Line 2: Line 2:
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]]
Line 3: Line 4:
[[../ToDoOldSR|Archived To-Do Items]] [[#EveryWeek|Every Week]]
Line 5: Line 6:
[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]
[[#ComingWeeks|Coming Weeks]]
Line 18: Line 17:
 * Get stuff from [[../WishList]]  * Get stuff from ../WishList
Line 21: Line 20:
== 2017-08-28 ==
== 2018-02-05 ==
 * --(Check PR3 area for Ø10x10 IM flag magnets.)--
 * --(Make in-air pico adapter cables.)--
 * --(Label in-air pico adapter cables.)--
 * Cable IM picos through to driver.
 * --(Cable BF LVDT through to driver.)--
 * --(Check LVDT resistances and inductances at various points from coils to rack.)--
 * Cable BF FR stepper through to driver.
 * Calibrate LVDT.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Install ballast mass in BF.
 * Build IRM around IM.

== 2018-02-13 ==
 * Cable/test/adjust IM OSEMs.
 * Cable IM OSEMs.
 * Adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Install pre-calculated BF trim mass.

==== Plan for week of 2/19 ====
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Add Cu segments to SF cap.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.

 
Line 24: Line 56:
== SR Prep Tasks ==
=== Design/Purchasing ===
 * Do rough mass budget for SR2/SR3/SRM.
 * Design SR assembly frame.
== SR Prep Tasks - To Be Scheduled ==
 * Review Shoda-san's Guardian.
 * Decide if we're really going to renumber IP channels.
 * Review DIO stuff.
 * Review SR2 model (especially screens, macro text file).
 * Review DAC channel requests.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Screws for geophone to interface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
 * Get geophone circuit boards from Okutomi-san.
 * Find fourth feedthrough
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
Line 29: Line 71:
==== Order now ====
 * Bread boards for SR -> すぐ見積り依頼
 * Include installation work in the contract
 * Total budget = 5MJPY
 * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼

==== Need simple design changes ====
 * SUS wires(3 types) for the LBB
  * Change the length -> すぐ見積り依頼
 * Receptacles for Bread board damper
  * There is a mistake in the PROMEC drawing.
  * Hirata-san will make a new 2D drawing
 * IM wire clamps for SR
  * Need to change the height
 * SR assembly frame -> 月曜日に見積り依頼
  * Mark is checking the design from Fabian
  * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame

==== Need Fabian's input ====
 * Cable clamps for BF,SF and PI -> 方式を決める
  * Design change for the PI clamps, because the SR PIs are NIKHEF ones.
 * Ballast masses for BF and SF
 * 製作に2週間程度
 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
  * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談

==== Need more discussion/checks ====
 * Blade spring assembly for LBB
  * Check the load of the LBB and decide the design load of the springs
  * Correct the length
  * Scale the width of the current blades to design the new blades -> 高橋さんと相談
   * SR用LBBの重さを確認
 * Bread board damper rings
  * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認



=== Electronics ===
 * Get cables/cards for SR3:
  * 5 DSub-37 cables (tent)
  * 5 DSub-15M to DSub-9M adapter cables (tent)
  * 3 DIO cards (tent)
  * 2 DSub-9 FF gender benders (for LVDTs)
  * extra ADC card(s)?
  * extra DAC card(s)?
  * BNC-LEMO adapter (for LVDTs)
  * etc
 * Get safety bars moved.
 * Get air hose connection moved.
 * Glue SR3.
 * Set up SR3 rack.
 * Set up SRM rack.
 * Rebuild two BFs.
 * Disassemble two top filters.
 * Rebuild three top filters.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2018-02-05

  • Check PR3 area for Ø10x10 IM flag magnets.

  • Make in-air pico adapter cables.

  • Label in-air pico adapter cables.

  • Cable IM picos through to driver.
  • Cable BF LVDT through to driver.

  • Check LVDT resistances and inductances at various points from coils to rack.

  • Cable BF FR stepper through to driver.
  • Calibrate LVDT.
  • Test IM picos and BF yaw pico.
  • Test FR.
  • Install ballast mass in BF.
  • Build IRM around IM.

2018-02-13

  • Cable/test/adjust IM OSEMs.
  • Cable IM OSEMs.
  • Adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
  • Install pre-calculated BF trim mass.

Plan for week of 2/19

  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Add Cu segments to SF cap.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

SR Prep Tasks - To Be Scheduled

  • Review Shoda-san's Guardian.
  • Decide if we're really going to renumber IP channels.
  • Review DIO stuff.
  • Review SR2 model (especially screens, macro text file).
  • Review DAC channel requests.
  • Find out (from Takahashi-san) specifications for geophone pod items:
    • Screws for pod (cap-neck and neck-body).
    • Screws for geophone to interface plate.
    • Screws for interface plate to PI.
  • Find or order geophone items.
  • Get geophone circuit boards from Okutomi-san.
  • Find fourth feedthrough
  • Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
  • Design final SF ballast masses (Fabian).
  • Get safety bars moved.
  • Get air hose connection moved.
  • Glue SR3.
  • Set up SR3 rack.
  • Set up SRM rack.
  • Rebuild two BFs.
  • Disassemble two top filters.
  • Rebuild three top filters.