cable routing (Enzo).
 * Calibrate all LVDTs (Enzo, Mark).
 * Remove cling wrap in BF and install vacuum-compatible heat shrink.
 * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
 * Rewire PI horizontal steppers with vacuum-compatible cable.
 * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
Line 139: Line 83:
 * Create a proper DAC Monitor MEDM screen.
 * Improve ADC Monitor MEDM screen.

<<Anchor(SRPrepTasks)>>

== SR Prep Tasks ==
=== Design/Purchasing ===
 * Do rough mass budget for SR2/SR3/SRM.
 * Design SR assembly frame.
 * Design final SF ballast masses (Fabian).

VIS Type B BS Near Term To-Do List

Archived BS To-Do Items

SR To-Do Items

Every Week

Coming Weeks

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-10-10

Main Assembly Sequence

  • Account for second bubble level (might be on BF).
  • Borrow portable hard drive.
  • Clean up sticker residue and magic marker writing.
  • Remove LVDT modules; identify and replace screws.
  • Check that all in-air cables are labeled.
  • If possible, reroute cable to eliminate need for fifth feedthrough.
  • Debug all electronics, especially actuation.
  • Measure IP period; adjust ballast mass.
  • Calibrate all LVDTs. BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3

  • Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
  • Set all EQ stops to TBD clearance.
  • Install small KOACH filters on LBB.
  • Remove First Contact.
  • Cable optical lever (Simon, Enzo)
  • Align optical lever (Simon)
  • Get ready for full TFs.

Etc

  • Move stuff out of PR2 area.
  • Tidy/label parts.
  • Move safety bars from BS AF area to SR2 area.
  • (Put up safety bars in SR3 area.)
  • Close hole in floor above BS AF area.

Software

  • Enter new IP matrices and do safe.snap.
  • Send stepper driver info to Miyo-kun.
  • Update real-time model to number channels from #0.
  • Remove old OL stuff; add link to new OL stuff.
  • Remove unused screens.
  • Sort out SVN.
  • Add support for comments to SUMCON.
  • Create SUMCON model with values commented.
  • Derive matrices for IP FRs.

Tasks Not To Forget

Major Tasks

  • Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
  • Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
  • Figure out how to make PI yaw adjustment reliable.

Minor Tasks

Mechanical

  • Put pointy-tipped screw in RM trolley for BS
  • Return/replace borrowed parts:
    • Temporary ballast mass (dog clamps) in BF.

Electrical

Real-time and SUMCON models

  • Create SUMCON models for full BS and major installation milestones.
  • Create controls design description (cf LIGO-T1100378).

  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.
  • Design and install GAS drift compensation filters.

KAGRA/Subgroups/VIS/TypeB/ToDoBS (last edited 2019-01-04 15:21:23 by MarkBarton)