Size: 3265
Comment:
|
Size: 2753
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 22: | Line 22: |
=== 2018-10-01 === ==== Etc ==== * Take SRM LVDT driver out of rack for Lucia. ==== SR2 ==== * Turn off KOACH filters in tank and see if BF keystone rises. * Install shelves in small rack, and put sat amps, drivers, etc inside. * Run power and network to pico drivers and steppers. * Test picos and steppers. * Adjust pitch/roll of IM with picos. * Offload BF GAS LVDT offset with FR stepper. * Add arc weights and geophones. (Might have to reserve one geophone for Fujii-Fun - check.) * Cable geophones. (Might have to reserve one cable for Fujii-kun - check.) * Unlock and center IP. * More TFs. |
=== 2018-11-26 === ==== SR3 ==== * Install extension cord for OL. |
Line 38: | Line 27: |
* Add TM OSEM cables. * Set TM pitch and tighten clamps. * Set RM pitch and tighten clamps. * Remove winch system and restore items removed from top of IM. * Suspend and weigh IM/... section. * Add BF crossbars to SS. * Build up SS to BF level. * Suspend IM/... section and adjust ballast/trim masses. * Install feedthroughs on AF (3 available; need to get a 4th). * Arrange power to SRM rack and get it running. * Check the IRIG-B 9999xx fix has been applied (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031||6031]]). |
* Clear space for SRM swap. * Ultrasonically clean metal parts associated with new SRM (except for solblack-coated ones) and tools. * Install IM-IRM safety bar. * Swap SRM glass mass. * Seal geophones. * Find two geophone cables used by Okutomi-san. * Rewire one geophone cable correctly. * Add extra ≈1 kg to SF cap and adjust tilt. * Center and fasten F0 yoke. * Calibrate F0 GAS LVDT. * Add arc weights and geophones. * Test geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables. * Remove crossbars. * Crane suspension into tank. |
Line 50: | Line 44: |
==== SR3 ==== * ''Don't even '''think''' about doing anything with SR3.'' |
==== SR2 (not so low priority) ==== * Run extension cord for OL. * Set up OL cabling. * Set up OL. * Add more arc weights and tweak IP centering. * Replace two borrowed geophones. * Remove tape, writing etc on PI and PI items. * Add new feedthrough to lower part of tank (with Izumi-san-tachi). * Install cable for MIF pico on LBB (with Izumi-san-tachi). * Add ballast mass to LBB. * Install manual yaw adjuster. * Get top plate reduced? |
Line 58: | Line 61: |
* Add SR3 LBB ballast mass. * Install SR3 LEN OL. * Rebuild PI #2 F0 for SRM. * Retrieve BNC-Lemo cable from Nakano-kun. |
* Check which LVDT cards are in which boxes. |
Line 63: | Line 63: |
* Install, cable SR3 PI yaw stepper. | * Install, cable PI yaw steppers. |
Line 65: | Line 65: |
* Grab and configure a picomotor driver as SR2_BF 10.68.150.25. | |
Line 67: | Line 66: |
* Rebuild filter in PI #2 for SRM. * Clean/Replace yoke in PI #2 for SRM. * Install clamps on PI #2 for SRM. * Install LBB blade units on PI #2 for SRM. * Install geophone plates on PI #2 for SRM. |
|
Line 79: | Line 73: |
* Set up SR2 Guardian. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-26
SR3
- Install extension cord for OL.
SRM
- Clear space for SRM swap.
- Ultrasonically clean metal parts associated with new SRM (except for solblack-coated ones) and tools.
- Install IM-IRM safety bar.
- Swap SRM glass mass.
- Seal geophones.
- Find two geophone cables used by Okutomi-san.
- Rewire one geophone cable correctly.
- Add extra ≈1 kg to SF cap and adjust tilt.
- Center and fasten F0 yoke.
- Calibrate F0 GAS LVDT.
- Add arc weights and geophones.
- Test geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables.
- Remove crossbars.
- Crane suspension into tank.
SR2 (not so low priority)
- Run extension cord for OL.
- Set up OL cabling.
- Set up OL.
- Add more arc weights and tweak IP centering.
- Replace two borrowed geophones.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi).
- Install cable for MIF pico on LBB (with Izumi-san-tachi).
- Add ballast mass to LBB.
- Install manual yaw adjuster.
- Get top plate reduced?
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .