Line 4: Line 4:

== 2017-09-25 ==

=== Main Assembly Sequence ===
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Fix #1 geophone adapter cable.
 * Unlock IP; use jacks and FRs to center.
 * (Debug issue with tilted IRM!)

=== LBB Sequence ===
 * Unclamp LBB ring sandwich; fully suspend Cu ring.
 * Unscrew LBB from tank brackets.
 * Hook LBB.
 * Remove TBD amount of spacers from between LBB and tank brackets.
 * Set LBB blade stops to nominal height.
 * Extend foot screws on LBB to just barely support LBB.
 * Adjust height of LBB magnet ring to set proper gap (4 mm??).
 * Retract LBB foot screws.
 * Add temporary ballast to LBB until LBB blades just barely sink below stops.
 * Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
 * Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
 * Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.

VIS Type B BS To-Do List - Archived Items

BS To Do List

2017-09-25

Main Assembly Sequence

  • Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Fix #1 geophone adapter cable.
  • Unlock IP; use jacks and FRs to center.
  • (Debug issue with tilted IRM!)

LBB Sequence

  • Unclamp LBB ring sandwich; fully suspend Cu ring.
  • Unscrew LBB from tank brackets.
  • Hook LBB.
  • Remove TBD amount of spacers from between LBB and tank brackets.
  • Set LBB blade stops to nominal height.
  • Extend foot screws on LBB to just barely support LBB.
  • Adjust height of LBB magnet ring to set proper gap (4 mm??).
  • Retract LBB foot screws.
  • Add temporary ballast to LBB until LBB blades just barely sink below stops.
  • Check distance from LBB to main beam height (or other suitable reference); adjust by screwing receptacles.
  • Set foot screws to give ≈5 mm (or TBD) movement range of LBB below nominal.
  • Set stop on LBB blades to give ≈3 mm (or TBD, less than Cu-magnet gap) of LBB above nominal.

2017-09-19

(No work Monday 9/18)

Main Assembly Sequence

  • Debug BF LVDT actuation.
  • Check F0 yoke height (top of coil former should be 37.5 mm above bottom of recess in top of baseplate) 36mm.
  • Test all PI items:
    • Yaw stepper (tested, not clearly working).
    • F0 LVDT sensing
    • F0 LVDT actuation
    • Calibrate F0 LVDT.
    • Horizontal LVDT sensing
    • Horizontal LVDT actuation
    • Geophones (issues with driver, cables, descramblers)
  • Lock the F0 and SF keystones and measure the resonance frequency of the BF GAS 2 Measurements: f1=0.443 Hz, f2=0.454 Hz.
  • Lock the SF and BF keystones and measure the resonance frequency of the F0 GAS 2 Measurements: f1=0.208 Hz, f2=0.210 Hz.
  • Double check BS pitch with OL.
  • Adjust SF damper ring to correct gap.
  • Install lock nuts on F0 GAS FR at TBD positions.
  • Lock BF and F0 keystones (but not SF keystone).

  • Lock RM to BS, IRM to IM and IM to RM.
  • Lock RM, IRM and BF (but not SF) to security structure.
  • Lock IP.
  • Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
  • Attach lifting fixture.
  • Remove BF- and SF-level crossbars.
  • Remove geophones for craning.
  • Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
  • Attach lifting plates.

Tank Preparation Sequence

  • Attach Cu segments to LBB damper ring.
  • Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
  • Crane tank lid off.
  • Crane LBB damper rings to top of tank and suspend.
  • Crane suspension out of assembly frame.
  • Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
  • Crane suspension into tank and connect upper rods to LBB Cu ring.
  • Fix poorly seated head.
  • Unlock suspension and readjust.

In parallel, time permitting

  • Fix issue with geophone distributor.

2017-09-11

Main Assembly Sequence

  • Debug other actuation.
  • Remove F0-SF rod and reinstall with hex cable clamp.
  • Route cables up past hex cable clamps.
  • Adjust SF trim mass for pitch/roll/vertical.
  • Route all SF/... cables through to the flange and test.
  • Cable all PI items through to the flange.
  • Disconnect the SS from the AF.
  • Recheck/adjust SF/... yaw.
  • Roughly level the PI so as to make the SS vertical.
  • Unlock the IP and adjust the level of the PI and the horizontal FRs to center the IP.
  • Test all PI items:
    • Horizontal steppers
    • Geophones
  • Lock the F0 and BF keystones and measure the resonance frequency of the SF GAS. 425 mHz

In parallel, time permitting

  • Fix links to ADC_MONITOR screens.
  • Check that all Take/Restore Safe.snap buttons work.
  • Check that we still have all LBB parts (there was an issue with borrowed lock nuts).
  • Wipe LLB damper parts with ethanol.
  • Install LBB Cu damper ring in tank (less Cu for now).
  • Apply magnets to LBB Magnet rings.
  • Clean rust from screw holes in LBB magnet ring.

2017-09-04

Main Assembly Sequence

  • Crane out SF.
  • Raise BF cap and retrieve lost hex cable clamp PEEK piece.
  • Crane in SF.
  • Install SF-BF rod with hex cable clamp.
  • Route cables via hex cable clamp up to below SF.
  • Adjust BF ballast mass for total weight and pitch/roll.
  • Look for missing screw from SF damper Cu segment in washed screws bag and reinstall.
  • Adjust yoke on SF to put top of secondary at 6 mm above top of baseplate (or to give ≈0 counts at nominal height).
  • Calibrate SF LVDT.
  • Install SF main ballast mass.
  • Cable and test SF fishing rod stepper.
  • Add SF cap.
  • Lift and weigh SF/... section.

In parallel

  • Rearrange arc weights on PI to allow installation of magic wand.
  • Install magic wand on PI.
  • Rearrange magnets on SF damper magnet ring for full three Cu segments.
  • Find Ni-plated rods for SF damper magnet ring and do fit check.
  • Find PI-SF rod with 8 mm heads and matching receptacles and do fit check.
  • Get Cu O-rings for feedthroughs.
  • Recalibrate remachined LBB springs and choose best three.

2017-08-28

Main Assembly

  • Wrap new IM bottom ballast masses (Mozumi).
  • Install new IM masses.
  • Set up optical level.
  • Adjust IM ballast mass to give desired roll/pitch/vertical.
  • Level BF.
  • Cable BF LVDT, test and calibrate.
  • Adjust top of IRM to level.
  • Install IRM side panels.
  • Install IRM OSEMs.
  • Cable IRM OSEMs and test.
  • Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops.
  • Add extra ballast mass to BF.
  • Add BF cap but don't anchor cables.
  • Cable and test BF cap picos.
  • Lift BF/IRM/IM/RM/BS and weigh.
  • Adjust BF ballast if necessary.
  • Crane in SF.
  • Remove Kapton tape from PI.

Electrical

  • Remove cling wrap in BF and install vacuum-compatible heat shrink.
  • Remove cling wrap on connections for PI vertical stepper and install vacuum-compatible heat shrink (needs wider diameter heat shrink or smaller pins).
  • Rewire PI horizontal steppers with vacuum-compatible cable.

2017-08-21

Main Assembly

  • Wrap new IM bottom ballast masses (Mozumi).
  • Install new IM masses.
  • Set up optical level.
  • Adjust IM ballast mass to give desired roll/pitch/vertical.
  • Level BF.
  • Cable BF LVDT, test and calibrate.
  • Adjust top of IRM to level.
  • Install IRM side panels.
  • Install IRM OSEMs.
  • Cable IRM OSEMs and test.
  • Adjust IRM and IRM OSEMs to get good alignment of IRM OSEMs and IM-IRM stops.

Electrical

  • Remove cling wrap in BF and install vacuum-compatible heat shrink.
  • Adjust yoke on BF to put top of secondary at 3.5 mm above top of baseplate (or to give ≈0 counts at nominal height).

Real-time and SUMCON models

  • Create a proper DAC Monitor MEDM screen.
  • Improve ADC Monitor MEDM screen.

2017-08-16

Facilities

  • Move cardboard box with old BF to storage.
  • Tidy up Hirata-san's stuff in genkan of cleanbooth.

Electronics

  • Return spare two Type5-2.2 cables to Sato-san's store.
  • Rip out remaining old in-air cabling.
  • Reinstall LVDT chassis.

Main Assembly

  • Remove LBB blade assemblies from PI.
  • Remove LBB blades from holders.
  • Remove LBB rings.
  • Send rings for recleaning.

2017-08-07

Electronics

  • Route new (longer) TM OSEM cables.
  • Recable/test IM-PIT/ROL/YAW picos.
  • Recable/test BF Stepper.

Main Assembly

  • Weigh filter lifting rod plus whatever other items used by Hirata-san in BF load capacity measurement.
  • Finish adjusting in/out of TM OSEMs.
  • Hang RM.
  • Remove endplate of IM, check pico centering.
  • Weigh/trim IM/RM/TM
  • Bring in BF.
  • Install IRM top plate.
  • Hook IM/RM/BS.

2017-07-31

Facilities

  • Re-secure floor panels around tank.
  • Wipe entire frame; blow dust out of grooves.
  • Organize new OL for setting BS pitch (Fabian).

Design/Documentation/Planning

  • Do version of 3D CAD with final-hang arrangement of suspension and LBB damper stuff (Hirata-san).

Electronics

Main Assembly

  • Remove dummy BS from RM.
  • Install coil-only OSEMs.
  • Measure coil resistances of wide-mouth OSEMs, new coil-only OSEMS (for Michimura-san).
  • Look up log book to find serial numbers of old coil+sensor RM OSEMs.
    • 2016-09-07: H1 = #22, H2 = #23, H3 = #25, H4 = #26
  • Pack RM coil+sensor OSEMs, label them with original serial numbers, and return them to Akutsu-san.
  • Reassemble top of AF.
  • Check verticality of AF, height of crossbars, centering of optical table.
  • Move NB-03 jacks at PI level of AF to top level.
  • Set height, level of IM support screws.
  • Install IM.

2017-07-24

Electronics

  • Look for LVDT driver box Syyxx3134.
  • Make sure SR3 boxes have notes on their JGW-S.... document pages.

Main Assembly

  • Remove BF-SF cables (note which had gender benders and which had extensions).
  • Remove SF.
  • Remove SF SS ring and poles.
  • Move (or remove) SF AF crossbars.
  • Remove IRM.
  • Remove old BF.
  • Remove RM and dummy BS.
  • Characterize blades (1,2,3,4,5,6,7).
  • Rebuild BF.
  • Check gluing result.
  • Cleanup optic after failed secondary prism bonds.
  • Cleanup jigs/prisms after failed secondary prism bonds.
  • Reglue secondary prisms.

2017-07-17

Facilities

  • Get blue underwear for Yoshioka-kun.

Design/Documentation/Planning

  • LBB ballast mass.
    • Do improved mass budget.

Main Assembly

  • Try to remove galled pole.
    • Consult with Takahashi-san.
    • Get alcohol in squirt bottle.
    • Try removing pole with alcohol as lubricant.
  • Inspect, finish setting up filter service area.
  • Search for wire.
  • Glue flags/prisms.

2017-07-10

Facilities

BS Prism/Flag gluing

  • Search for prisms (Mark/Enzo).
  • Clean magnet jigs, prisms (Hirata).
  • Assemble (with glue) magnet jigs. (Mark)
  • Glue flags/prisms.

Design/Documentation/Planning

  • Order longer threaded rods for arc weights on PI (Hirata-san).
  • Final ballast mass design for BF and SF.
    • Do revised drawings (Hirata-san).
    • Decide final numbers.
    • Get quote.
    • Place order.
  • Final ballast mass for IM.
    • Final design (Fabian).
    • Drawings (Hirata-san).
    • Get quotes (Hirata-san)
    • Place order (Hirata-san).
  • Measure total LBB load capacity.

Electronics

  • Document LVDT driver rebuild and other changes.

Main Assembly

  • Search for wire (Mark/Enzo).
  • Experiment with rearranging arc weights to accommodate magic wand.
  • Remove arc weights; load onto LBB; measure total load capacity.
  • Unload arc weights and store.
  • Disconnect cables (Mark/Enzo).
  • Connect tank lid to tank ring (Mark/Enzo).
  • Dismantle LBB and rings.
    • Remove screw feet.
    • Replace blocks.
  • Reinstall spacers and clamps on LBB damper rings.
  • Unhook rods supporting LBB intermediate ring.
  • Crane out suspension.
  • Crane down rings.
  • Remove rings.
  • Send rings for recleaning.
  • Reinstall AF crossbars and jacks.

2017-06-26

BS Prism/Flag gluing

  • Organize transport company for Kashiwa->Kamioka

  • Collect mirror, mirror box, tools etc from Kashiwa.
  • Ship mirror to Kamioka via Akabou.
  • Ship gluing tools to Kamioka via Yu-Pack.
  • Get 5 mm prisms cut down to 3 mm (ATC, Hirata-san).
  • Get magnet jigs remade (ATC).

Design/Documentation/Planning

  • Do version of 3D CAD with test-hang arrangement of suspension and LBB damper stuff (Hirata-san).

Electronics

  • Fix #0 LVDT actuator coil.

2017-06-26

BS Prism/Flag gluing

  • Push Hirose-san to set exact date.
  • Organize NAOJ vehicle for Mitaka->Kashiwa

  • Collect all items required.
    • Mirror box.
    • Prisms. (not found!)

    • Stub flags.
    • Magnets: SmCo, 2 mm diameter, 3 mm long

    • Prism jigs
    • Flag jigs
  • Glue magnets to flags, 2 N, 2 S.
  • Organize clean suits.
    • Make a list of people's sizes
    • Get Mark/Enzo to bring from Kamioka.

Main Assembly

  • Adjust pitch/yaw/vertical of dummy optic.
  • Crane tank lid on.
  • Start TFs.

Electronics

  • Wash extra F-F gender benders.
  • Fix broken picomotor cable.
  • Sort out naming convention for PI LVDTs, geophones and horizontal steppers.

LSOL

  • Assist Simon with hardware installation of LSOL.
  • Assist Simon with modifications to realtime model for LSOL.

Real-time and SUMCON models

  • Derive and install PI LVDT matrices.
  • Check LSOL section of k1visbs model.

2017-06-19

Facilities

  • Remove cling wrap from stuff.
  • Plug stuff back in (charging station, KOACH filters, OL etc).
  • Power up rack.

Main Assembly

  • Remove crossbars below BF and SF.
  • Set SF damper to 4 mm clearance.
  • Find wrenches for vacuum tank jacks (41 mm and possibly 75 mm).
  • Adjust jacks to nominal height.
  • Do up all EQ stops etc (except SF).
  • Remove geophones (temporarily, for craning).
  • Crane suspension into tank.
  • Hook LBB Cu ring.
  • Hook LBB.
  • Crane vacuum tank lid+ring back on.
  • Remove vacuum tank lid (only) and store on pallet.
  • Add ballast to LBB.
  • Replace geophones.
  • Unlock all but IP and check pendulum is centered in security structure. Adjust with jacks.
  • Unlock IP and adjust to center with jacks.

Electronics

  • Disconnect in-vacuum and in-air cabling from feedthroughs (label in-vacuum ones).
  • Remove port covers where feedthroughs will go, move feedthroughs from assembly frame and install on vacuum tank ring.
  • Reconnect in-vacuum cabling.
  • Adjust in-air cabling to match 135° rotation of BS.
  • Reconnect in-air cables. (all but 4)

2017-06-12

Main Assembly

  • Check pitch/roll of SF and adjust trim as required.
  • Prepare LBB.
    • Attach LBB outriggers and rod receptacles.
  • Prepare LBB Cu ring.
    • Remove from tank, fix incompletely threaded holes, reinstall in tank.
    • Lay down spacers to protect magnets (in next step).
  • Prepare LBB magnet ring.
    • Disassemble.
    • Pass pieces into tank.
    • Reassemble on top of Cu ring.
  • Install LBB damper.
    • Bind LBB damper rings together with slings.
    • Remove vacuum tank lid and ring.
    • Crane rings up to install height, hook LBB magnet ring and support LBB Cu ring by TBD method.

Electronics

  • Cable and test PI yaw stepper.
  • Cable and test PI vertical stepper.
  • Cable and test PI horizontal steppers.
  • Cable and test PI horizontal LVDTs.
  • Finalize OSEM cable lengths and update D1503600, E1503091 and Sato-san's spreadsheet.
  • Recount cables in box and in test hang, and update Sato-san's spreadsheet.
  • Cable and test PI vertical LVDT.
  • Debug/fix PI vertical LVDTs #0 and #2.
  • Debug/fix geophone #1.

2017-05-29

Facilities

Design/Purchasing

  • Get more cable ties.

Main Assembly

  • Reinstall blades in LBB blade units.
  • Do load test on LBB blade units.

Electronics

  • Route BF/... cabling up past SF to PI.
  • Route SF cabling up to PI.
  • Add Type 3 extensions to SF/... cables.
  • Move vacuum flanges to positions on assembly frame more convenient for next stage (accessible from second floor, one on each corner of frame).
  • Move in-air cabling to match flange positions.

2017-05-22

Facilities

Design/Purchasing

  • Design, order modifications to LBB blade springs.
  • Get more duckboards.

Main Assembly

  • Find geophone adapter plates.
  • Ultrasonically clean geophone adapter plates and screws.
  • Install geophone adapter plates.
  • Get more PEEK clamp pieces from Sato-san and install.
  • Lift PI and hang LBB damper ring.
  • Crane PI back in.
  • Install rod, this time with hex cable clamp.
  • Re-hook SF/... section.
  • Trim SF/... section.
  • Install geophones.

Electronics

  • Debug and calibrate SF LVDT.
  • Debug stepper motors.
  • Make two more (in-air) geophone unscrambler cables per E1503600-v13 Sheet 8.

2017-05-15

Facilities

  • Get more UHV foil.
  • Clear spaces for PR2 bellows work and SR2 ladder installation on 5/15.
  • Fix safety bar on -X side of assembly frame (move to other side of pillars and attach more securely).

Main Assembly

  • Secure arc weights with M8 nuts.
  • Remove PI.
  • Unjam PI-SF rod.
  • Remove SF cap.
  • Remove blades from LBB blade units and send off for rework.
  • Install remaining cable clamps on PI.
  • Remove one Cu damper segment from SF cap and reconfigure remaining two to be symmetrical.
  • Decide pattern of SF damper ring magnets (72 pieces in 2/3 of the original ring).
  • Install magnets on SF damper ring.

Electronics

  • Make PI vertical/yaw stepper in-air adapter cable per E1503600-v13 Sheet 7.

2017-05-09

Safety

  • Install safety bars

Continue PI Prep

  • Find, install and wire up PI yaw stepper and bracket.
  • Test IP.
  • Install LBB blades in blade units.
  • Check LBB blade unit alignment (was off by 21 mm due to blades being too long).

Hanging SF/BF/IRM/IM/RM/BS

  • Fix centering of SF/... section.

Electronics

  • Count used, unused, broken and needed in-vacuum cables and send data to Sato-san.
  • Check connections in new geophone adapters (they turned out to be new-style).
  • Decide final length for BS OSEM cables.

2017-04-24

Continue PI Prep

  • Install LLB blades.
  • Install LLB blade units in PI.

Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)

  • Crane in PI.
  • Connect up SF/... .
  • Measure overweight if any.

Electronics (mostly Enzo, Mark)

  • Update E1503600 with DIO card for HPCDs, etc, etc.
  • Decide final length for BS OSEM cables (Enzo, Mark, Fabian)

Real-time and SUMCON models (mostly Perry, Mark)

  • Understand/document/debug Kokeyama-san's DIO stuff.
  • Measure LPCD and HPCD output filter response.
  • Design and install software compensation filters for LPCD and HPCD output filters.

2017-04-17

SF/BF/...

  • Trim BF to correct pitch/roll.
  • Install temporary ballast mass in SF.
  • Lift SF/BF/... and check SF pitch/roll balance and overall weight.

Continue PI Prep

  • Finish reattaching repaired LVDT coil(s) and redoing connectors with correct gender.
  • Install fishing rod.
  • Enlarge ring of crane adapter.
  • Find table, weights, etc for use with LBB blade bending jigs.
  • Set up LBB blade tensioning jig.

Hanging BF/IRM/IM/RM/BS (mostly Mark, Fabian, Perry)

  • Test SF fishing rod stepper.
  • Debug TM-H4.

Electronics (mostly Enzo, Mark)

  • Work with Miyo-kun to get pico drivers added to BS rack and screens
  • Update E1503600 with DIO card for HPCDs, etc, etc.
  • Decide final length for BS OSEM cables (Enzo, Mark, Fabian)
  • Make table of ADC/DAC assignments and check for consistency with D1503600 and k1visbs (Enzo, Mark)

2017-04-03

PI Move

  • General prep
    • Decide if air shower needs to be moved.
    • Triple-check dimensions around second-floor parking spot for PI; decide best place for pallet.
    • Check for obstacles along path around -X side of cleanbooth.
    • Find/clean Saito-sensei's PI lifting adapter and any needed fasteners.
    • Check both crane remote controls (clean and dirty) are charged.
  • Prepare PI for moving.
    • Remove accelerometers and store safely.
    • Remove large weights. (How? With forklift at last minute? Where to?)
    • Remove arc weights (move some to second floor, wrap rest for storage).
    • Attach lifting plates.
    • Wrap with clingwrap, cover with spare cleanbag.
    • Remove old cabling from PI to rack.
  • Prepare second floor for receiving PI.
    • Clean and clingwrap pallet.
    • Find metal plates and/or duckboards for on top of pallets.
    • Move BS cables on -Y side of tank off top of beam.
    • Find shims (about 75 mm high) to put on beam where cables were, to help support pallet.
  • Clear path to remove PI with forklift.
    • Move any obstacles identified previously.
    • Shutdown BS/PR2 racks and move electrical cables.
    • Move any stored items on -Y side of portable cleanroom.
    • Move portable cleanroom towards -Y.
    • Move worktables from next to BS/PR2 racks.
  • Move PI
    • Disconnect fan cables, curtain (Miyoki-san).
    • Unzip ceiling panel.
    • Crane pallet into cleanbooth.
    • Lay foil on pallet.
    • Forklift PI to -X,+Y corner of cleanbooth
    • Crane PI into clean booth.
  • Cleanup
    • Zip up ceiling panel.
    • Reconnect fan cables, curtain (Miyoki-san).
    • Replace tables near BS/PR2 racks
    • Move portable cleanroom back to original spot.
    • Re-lay electrical cables.
    • Power up racks.

Electronics (mostly Enzo, Mark)

  • Make more anti-feedthrough adapters.

Real-time and SUMCON models (mostly Perry, Mark)

  • Reroute in-vacuum cables up to SF level; add in-vacuum extension cables if necessary.
  • Get Perry (and Enzo) set up with SUMCON.
  • Update SUMCON model of full BS.
  • Do cut-down SUMCON model of just payload hanging from fixed BS.
  • Compare measured TFs to cut-down model(s).