Differences between revisions 1 and 57 (spanning 56 versions)
Revision 1 as of 2017-08-28 08:04:31
Size: 2490
Editor: MarkBarton
Comment:
Revision 57 as of 2018-05-17 12:48:03
Size: 2778
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
[[KAGRA/Subgroups/VIS/TypeB/ToDoOldSR|Archived To-Do Items]]
Line 3: Line 4:
[[../ToDoOldSR|Archived To-Do Items]] [[#EveryWeek|Every Week]]
Line 5: Line 6:
[[#EveryWeek |Every Week]]

[[#ComingWeeks |Coming Weeks]]
[[#ComingWeeks|Coming Weeks]]
Line 14: Line 13:
=== Facilities === ==== Facilities ====
Line 18: Line 17:
 * Get stuff from [[../WishList]]  * Get stuff from ../WishList
Line 21: Line 20:
== 2017-08-28 == == Coming Weeks ==

=== 2018-05-21 ===
==== Main Sequence ====
 * Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.
 * Install IRM sides, and IM OSEMs.
 * Center IM OSEMs (in/out and laterally)
 * Route all cables to underneath BF.
 * Add BF internal ballast mass.
 * Add BF cap.
==== F0/LBB Stuff ====
 * Create LBB blade sets (if screws are available)
 * Install LBB blade sets on PIs #1 and #3 (if possible).
 * Install cable clamps on PIs #1 and #3.
 * Put LBB damper rings in SR3 tank.

=== 2018-05-28 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-06-04 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-06-11 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-06-18 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

Line 24: Line 75:
== SR Prep Tasks ==
=== Design/Purchasing ===
 * Do rough mass budget for SR2/SR3/SRM.
 * Design SR assembly frame.
 * Design final SF ballast masses (Fabian).
==== Order now ====
 * Bread boards for SR -> すぐ見積り依頼
 * Include installation work in the contract
 * Total budget = 5MJPY
 * PEEK collet for "Small hexagon"(cable clamp) -> すぐ見積り依頼
== SR Prep Tasks - To Be Scheduled ==
=== Tunnel ===
 * Calibrate last six IM OSEMs.
 * Install first set of LBB damper rings in SR3 tank.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Finish half-completed geophones.
 * Characterize final top filter blades (from 5/31).
 * Rebuild filters in PIs #1 and #3.
 * Install clamps on PIs #1 and #3.
 * Install LBB units on PIs #1 and #3.
 * Install correct IP in PI #3.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
=== Mitaka or remotely ===
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
 * Review DAC channel requests.
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Install damping filters for SR2.
 * Do buoyancy calculation (see LIGO-T1100616).
Line 35: Line 102:
==== Need simple design changes ====
 * SUS wires(3 types) for the LBB
  * Change the length -> すぐ見積り依頼
 * Receptacles for Bread board damper
  * There is a mistake in the PROMEC drawing.
  * Hirata-san will make a new 2D drawing
 * IM wire clamps for SR
  * Need to change the height
 * SR assembly frame -> 月曜日に見積り依頼
  * Mark is checking the design from Fabian
  * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame

==== Need Fabian's input ====
 * Cable clamps for BF,SF and PI -> 方式を決める
  * Design change for the PI clamps, because the SR PIs are NIKHEF ones.
 * Ballast masses for BF and SF
 * 製作に2週間程度
 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
  * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談

==== Need more discussion/checks ====
 * Blade spring assembly for LBB
  * Check the load of the LBB and decide the design load of the springs
  * Correct the length
  * Scale the width of the current blades to design the new blades -> 高橋さんと相談
   * SR用LBBの重さを確認
 * Bread board damper rings
  * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> 至急確認



=== Electronics ===
 * Get cables/cards for SR3:
  * 5 DSub-37 cables (tent)
  * 5 DSub-15M to DSub-9M adapter cables (tent)
  * 3 DIO cards (tent)
  * 2 DSub-9 FF gender benders (for LVDTs)
  * extra ADC card(s)?
  * extra DAC card(s)?
  * BNC-LEMO adapter (for LVDTs)
  * etc
=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-05-21

Main Sequence

  • Cable and (re-)test TM OSEMs, IM picos, BF yaw pico, BF LVDT and FR.
  • Install IRM sides, and IM OSEMs.
  • Center IM OSEMs (in/out and laterally)
  • Route all cables to underneath BF.
  • Add BF internal ballast mass.
  • Add BF cap.

F0/LBB Stuff

  • Create LBB blade sets (if screws are available)
  • Install LBB blade sets on PIs #1 and #3 (if possible).
  • Install cable clamps on PIs #1 and #3.
  • Put LBB damper rings in SR3 tank.

2018-05-28

Main Sequence

F0/LBB Stuff

2018-06-04

Main Sequence

F0/LBB Stuff

2018-06-11

Main Sequence

F0/LBB Stuff

2018-06-18

Main Sequence

F0/LBB Stuff

2018-06-25

Main Sequence

F0/LBB Stuff

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Calibrate last six IM OSEMs.
  • Install first set of LBB damper rings in SR3 tank.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Finish half-completed geophones.
  • Characterize final top filter blades (from 5/31).
  • Rebuild filters in PIs #1 and #3.
  • Install clamps on PIs #1 and #3.
  • Install LBB units on PIs #1 and #3.
  • Install correct IP in PI #3.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)