VIS Type B Near Term To-Do List
2017-03-13
Facilities
- Vacuum and roll floor (All)
- Wipe ladders (All)
- Tidy tools, parts (All)
- Find missing light lent to Kokeyama-san (Mark)
- Mark/photograph/count peeling patches on the floor.
- Mark/photograph/count pillars with bare concrete bases.
Electronics
- Wire up BF roll/pitch picos (Enzo)
- Work with Miyo-kun to get pico drivers added to BS rack and screens (Enzo, Mark)
- Grab remaining cables etc per E1605111 and update document (Enzo)
- Update E1503600 with DIO card for HPCDs, etc, etc. (Enzo)
- Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
- Send list of required in-vacuum cables to Takahashi-san (Enzo, Mark)
- Debug 900 Hz noise on BF LVDT output (Enzo, Mark)
- Debug excess noise on TM-H3 OSEM (Enzo, Mark)
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
- Make spreadsheet on Google Docs or the like with in-vacuum cable inventory (Hirata)
PI Prep
- Inspect PI, compare to CAD and 2D drawings (Hirata, Mark)
- Identify missing PI parts (Hirata, Mark)
- Find and reattach repaired LVDT coil(s) (???)
Hanging BF/IRM/IM/RM/BS
- Correct orientation of SF cap (Mark, Fabian, Perry)
- Correct orientation of SF (Mark, Fabian, Perry)
- Find/attach cable clamps for SF (Fabian)
Real-time and SUMCON models
- Update SUMCON model of full BS (Perry?, Okutomi?, Mark?)
- Do cut-down SUMCON model of just payload hanging from fixed BS (Perry?, Okitomi?, Mark?)
- Compare measured TFs to cut-down model
- Create a proper DAC Monitor MEDM screen
- Improve ADC Monitor MEDM screen