5666
Comment:
|
3240
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== Coming Weeks 2017-06-26 == === Facilities === |
|
Line 26: | Line 22: |
=== Design/Documentation/Planning === * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). |
== 2017-09-25 == |
Line 33: | Line 24: |
== BS Prism/Flag gluing == * --(Push Hirose-san to set exact date.)-- * --(Organize NAOJ vehicle for Mitaka->Kashiwa)-- * Organize transport company for Kashiwa->Kamioka * Akabou Yoshihara Delivery Service (赤帽よしはら運送) yoshihara@akabou.ne.jp (吉原様) * Collect all items required. * --(Mirror box.)-- * --(Prisms.)-- * --(Stub flags.)-- * --(Magnets: SmCo, 2 mm diameter, 3 mm long)-- * --(Prism jigs)-- * --(Flag jigs)-- * Glue magnets to flags, 2 N, 2 S. * --(Organize clean suits.)-- * --(Make a list of people's sizes)-- * --(Get Mark/Enzo to bring from Kamioka.)-- |
=== Main Assembly Sequence === * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). * Fix #1 geophone adapter cable. * Fix broken pico adapter cable? * Debug all electronics, starting with IRM OSEMs. * Unlock IP; use jacks and FRs to center. * Check IP yaw. * Recheck centering of suspension in assembly frame. * Measure IP period; adjust ballast mass. * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * LBB stuff (see below). * |
Line 50: | Line 37: |
=== Main Assembly === * --(Adjust pitch/yaw/vertical of dummy optic.)-- * --(Crane tank lid on.)-- * Start TFs. |
=== LBB Sequence * Unclamp LBB ring sandwich; fully suspend Cu ring. * Unscrew LBB from tank brackets. * Hook LBB. * Remove TBD amount of spacers from between LBB and tank brackets. * Set LBB blade stops to nominal height. * Extend foot screws on LBB to just barely support LBB. * Adjust height of LBB magnet ring to set proper gap (4 mm??). * Retract LBB foot screws. * Add temporary ballast to LBB until LBB blades just barely sink below stops. * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles. * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal. * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal. |
Line 55: | Line 51: |
=== Electronics === * --(Wash extra F-F gender benders.)-- * --(Fix broken picomotor cable.)-- * Install new LVDT driver and set gains. * Document LVDT driver rebuild and other changes. * --(Debug all cabling!)-- * Fix #0 LVDT actuator coil. * Get pico drive screens fixed (Miyo-kun) * --(Sort out naming convention for PI LVDTs, geophones and horizontal steppers.)-- === LSOL === * --(Assist Simon with hardware installation of LSOL.)-- * --(Assist Simon with modifications to realtime model for LSOL.)-- === Real-time and SUMCON models === * --(Derive and install PI LVDT matrices.)-- * --(Check LSOL section of k1visbs model.)-- |
=== In parallel, time permitting === |
Line 74: | Line 54: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 76: | Line 56: |
--( * Final ballast mass design for BF and SF (Fabian).)-- * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * --(Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san).)-- * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Prepare real BS: * --(Coordinate with Hirose-san)--. * Book transport of mirror (Kashiwa or Mitaka to KAGRA) * --(Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs)--. * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san). * --(Organize cleanroom gear for Kashiwa trip(s).)-- * Put magnets in flags. * Glue flags/prisms at Kashiwa. * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata). * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata). * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. * Unlock BF keystone and try running BF fishing rod to fix sag problem. |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) * Figure out how to make PI yaw adjustment reliable. |
Line 105: | Line 64: |
* Swap out temporary ballast mass in BF, SF. | * Put pointy-tipped screw in RM trolley for BS |
Line 109: | Line 68: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. |
|
Line 113: | Line 69: |
* Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 119: | Line 72: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, --(PI-GAS)--, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 133: | Line 83: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-25
Main Assembly Sequence
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
- Fix #1 geophone adapter cable.
- Fix broken pico adapter cable?
- Debug all electronics, starting with IRM OSEMs.
- Unlock IP; use jacks and FRs to center.
- Check IP yaw.
- Recheck centering of suspension in assembly frame.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- LBB stuff (see below).
=== LBB Sequence
- Unclamp LBB ring sandwich; fully suspend Cu ring.
- Unscrew LBB from tank brackets.
- Hook LBB.
- Remove TBD amount of spacers from between LBB and tank brackets.
- Set LBB blade stops to nominal height.
- Extend foot screws on LBB to just barely support LBB.
- Adjust height of LBB magnet ring to set proper gap (4 mm??).
- Retract LBB foot screws.
- Add temporary ballast to LBB until LBB blades just barely sink below stops.
- Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
- Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
- Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.
In parallel, time permitting
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.