=== 2018-10-22 === ==== SRM (top priority) ==== * Main sequence * Adjust H2 and H3 OSEMs laterally and in/out. * Weigh BF/... section and adjust trim mass to fix pitch/roll. * Anchor cables to BF cap. * Install SF crossbars. * Build up SS to SF ring. * Bring in SF. * Hook BF/... . * PI * Choose and install CuBe spring.? * Replace yoke in F0.? * Install LBB blade units on PI.? * Install geophone plates on PI.? * Electronics * Scavenge HPCDs from SR2 and SR3. * Organize to get LPCDs modified. |
=== 2018-12-17 === ==== SRM ==== * Install/test new yaw mechanism. * Adjust height. * Check/adjust optic pitch; release LED to SR2. * Install Enomoto-kun's beam target plate (if available). * Install extension cord for pico drivers. * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.) * Find one geophone cable ordered for SRM but missing. * Rearrange miswired geophone cable. * Rebuild defective geophone cable. * Seal geophones. * Install geophones and arc weights. * Center IP. ==== SR3 ==== * Install/test new yaw mechanism. * Adjust height. * Realign OL. |
Line 41: | Line 41: |
==== SR2 (low priority) ==== * More TFs * Add more arc weights? * Do control filter design and installation. * Do measurement of yaw torque required for F0 yaw adjustment. * Gather items for SR2 OL. ==== Etc ==== * Tidy up: * Gather all PR/SR gluing tools and clean/label/organize them. * Move safety bar stuff to portable cleanroom between SR2 and SR3. * Clear space under SR3 stairs. * Etc, etc, etc. * Monitor AF disassembly. * Get SR2 optical table moved to SR3 area (under stairs). * Move cables; set up for geophone testing. * Make more feedthrough adaptors. |
==== SR2 ==== * Install/test new yaw adjuster. * Adjust height. * Get top plate reduced? * Set up OL cabling. * Set up OL. * Remove tape, writing etc on PI and PI items. * Add new feedthrough to lower part of tank (with Izumi-san-tachi)? * Install cable for MIF pico on LBB (with Izumi-san-tachi)? * Add ballast mass to LBB. |
Line 64: | Line 57: |
* Install, cable PI yaw steppers. * Correct flipped connections in SRM PI LVDTs. |
|
Line 71: | Line 62: |
* Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] |
|
Line 74: | Line 63: |
* Set up SR2 Guardian. | |
Line 77: | Line 65: |
* Set up SR2 Guardian. * Install damping filters for SR2. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-12-17
SRM
- Install/test new yaw mechanism.
- Adjust height.
- Check/adjust optic pitch; release LED to SR2.
- Install Enomoto-kun's beam target plate (if available).
- Install extension cord for pico drivers.
- Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
- Find one geophone cable ordered for SRM but missing.
- Rearrange miswired geophone cable.
- Rebuild defective geophone cable.
- Seal geophones.
- Install geophones and arc weights.
- Center IP.
SR3
- Install/test new yaw mechanism.
- Adjust height.
- Realign OL.
SR2
- Install/test new yaw adjuster.
- Adjust height.
- Get top plate reduced?
- Set up OL cabling.
- Set up OL.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
- Install cable for MIF pico on LBB (with Izumi-san-tachi)?
- Add ballast mass to LBB.
SR Prep Tasks - To Be Scheduled
Tunnel
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Split SRx real-time models?
Ordering
See ../WishList .