3512
Comment:
|
2365
|
Deletions are marked like this. | Additions are marked like this. |
Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-11-27 == * --(Bring SR2 into tunnel.)-- * --(Bring spare mirror box into tunnel.)-- * --(Bring 6 L-brackets for chassis boxes into tunnel.)-- * --(Bring cleaned parts from near ultrasonic cleaner into tunnel.)-- * --(Move SR2 rack into position.)-- * Set up SR2 rack * --(Add L-brackets to new whitening filter and two HPCDs (one in BS rack).)-- * Get ADC/DAC/DIO cards. * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Get cables/cards for SR2: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 2 DSub-9 FF gender benders (for LVDTs) * BNC-LEMO adapter (for LVDT sig gen) * --(Screw boxes into rack.)-- * --(Update SR2 suspension items doc.)-- * Run cables to assembly frame. * Find and attach feedthroughs. * --(Transfer spare mirror to spare mirror box.)-- * --(Transfer SR2 to good mirror box.)-- * Find mirror gluing items: * Prism micrometer stages * Prism jigs * Lenses for inspecting scribe lines * Procedure document. * Do mirror gluing. |
=== 2018-08-15 === ==== SR3 ==== * Controls work (Enzo and team). * Diagonalize OL (Terrence). * Do SF damper test (Hatoya-san). * Tune IP (Fujii-kun). |
Line 49: | Line 29: |
== 2017-12-04 == * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Adjust verticality of assembly frame; center and immobilize optical table. |
==== Software Etc ==== |
Line 60: | Line 34: |
* Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Rebuild PI #2 F0. * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SR2 PI LVDTs. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Get independent power supply for SR3 so SR2 can be powered back up. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Calibrate last six IM OSEMs. * Rebuild filter in PI #1. * Install clamps on PI #1. * Install geophone plates on PI #3. * Install geophone plates on PI #1. * Install correct IP in PI #2. * Rebuild filter in PI #2. * Install clamps on PI #2. * Install LBB blade units on PI #2. * Install geophone plates on PI #2. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 66: | Line 56: |
=== Design/Purchasing === * Lots of stuff - see Hirata-san's spreadsheet. |
=== Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? |
Line 69: | Line 68: |
==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-08-15
SR3
- Controls work (Enzo and team).
- Diagonalize OL (Terrence).
- Do SF damper test (Hatoya-san).
- Tune IP (Fujii-kun).
Software Etc
SR Prep Tasks - To Be Scheduled
Tunnel
- Rebuild PI #2 F0.
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SR2 PI LVDTs.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Get independent power supply for SR3 so SR2 can be powered back up.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Calibrate last six IM OSEMs.
- Rebuild filter in PI #1.
- Install clamps on PI #1.
- Install geophone plates on PI #3.
- Install geophone plates on PI #1.
- Install correct IP in PI #2.
- Rebuild filter in PI #2.
- Install clamps on PI #2.
- Install LBB blade units on PI #2.
- Install geophone plates on PI #2.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .