2490
Comment:
|
3218
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]] | |
Line 3: | Line 4: |
[[../ToDoOldSR|Archived To-Do Items]] | [[#EveryWeek|Every Week]] |
Line 5: | Line 6: |
[[#EveryWeek |Every Week]] [[#ComingWeeks |Coming Weeks]] |
[[#ComingWeeks|Coming Weeks]] |
Line 18: | Line 17: |
* Get stuff from [[../WishList]] | * Get stuff from ../WishList |
Line 21: | Line 20: |
== 2017-08-28 == | == 2017-11-13 == * Find collet from maraging rod adapter. * Wrap and label BS parts. * Bring work table from PR2 area. * Bring racks from SRM area. * Take photos and make notes about where SR2 safety bars need to go (time permitting, also SR3). * Look for needed screws, especially for IM. * Bring SR2 into tunnel? * Find mirror gluing items. * Mirror * Mirror box * --(Prisms)-- * Secondary prisms * Magnets * Magnet bases * Prism micrometer stages * --(Prism jigs)-- * Magnet jigs * --(Balance)-- * --(Stirrers)-- * --(Mixing dishes)-- * Lenses for inspecting scribe lines * Procedure document. * EP30 * Glass beads * Rehearse mirror gluing. |
Line 23: | Line 49: |
Line 27: | Line 54: |
* Design SR assembly frame. | |
Line 29: | Line 55: |
Line 30: | Line 58: |
* Bread boards for SR -> すぐ見積り依頼 | * Bread boards for SR -> Orderd. delivery date:10/18-20 |
Line 33: | Line 61: |
* PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼 | * PEEK collet for "Small hexagon"(cable clamp) -> need modification. |
Line 37: | Line 65: |
* Change the length -> すぐ見積り依頼 | * Change the length -> Orderd. delivery date:10/ |
Line 42: | Line 70: |
* Need to change the height * SR assembly frame -> 月曜日に見積り依頼 |
* Need to change the height -> watiting second quote. * SR assembly frame -> Ordered. delivery date:9/27-29 |
Line 62: | Line 90: |
* Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認 |
* Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-11-13
- Find collet from maraging rod adapter.
- Wrap and label BS parts.
- Bring work table from PR2 area.
- Bring racks from SRM area.
- Take photos and make notes about where SR2 safety bars need to go (time permitting, also SR3).
- Look for needed screws, especially for IM.
- Bring SR2 into tunnel?
- Find mirror gluing items.
- Mirror
- Mirror box
Prisms
- Secondary prisms
- Magnets
- Magnet bases
- Prism micrometer stages
Prism jigs
- Magnet jigs
Balance
Stirrers
Mixing dishes
- Lenses for inspecting scribe lines
- Procedure document.
- EP30
- Glass beads
- Rehearse mirror gluing.
SR Prep Tasks
Design/Purchasing
- Do rough mass budget for SR2/SR3/SRM.
- Design final SF ballast masses (Fabian).
Order now
Bread boards for SR -> Orderd. delivery date:10/18-20
- Include installation work in the contract
- Total budget = 5MJPY
PEEK collet for "Small hexagon"(cable clamp) -> need modification.
Need simple design changes
- SUS wires(3 types) for the LBB
Change the length -> Orderd. delivery date:10/
- Receptacles for Bread board damper
- There is a mistake in the PROMEC drawing.
- Hirata-san will make a new 2D drawing
- IM wire clamps for SR
Need to change the height -> watiting second quote.
SR assembly frame -> Ordered. delivery date:9/27-29
- Mark is checking the design from Fabian
- We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame
Need Fabian's input
Cable clamps for BF,SF and PI -> 方式を決める
- Design change for the PI clamps, because the SR PIs are NIKHEF ones.
- Ballast masses for BF and SF
- 製作に2週間程度
- 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
測定に必要な物品の準備 -> 月曜日に高橋さんと相談
Need more discussion/checks
- Blade spring assembly for LBB
- Check the load of the LBB and decide the design load of the springs
- Correct the length
Scale the width of the current blades to design the new blades -> 高橋さんと相談
- SR用LBBの重さを確認
- Bread board damper rings
Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification
Electronics
- Get cables/cards for SR3:
- 5 DSub-37 cables (tent)
- 5 DSub-15M to DSub-9M adapter cables (tent)
- 3 DIO cards (tent)
- 2 DSub-9 FF gender benders (for LVDTs)
- extra ADC card(s)?
- extra DAC card(s)?
- BNC-LEMO adapter (for LVDTs)
- etc