= 2017-04-03 = | ../ToDo == 2017-06-26 == === BS Prism/Flag gluing === * Organize transport company for Kashiwa->Kamioka * Collect mirror, mirror box, tools etc from Kashiwa. * Ship mirror to Kamioka via Akabou. * Ship gluing tools to Kamioka via Yu-Pack. * Get 5 mm prisms cut down to 3 mm (ATC, Hirata-san). * Get magnet jigs remade (ATC). === Design/Documentation/Planning === * Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san). === Electronics === * Fix #0 LVDT actuator coil. == 2017-06-26 == == BS Prism/Flag gluing == * Push Hirose-san to set exact date. * Organize NAOJ vehicle for Mitaka->Kashiwa * Collect all items required. * Mirror box. * ''Prisms.'' (not found!) * Stub flags. * Magnets: SmCo, 2 mm diameter, 3 mm long * Prism jigs * Flag jigs * Glue magnets to flags, 2 N, 2 S. * Organize clean suits. * Make a list of people's sizes * Get Mark/Enzo to bring from Kamioka. === Main Assembly === * Adjust pitch/yaw/vertical of dummy optic. * Crane tank lid on. * Start TFs. === Electronics === * Wash extra F-F gender benders. * Fix broken picomotor cable. * Sort out naming convention for PI LVDTs, geophones and horizontal steppers. === LSOL === * Assist Simon with hardware installation of LSOL. * Assist Simon with modifications to realtime model for LSOL. === Real-time and SUMCON models === * Derive and install PI LVDT matrices. * Check LSOL section of k1visbs model. == 2017-06-19 == === Facilities === * Remove cling wrap from stuff. * Plug stuff back in (charging station, KOACH filters, OL etc). * Power up rack. === Main Assembly === * Remove crossbars below BF and SF. * Set SF damper to 4 mm clearance. * Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm). * Adjust jacks to nominal height. * Do up all EQ stops etc (except SF). * Remove geophones (temporarily, for craning). * Crane suspension into tank. * Hook LBB Cu ring. * Hook LBB. * Crane vacuum tank lid+ring back on. * Remove vacuum tank lid (only) and store on pallet. * Add ballast to LBB. * Replace geophones. * Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks. * Unlock IP and adjust to center with jacks. === Electronics === * Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones). * Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring. * Reconnect in-vacuum cabling. * Adjust in-air cabling to match 135° rotation of BS. * Reconnect in-air cables. (all but 4) == 2017-06-12 == === Main Assembly === * Check pitch/roll of SF and adjust trim as required. * Prepare LBB. * Attach LBB outriggers and rod receptacles. * Prepare LBB Cu ring. * Remove from tank, fix incompletely threaded holes, reinstall in tank. * Lay down spacers to protect magnets (in next step). * Prepare LBB magnet ring. * Disassemble. * Pass pieces into tank. * Reassemble on top of Cu ring. * Install LBB damper. * Bind LBB damper rings together with slings. * Remove vacuum tank lid and ring. * Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method. === Electronics === * Cable and test PI yaw stepper. * Cable and test PI vertical stepper. * Cable and test PI horizontal steppers. * Cable and test PI horizontal LVDTs. * Finalize OSEM cable lengths and update D1503600, E1503091 and Sato-san's spreadsheet. * Recount cables in box and in test hang, and update Sato-san's spreadsheet. * Cable and test PI vertical LVDT. * Debug/fix PI vertical LVDTs #0 and #2. * Debug/fix geophone #1. == 2017-05-29 == === Facilities === === Design/Purchasing === * Get more cable ties. === Main Assembly === * Reinstall blades in LBB blade units. * Do load test on LBB blade units. === Electronics === * Route BF/... cabling up past SF to PI. * Route SF cabling up to PI. * Add Type 3 extensions to SF/... cables. * Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame). * Move in-air cabling to match flange positions. == 2017-05-22 == === Facilities === === Design/Purchasing === * Design, order modifications to LBB blade springs. * Get more duckboards. === Main Assembly === * Find geophone adapter plates. * Ultrasonically clean geophone adapter plates and screws. * Install geophone adapter plates. * Get more PEEK clamp pieces from Sato-san and install. * Lift PI and hang LBB damper ring. * Crane PI back in. * Install rod, this time with hex cable clamp. * Re-hook SF/... section. * Trim SF/... section. * Install geophones. === Electronics === * Debug and calibrate SF LVDT. * Debug stepper motors. * Make two more (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8. == 2017-05-15 == === Facilities === * Get more UHV foil. * Clear spaces for PR2 bellows work and SR2 ladder installation on 5/15. * Fix safety bar on -X side of assembly frame (move to other side of pillars and attach more securely). === Main Assembly === * Secure arc weights with M8 nuts. * Remove PI. * Unjam PI-SF rod. * Remove SF cap. * Remove blades from LBB blade units and send off for rework. * Install remaining cable clamps on PI. * Remove one Cu damper segment from SF cap and reconfigure remaining two to be symmetrical. * Decide pattern of SF damper ring magnets (72 pieces in 2/3 of the original ring). * Install magnets on SF damper ring. === Electronics === * Make PI vertical/yaw stepper in-air adapter cable per E1503600-v13 Sheet 7. == 2017-05-09 == === Safety === * Install safety bars === Continue PI Prep === * Find, install and wire up PI yaw stepper and bracket. * Test IP. * Install LBB blades in blade units. * Check LBB blade unit alignment (was off by 21 mm due to blades being too long). === Hanging SF/BF/IRM/IM/RM/BS === * Fix centering of SF/... section. === Electronics === * Count used, unused, broken and needed in-vacuum cables and send data to Sato-san. * Check connections in new geophone adapters (they turned out to be new-style). * Decide final length for BS OSEM cables. == 2017-04-24 == === Continue PI Prep === * Install LLB blades. * Install LLB blade units in PI. === Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) === * Crane in PI. * Connect up SF/... . * Measure overweight if any. === Electronics (mostly Enzo, Mark) === * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) == Real-time and SUMCON models (mostly Perry, Mark) == * Understand/document/debug Kokeyama-san's DIO stuff. * Measure LPCD and HPCD output filter response. * Design and install software compensation filters for LPCD and HPCD output filters. == 2017-04-17 == === SF/BF/... === * Trim BF to correct pitch/roll. * Install temporary ballast mass in SF. * Lift SF/BF/... and check SF pitch/roll balance and overall weight. === Continue PI Prep === * Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender. * Install fishing rod. * Enlarge ring of crane adapter. * Find table, weights, etc for use with LBB blade bending jigs. * Set up LBB blade tensioning jig. === Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry) === * Test SF fishing rod stepper. * Debug TM-H4. === Electronics (mostly Enzo, Mark) === * Work with Miyo-kun to get pico drivers added to BS rack and screens * Update E1503600 with DIO card for HPCDs, etc, etc. * Decide final length for BS OSEM cables (Enzo, Mark, Fabian) * Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark) == 2017-04-03 == |
VIS Type B To-Do List - Archived Items
2017-06-26
BS Prism/Flag gluing
Organize transport company for Kashiwa->Kamioka
- Collect mirror, mirror box, tools etc from Kashiwa.
- Ship mirror to Kamioka via Akabou.
- Ship gluing tools to Kamioka via Yu-Pack.
- Get 5 mm prisms cut down to 3 mm (ATC, Hirata-san).
- Get magnet jigs remade (ATC).
Design/Documentation/Planning
- Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).
Electronics
- Fix #0 LVDT actuator coil.
2017-06-26
BS Prism/Flag gluing
- Push Hirose-san to set exact date.
Organize NAOJ vehicle for Mitaka->Kashiwa
- Collect all items required.
- Mirror box.
Prisms. (not found!)
- Stub flags.
Magnets: SmCo, 2 mm diameter, 3 mm long
- Prism jigs
- Flag jigs
- Glue magnets to flags, 2 N, 2 S.
- Organize clean suits.
- Make a list of people's sizes
- Get Mark/Enzo to bring from Kamioka.
Main Assembly
- Adjust pitch/yaw/vertical of dummy optic.
- Crane tank lid on.
- Start TFs.
Electronics
- Wash extra F-F gender benders.
- Fix broken picomotor cable.
- Sort out naming convention for PI LVDTs, geophones and horizontal steppers.
LSOL
- Assist Simon with hardware installation of LSOL.
- Assist Simon with modifications to realtime model for LSOL.
Real-time and SUMCON models
- Derive and install PI LVDT matrices.
- Check LSOL section of k1visbs model.
2017-06-19
Facilities
- Remove cling wrap from stuff.
- Plug stuff back in (charging station, KOACH filters, OL etc).
- Power up rack.
Main Assembly
- Remove crossbars below BF and SF.
- Set SF damper to 4 mm clearance.
- Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).
- Adjust jacks to nominal height.
- Do up all EQ stops etc (except SF).
- Remove geophones (temporarily, for craning).
- Crane suspension into tank.
- Hook LBB Cu ring.
- Hook LBB.
- Crane vacuum tank lid+ring back on.
- Remove vacuum tank lid (only) and store on pallet.
- Add ballast to LBB.
- Replace geophones.
- Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks.
- Unlock IP and adjust to center with jacks.
Electronics
- Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).
- Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
- Reconnect in-vacuum cabling.
- Adjust in-air cabling to match 135° rotation of BS.
- Reconnect in-air cables. (all but 4)
2017-06-12
Main Assembly
- Check pitch/roll of SF and adjust trim as required.
- Prepare LBB.
- Attach LBB outriggers and rod receptacles.
- Prepare LBB Cu ring.
- Remove from tank, fix incompletely threaded holes, reinstall in tank.
- Lay down spacers to protect magnets (in next step).
- Prepare LBB magnet ring.
- Disassemble.
- Pass pieces into tank.
- Reassemble on top of Cu ring.
- Install LBB damper.
- Bind LBB damper rings together with slings.
- Remove vacuum tank lid and ring.
- Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.
Electronics
- Cable and test PI yaw stepper.
- Cable and test PI vertical stepper.
- Cable and test PI horizontal steppers.
- Cable and test PI horizontal LVDTs.
- Finalize OSEM cable lengths and update D1503600, E1503091 and Sato-san's spreadsheet.
- Recount cables in box and in test hang, and update Sato-san's spreadsheet.
- Cable and test PI vertical LVDT.
- Debug/fix PI vertical LVDTs #0 and #2.
- Debug/fix geophone #1.
2017-05-29
Facilities
Design/Purchasing
- Get more cable ties.
Main Assembly
- Reinstall blades in LBB blade units.
- Do load test on LBB blade units.
Electronics
- Route BF/... cabling up past SF to PI.
- Route SF cabling up to PI.
- Add Type 3 extensions to SF/... cables.
- Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame).
- Move in-air cabling to match flange positions.
2017-05-22
Facilities
Design/Purchasing
- Design, order modifications to LBB blade springs.
- Get more duckboards.
Main Assembly
- Find geophone adapter plates.
- Ultrasonically clean geophone adapter plates and screws.
- Install geophone adapter plates.
- Get more PEEK clamp pieces from Sato-san and install.
- Lift PI and hang LBB damper ring.
- Crane PI back in.
- Install rod, this time with hex cable clamp.
- Re-hook SF/... section.
- Trim SF/... section.
- Install geophones.
Electronics
- Debug and calibrate SF LVDT.
- Debug stepper motors.
- Make two more (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8.
2017-05-15
Facilities
- Get more UHV foil.
- Clear spaces for PR2 bellows work and SR2 ladder installation on 5/15.
- Fix safety bar on -X side of assembly frame (move to other side of pillars and attach more securely).
Main Assembly
- Secure arc weights with M8 nuts.
- Remove PI.
- Unjam PI-SF rod.
- Remove SF cap.
- Remove blades from LBB blade units and send off for rework.
- Install remaining cable clamps on PI.
- Remove one Cu damper segment from SF cap and reconfigure remaining two to be symmetrical.
- Decide pattern of SF damper ring magnets (72 pieces in 2/3 of the original ring).
- Install magnets on SF damper ring.
Electronics
- Make PI vertical/yaw stepper in-air adapter cable per E1503600-v13 Sheet 7.
2017-05-09
Safety
- Install safety bars
Continue PI Prep
- Find, install and wire up PI yaw stepper and bracket.
- Test IP.
- Install LBB blades in blade units.
- Check LBB blade unit alignment (was off by 21 mm due to blades being too long).
Hanging SF/BF/IRM/IM/RM/BS
- Fix centering of SF/... section.
Electronics
- Count used, unused, broken and needed in-vacuum cables and send data to Sato-san.
- Check connections in new geophone adapters (they turned out to be new-style).
- Decide final length for BS OSEM cables.
2017-04-24
Continue PI Prep
- Install LLB blades.
- Install LLB blade units in PI.
Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)
- Crane in PI.
- Connect up SF/... .
- Measure overweight if any.
Electronics (mostly Enzo, Mark)
- Update E1503600 with DIO card for HPCDs, etc, etc.
- Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
Real-time and SUMCON models (mostly Perry, Mark)
- Understand/document/debug Kokeyama-san's DIO stuff.
- Measure LPCD and HPCD output filter response.
- Design and install software compensation filters for LPCD and HPCD output filters.
2017-04-17
SF/BF/...
- Trim BF to correct pitch/roll.
- Install temporary ballast mass in SF.
- Lift SF/BF/... and check SF pitch/roll balance and overall weight.
Continue PI Prep
- Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender.
- Install fishing rod.
- Enlarge ring of crane adapter.
- Find table, weights, etc for use with LBB blade bending jigs.
- Set up LBB blade tensioning jig.
Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)
- Test SF fishing rod stepper.
- Debug TM-H4.
Electronics (mostly Enzo, Mark)
- Work with Miyo-kun to get pico drivers added to BS rack and screens
- Update E1503600 with DIO card for HPCDs, etc, etc.
- Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
- Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)
2017-04-03
PI Move
- General prep
- Decide if air shower needs to be moved.
- Triple-check dimensions around second-floor parking spot for PI; decide best place for pallet.
- Check for obstacles along path around -X side of cleanbooth.
- Find/clean Saito-sensei's PI lifting adapter and any needed fasteners.
- Check both crane remote controls (clean and dirty) are charged.
- Prepare PI for moving.
- Remove accelerometers and store safely.
- Remove large weights. (How? With forklift at last minute? Where to?)
- Remove arc weights (move some to second floor, wrap rest for storage).
- Attach lifting plates.
- Wrap with clingwrap, cover with spare cleanbag.
- Remove old cabling from PI to rack.
- Prepare second floor for receiving PI.
- Clean and clingwrap pallet.
- Find metal plates and/or duckboards for on top of pallets.
- Move BS cables on -Y side of tank off top of beam.
- Find shims (about 75 mm high) to put on beam where cables were, to help support pallet.
- Clear path to remove PI with forklift.
- Move any obstacles identified previously.
- Shutdown BS/PR2 racks and move electrical cables.
- Move any stored items on -Y side of portable cleanroom.
- Move portable cleanroom towards -Y.
- Move worktables from next to BS/PR2 racks.
- Move PI
- Disconnect fan cables, curtain (Miyoki-san).
- Unzip ceiling panel.
- Crane pallet into cleanbooth.
- Lay foil on pallet.
- Forklift PI to -X,+Y corner of cleanbooth
- Crane PI into clean booth.
- Cleanup
- Zip up ceiling panel.
- Reconnect fan cables, curtain (Miyoki-san).
- Replace tables near BS/PR2 racks
- Move portable cleanroom back to original spot.
- Re-lay electrical cables.
- Power up racks.
Electronics (mostly Enzo, Mark)
- Make more anti-feedthrough adapters.
Real-time and SUMCON models (mostly Perry, Mark)
- Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary.
- Get Perry (and Enzo) set up with SUMCON.
- Update SUMCON model of full BS.
- Do cut-down SUMCON model of just payload hanging from fixed BS.
- Compare measured TFs to cut-down model(s).