2979
Comment:
|
2537
|
Deletions are marked like this. | Additions are marked like this. |
Line 22: | Line 22: |
=== 2018-09-25 === ==== Etc ==== |
=== 2018-11-05 === ==== SRM (top priority) ==== * LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. * Main sequence * Prepare SF magnet ring. * Install #353 poles * Move NB-03 jacks down. * Crane PI into AF. * Install F0-SF rod (#331) and flying saucer. * Route SF/... cables up to underside of F0. * Do vertical height budget. * Adjust SF trim mass for balance and keystone height. * Measure bounce frequencies. ==== SR2 (low priority) ==== * Set up OL. |
Line 25: | Line 42: |
==== SR2 ==== * Open tank and move feedthroughs. * Reconnect in-vacuum cables. * Move in-air cables, with priority on IM OSEMs, then IM picos and BF/SF GAS and FRs. * Remove IM-RM safety bar. * Unlock and realign SF/... section. * Add arc weights and geophones. * Unlock and center IP. |
=== 2018-11-12 === |
Line 35: | Line 44: |
* Add TM OSEM cables. * Set TM pitch and tighten clamps. * Set RM pitch and tighten clamps. * Remove winch system and restore items removed from top of IM. * Suspend and weigh IM/... section. * Add BF crossbars to SS. * Build up SS to BF level. * Suspend IM/... section and adjust ballast/trim masses. * Install feedthroughs on AF (3 available; need to get a 4th). * Arrange power to SRM rack and get it running. * Check the IRIG-B 9999xx fix has been applied (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031||6031]]). ==== SR3 ==== * ''Don't even '''think''' about doing anything with SR3.'' |
* Main sequence * Cable/test IP LVDTs. * Cable/test IP FRs. * Unlock IP and center roughly. * Calibrate IP LVDTs. * Check/adjust alignment of SS. * Add arc weights and geophones (or extra mass equivalent to geophones). * Cable/test geophones. * Improve centering/tuning of IP and SS alignment. |
Line 55: | Line 58: |
* Add SR3 LBB ballast mass. * Install SR3 LEN OL. * Rebuild PI #2 F0 for SRM. * Retrieve BNC-Lemo cable from Nakano-kun. |
* Check which LVDT cards are in which boxes. |
Line 60: | Line 60: |
* Install, cable SR3 PI yaw stepper. | * Install, cable PI yaw steppers. |
Line 62: | Line 62: |
* Grab and configure a picomotor driver as SR2_BF 10.68.150.25. | |
Line 64: | Line 63: |
* Rebuild filter in PI #2 for SRM. * Clean/Replace yoke in PI #2 for SRM. * Install clamps on PI #2 for SRM. * Install LBB blade units on PI #2 for SRM. * Install geophone plates on PI #2 for SRM. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-05
SRM (top priority)
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
- Main sequence
- Prepare SF magnet ring.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
- Measure bounce frequencies.
SR2 (low priority)
- Set up OL.
2018-11-12
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .