Line 1: | Line 1: |
= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== Coming Weeks 2017-07-10 == === Facilities === |
== 2017-09-11 == |
Line 26: | Line 23: |
=== Design/Documentation/Planning === * Design final BF/SF ballast mass assuming BF can be made to work without rebuild (Fabian). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). |
=== Main Assembly Sequence === * Debug BF LVDT actuation. * --(Debug other actuation.)-- * --(Remove F0-SF rod and reinstall with hex cable clamp.)-- * --(Route cables up past hex cable clamps.)-- * --(Adjust SF trim mass for pitch/roll/vertical.)-- * --(Route all SF/... cables through to the flange and test.)-- * --(Cable all PI items through to the flange.)-- * --(Disconnect the SS from the AF.)-- * --(Recheck/adjust SF/... yaw.)-- * --(Roughly level the PI so as to make the SS vertical.)-- * --(Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.)-- * Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate). * Test all PI items: * Yaw stepper. * F0 LVDT sensing * F0 LVDT actuation * --(Horizontal steppers)-- * Horizontal LVDT sensing * Horizontal LVDT actuation * --(Geophones)-- (except one cable broken: #1) * Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS. * --(Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS.)-- 425 mHz * Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS. |
Line 33: | Line 48: |
== BS Prism/Flag gluing == * Push Hirose-san to set exact date. * Organize NAOJ vehicle for Mitaka->Kashiwa * Organize transport company for Kashiwa->Kamioka * Akabou Yoshihara Delivery Service (赤帽よしはら運送) yoshihara@akabou.ne.jp (吉原様) * Collect all items required. * Mirror box. * Prisms. * Stub flags. * Magnets: SmCo, 2 mm diameter, 3 mm long * Prism jigs * Flag jigs * Glue magnets to flags, 2 N, 2 S. * Organize clean suits. * Make a list of people's sizes * Get Mark/Enzo to bring from Kamioka. |
=== In parallel, time permitting === * --(Fix links to ADC_MONITOR screens.)-- * --(Check that all Take/Restore Safe.snap buttons work.)-- * --(Check that we still have all LBB parts (there was an issue with borrowed lock nuts).)-- * --(Wipe LLB damper parts with ethanol.)-- * Figure out how to tighten PI yaw return spring. * --(Install LBB Cu damper ring in tank (less Cu for now).)-- * --(Apply magnets to LBB Magnet rings.)-- * --(Clean rust from screw holes in LBB magnet ring.)-- * Fix #1 geophone adapter cable. * Fix broken pico adapter cable. |
Line 50: | Line 60: |
=== Main Assembly === * Adjust pitch/yaw/vertical of dummy optic. * Crane tank lid on. * Start TFs. |
== 2017-09-19 == (No work Monday 9/18) * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20). * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * Attach lifting plates. * Lock BF and F0 keystones (but ''not'' SF keystone). * Remove F0 keystone top plate; attach lifting fixture. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Add ballast |
Line 55: | Line 80: |
=== Electronics === * Wash extra F-F gender benders. * Fix broken picomotor cable. * Install new LVDT driver and set gains. * Document LVDT driver rebuild and other changes. * Debug all cabling! * Fix #0 LVDT actuator coil. * Get pico drive screens fixed (Miyo-kun) * Sort out naming convention for PI LVDTs, geophones and horizontal steppers. |
=== Main Assembly Sequence === |
Line 65: | Line 82: |
=== LSOL === * Assist Simon with hardware installation of LSOL. * Assist Simon with modifications to realtime model for LSOL. === Real-time and SUMCON models === * Derive and install PI LVDT matrices. * Check LSOL section of k1visbs model. |
== Dates == * BUMAX countersunk screws for LBB Cu (by 9/20) * SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup) * LBB Cu segments: 9/19-20 |
Line 74: | Line 88: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 76: | Line 90: |
* Final ballast mass design for BF and SF (Fabian). * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Get final OSEM cables (six of 1.7 m, two of 2.2 m, two of 2.4 m; Sato-san). * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Prepare real BS: * Coordinate with Hirose-san. * Book transport of mirror (Kashiwa or Mitaka to KAGRA) * Gather mirror box, gluing supplies, prisms, magnets, new flags, new flag jigs. * Solve problem of lack of scribe line on one side of BS (Mark, Hirata-san). * Organize cleanroom gear for Kashiwa trip(s). * Put magnets in flags. * Glue flags/prisms at Kashiwa. * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Try rearranging arc weights to make room for magic wand (3D CAD or actual weights; Fabian or Hirata). * If needed based on previous, order longer threaded rods for arc weights on PI (Hirata). * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. * Unlock BF keystone and try running BF fishing rod to fix sag problem. |
* Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Get pico drive screens fixed (Miyo-kun) |
Line 106: | Line 98: |
* Swap out temporary ballast mass in BF, SF. | |
Line 110: | Line 101: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. |
|
Line 114: | Line 102: |
* Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 120: | Line 105: |
* Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
* Calibrate all LVDTs (Enzo, Mark). --(BF)--, --(SF)--, PI-GAS, PI-H1, PI-H2, PI-H3 * Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height). |
Line 134: | Line 116: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-09-11
Main Assembly Sequence
- Debug BF LVDT actuation.
Debug other actuation.
Remove F0-SF rod and reinstall with hex cable clamp.
Route cables up past hex cable clamps.
Adjust SF trim mass for pitch/roll/vertical.
Route all SF/... cables through to the flange and test.
Cable all PI items through to the flange.
Disconnect the SS from the AF.
Recheck/adjust SF/... yaw.
Roughly level the PI so as to make the SS vertical.
Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.
- Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate).
- Test all PI items:
- Yaw stepper.
- F0 LVDT sensing
- F0 LVDT actuation
Horizontal steppers
- Horizontal LVDT sensing
- Horizontal LVDT actuation
Geophones (except one cable broken: #1)
- Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS.
Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS. 425 mHz
- Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS.
In parallel, time permitting
Fix links to ADC_MONITOR screens.
Check that all Take/Restore Safe.snap buttons work.
Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
Wipe LLB damper parts with ethanol.
- Figure out how to tighten PI yaw return spring.
Install LBB Cu damper ring in tank (less Cu for now).
Apply magnets to LBB Magnet rings.
Clean rust from screw holes in LBB magnet ring.
- Fix #1 geophone adapter cable.
- Fix broken pico adapter cable.
2017-09-19
(No work Monday 9/18)
- Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
- Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
- Crane tank lid off.
- Crane LBB damper rings to top of tank and suspend.
- Remove BF- and SF-level crossbars.
- Remove geophones for craning.
- Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
- Attach lifting plates.
Lock BF and F0 keystones (but not SF keystone).
- Remove F0 keystone top plate; attach lifting fixture.
- Crane suspension out of assembly frame.
- Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
- Crane suspension into tank and connect upper rods to LBB Cu ring.
- Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
- Install LBB lower rods and hook LBB.
- Measure required ballast for LBB.
- Add ballast
Main Assembly Sequence
Dates
- BUMAX countersunk screws for LBB Cu (by 9/20)
- SDC screws for LBB half rings: 9/15 (Fri) (have Ag-coated as backup)
- LBB Cu segments: 9/19-20
Tasks Not To Forget
Major Tasks
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Get pico drive screens fixed (Miyo-kun)
Minor Tasks
Mechanical
- Get clean bag laundered.
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Lock washers for LBB dampers
- Temporary ballast mass (dog clamps) in BF.
- Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match.
Electrical
- Decide final in-vacuum and in-air cable routing (Enzo).
Calibrate all LVDTs (Enzo, Mark). BF, SF, PI-GAS, PI-H1, PI-H2, PI-H3
- Adjust yoke on PI to put top of secondary at TBD mm above top of baseplate (or to give ≈0 counts at nominal height).
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.