2490
Comment:
|
2167
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]] | |
Line 3: | Line 4: |
[[../ToDoOldSR|Archived To-Do Items]] | [[#EveryWeek|Every Week]] |
Line 5: | Line 6: |
[[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] |
[[#ComingWeeks|Coming Weeks]] |
Line 18: | Line 17: |
* Get stuff from [[../WishList]] | * Get stuff from ../WishList |
Line 21: | Line 20: |
== 2017-08-28 == | == 2018-01-15 == * Cable RM OSEMs to rack. * Setup QPD and do temporary cables to rack. * Do TFs from RM OSEMS to OL pitch/roll. * Make IM OSEMs. * Install load gauge adapter. * Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance. * Test IM picos. == 2018-01-22 == * Crane in BF. * Hook IM. * Route cables via flying saucer up to under BF. * Recheck total mass and pitch/roll balance. * Check BF yaw pico. == 2018-01-28 == * Install IRM. * Adjust IM OSEMs. * Cable IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. * Install pre-calculated BF trim mass. * Lift * Find in-vac cables: * 1 x Type 3-2m * 5 x Type 1-2m * Set up SR2 rack * Get more 1-m power cables and connect up remaining boxes. * Run LAN and power cables for stepper drivers. * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. |
Line 24: | Line 59: |
== SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. |
== SR Prep Tasks - To Be Scheduled == * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * --(Cu O-rings for pod (two sizes).)-- * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough * Hassle Miyo-kun for stepper drivers. * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. |
Line 29: | Line 73: |
==== Order now ==== * Bread boards for SR -> すぐ見積り依頼 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 ==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> すぐ見積り依頼 * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height * SR assembly frame -> 月曜日に見積り依頼 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
* Get safety bars moved. * Get air hose connection moved. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2018-01-15
- Cable RM OSEMs to rack.
- Setup QPD and do temporary cables to rack.
- Do TFs from RM OSEMS to OL pitch/roll.
- Make IM OSEMs.
- Install load gauge adapter.
- Lift IM/RM/SR with LGA, check/adjust total mass and pitch/yaw balance.
- Test IM picos.
2018-01-22
- Crane in BF.
- Hook IM.
- Route cables via flying saucer up to under BF.
- Recheck total mass and pitch/roll balance.
- Check BF yaw pico.
2018-01-28
- Install IRM.
- Adjust IM OSEMs.
- Cable IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
- Install pre-calculated BF trim mass.
- Lift
- Find in-vac cables:
- 1 x Type 3-2m
- 5 x Type 1-2m
- Set up SR2 rack
- Get more 1-m power cables and connect up remaining boxes.
- Run LAN and power cables for stepper drivers.
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
SR Prep Tasks - To Be Scheduled
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
Cu O-rings for pod (two sizes).
- Viton O-ring for under geophone.
- Screws for immobilizing geophone (M4?).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Hassle Miyo-kun for stepper drivers.
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.