= VIS Type B Near Term To-Do List = | = VIS Type B BS Near Term To-Do List = |
Line 3: | Line 3: |
[[../ToDoOld|Archived To-Do Items]] | [[../ToDoOldBS|Archived BS To-Do Items]] [[../ToDoSR|SR To-Do Items]] |
Line 8: | Line 10: |
[[#RealBSHang|Preparation for Real BS Hang]] [[#SRPrepTasks|Preparation for SR Installation]] |
|
Line 23: | Line 21: |
== Coming Weeks 2017-07-24 == === Facilities === |
|
Line 26: | Line 22: |
=== Design/Documentation/Planning === * Organize new OL for setting BS pitch (Fabian). * Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san). * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * LBB ballast mass. * Research real payload. * Do improved mass budget. === Electronics === * --(Look for LVDT driver box Syyxx3134.)-- * --(Make sure SR3 boxes have notes on their JGW-S.... document pages.)-- |
== 2017-10-16 == |
Line 38: | Line 24: |
=== Main Assembly === * --(Remove BF-SF cables (note which had gender benders and which had extensions).)-- * --(Remove SF.)-- * --(Remove SF SS ring and poles.)-- * Move (or remove) SF AF crossbars. * Remove IRM. * Remove old BF. * Remove RM and dummy BS. * Check centering of IM picos. * Characterize blades (--(1)--,--(2)--,--(3)--,4,5,6). * Rebuild BF. * Check verticality of AF, height of crossbars, centering of optical table. * --(Check gluing result.)-- * --(Cleanup optic after failed secondary prism bonds.)-- * --(Cleanup jigs/prisms after failed secondary prism bonds.)-- * --(Reglue secondary prisms.)-- * Remove LBB rings. * Send rings for recleaning. |
=== Main Assembly Sequence === * --(Borrow portable hard drive.)-- * --(Remove sticker residue and permanent marker writing on PI.)-- * --(Fix broken and unreliable connections on IP LVDTs.)-- * --(Reconfigure the stepper motor cables for Miyo-kun.)-- * Wipe any rust from around IP LVDTs. * --(Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.)-- * Calibrate IP LVDT actuation against IP LVDT sensing. * --(Install damping filters for IP LVDTs.)-- * Adjust gains and debug damping for IM OSEMs and GAS LVDTs. * Modify IP LVDT damping filters to include set point. * --(Install and debug IP LVDT and geophone diagonalization matrices.)-- * --(Work with alignment team.)-- * --(Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed))-- * --(Work with Miyo-kun to get user interface for stepper motors.)-- * --(Calibrate IP FR actuation against IP LVDT sensing.)-- * SR procurement. * --(Lower LBB by 17.5 mm; suspend and rebalance after removing table KOACH filters.)-- * --(Reroute cable to eliminate need for fifth feedthrough.)-- * Set all EQ stops to TBD clearance. * Measure IP period; adjust ballast mass. * Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs. * TFs. === Etc === * Move stuff out of PR2 area. * Tidy/label parts. * Move safety bars from BS AF area to SR2 area. * (Put up safety bars in SR3 area.) * Close hole in floor above BS AF area. === Software === * --(Enter new IP matrices and do safe.snap.)-- * --(Send stepper driver info to Miyo-kun)--. * Update real-time model to number channels from #0. * Remove old OL stuff; add link to new OL stuff. * Remove unused screens. * Sort out SVN. * --(Add support for comments to SUMCON.)-- * Create SUMCON model with values commented. * --(Derive matrices for IP FRs.)-- === Design === * Finalize redesign of IP yaw adjuster. * Design better F0 FR adjuster. |
Line 58: | Line 71: |
== Real BS Hang Tasks == | == Tasks Not To Forget == |
Line 60: | Line 73: |
* Get pico drive screens fixed (Miyo-kun) * Final ballast mass production for BF and SF (Hirata-san). (have quotes) * Design of receptacles for rods with 8 mm heads. * Possible rebuild of BF and/or SF * Set up build/test stand for filters. * Get filter test weights. * Find spare BF blade(s). * Reclean stuff: * PI (remove Kapton tape etc, etc). * LLB damper stuff, especially Cu segments. * Calibrate PI vertical LVDT. * Set yoke on PI vertical LVDT (if necessary). * Calibrate PI horizontal LVDTs. * Unlock BF keystone and try running BF fishing rod to fix sag problem. |
* (Time permitting) Try adding mass to IP. * Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD. * Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san). * Figure out how to make PI yaw adjustment reliable. |
Line 77: | Line 80: |
* Get clean bag laundered. | |
Line 79: | Line 81: |
* Swap out temporary ballast mass in BF, SF. | |
Line 81: | Line 82: |
* Lock washers for LBB dampers | |
Line 83: | Line 83: |
* Wide-mouth OSEMs from RM to Akutsu-san * Adjust height of crossbars below BF. * If possible, fix galled pole in BF level of EQ stop. * Swap in new F0-SF maraging rod (with 8-mm heads) and new receptacles to match. * Check inside SF for lost ruler. * Tighten PI yaw return spring. * Get Cu O-rings for feedthroughs. |
|
Line 92: | Line 85: |
* Decide final in-vacuum and in-air cable routing (Enzo). * Calibrate all LVDTs (Enzo, Mark). * Remove cling wrap in BF and install vacuum-compatible heat shrink. * Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins). * Rewire PI horizontal steppers with vacuum-compatible cable. * Adjust yoke on BF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height). |
|
Line 107: | Line 94: |
* Create a proper DAC Monitor MEDM screen. * Improve ADC Monitor MEDM screen. <<Anchor(SRPrepTasks)>> == SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B BS Near Term To-Do List
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-10-16
Main Assembly Sequence
Borrow portable hard drive.
Remove sticker residue and permanent marker writing on PI.
Fix broken and unreliable connections on IP LVDTs.
Reconfigure the stepper motor cables for Miyo-kun.
- Wipe any rust from around IP LVDTs.
Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.
- Calibrate IP LVDT actuation against IP LVDT sensing.
Install damping filters for IP LVDTs.
- Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
- Modify IP LVDT damping filters to include set point.
Install and debug IP LVDT and geophone diagonalization matrices.
Work with alignment team.
Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed)
Work with Miyo-kun to get user interface for stepper motors.
Calibrate IP FR actuation against IP LVDT sensing.
- SR procurement.
Lower LBB by 17.5 mm; suspend and rebalance after removing table KOACH filters.
Reroute cable to eliminate need for fifth feedthrough.
- Set all EQ stops to TBD clearance.
- Measure IP period; adjust ballast mass.
- Calibrate IP LVDT sensing against IP LVDT actuation, IP FRs.
- TFs.
Etc
- Move stuff out of PR2 area.
- Tidy/label parts.
- Move safety bars from BS AF area to SR2 area.
- (Put up safety bars in SR3 area.)
- Close hole in floor above BS AF area.
Software
Enter new IP matrices and do safe.snap.
Send stepper driver info to Miyo-kun.
- Update real-time model to number channels from #0.
- Remove old OL stuff; add link to new OL stuff.
- Remove unused screens.
- Sort out SVN.
Add support for comments to SUMCON.
- Create SUMCON model with values commented.
Derive matrices for IP FRs.
Design
- Finalize redesign of IP yaw adjuster.
- Design better F0 FR adjuster.
Tasks Not To Forget
Major Tasks
- (Time permitting) Try adding mass to IP.
- Update BS Install Procedure with screenshots from new on-assembly-frame 3D CAD.
- Finish assembly drawing for LBB and LBB damper ring and post on JGWDoc (Hirata-san).
- Figure out how to make PI yaw adjustment reliable.
Minor Tasks
Mechanical
- Put pointy-tipped screw in RM trolley for BS
- Return/replace borrowed parts:
- Temporary ballast mass (dog clamps) in BF.
Electrical
Real-time and SUMCON models
- Create SUMCON models for full BS and major installation milestones.
Create controls design description (cf LIGO-T1100378).
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
- Design and install GAS drift compensation filters.