Size: 2490
Comment:
|
Size: 2537
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]] | |
Line 3: | Line 4: |
[[../ToDoOldSR|Archived To-Do Items]] | [[#EveryWeek|Every Week]] |
Line 5: | Line 6: |
[[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] |
[[#ComingWeeks|Coming Weeks]] |
Line 14: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 16: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 18: | Line 17: |
* Get stuff from [[../WishList]] | * Get stuff from ../WishList |
Line 21: | Line 20: |
== 2017-08-28 == | == Coming Weeks == === 2018-11-05 === ==== SRM (top priority) ==== * LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. * Main sequence * Prepare SF magnet ring. * Install #353 poles * Move NB-03 jacks down. * Crane PI into AF. * Install F0-SF rod (#331) and flying saucer. * Route SF/... cables up to underside of F0. * Do vertical height budget. * Adjust SF trim mass for balance and keystone height. * Measure bounce frequencies. ==== SR2 (low priority) ==== * Set up OL. === 2018-11-12 === ==== SRM ==== * Main sequence * Cable/test IP LVDTs. * Cable/test IP FRs. * Unlock IP and center roughly. * Calibrate IP LVDTs. * Check/adjust alignment of SS. * Add arc weights and geophones (or extra mass equivalent to geophones). * Cable/test geophones. * Improve centering/tuning of IP and SS alignment. |
Line 24: | Line 56: |
== SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). ==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 |
== SR Prep Tasks - To Be Scheduled == === Tunnel === * Check which LVDT cards are in which boxes. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable PI yaw steppers. * Correct flipped connections in SRM PI LVDTs. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 35: | Line 65: |
==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame |
=== Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? |
Line 47: | Line 77: |
==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-05
SRM (top priority)
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
- Main sequence
- Prepare SF magnet ring.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
- Measure bounce frequencies.
SR2 (low priority)
- Set up OL.
2018-11-12
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .