=== 2018-10-22 ===
==== SRM (top priority) ====
 * Main sequence
  * Adjust H2 and H3 OSEMs laterally and in/out.
  * Weigh BF/... section and adjust trim mass to fix pitch/roll.
  * Anchor cables to BF cap.
  * Install SF crossbars.
  * Build up SS to SF ring.
  * Bring in SF.
  * Hook BF/... .
 * PI
  * Choose and install CuBe spring.?
  * Replace yoke in F0.?
  * Install LBB blade units on PI.?
  * Install geophone plates on PI.?
 * Electronics
  * Scavenge HPCDs from SR2 and SR3.
  * Organize to get LPCDs modified.
=== 2018-12-17 ===
==== SRM ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Check/adjust optic pitch; release LED to SR2.
 * Install Enomoto-kun's beam target plate (if available).
 * Install extension cord for pico drivers.
 * Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
 * Find one geophone cable ordered for SRM but missing.
 * Rearrange miswired geophone cable.
 * Rebuild defective geophone cable.
 * Seal geophones.
 * Install geophones and arc weights.
 * Center IP.
==== SR3 ====
 * Install/test new yaw mechanism.
 * Adjust height.
 * Realign OL.
Line 41: Line 41:
==== SR2 (low priority) ====
 * More TFs
 * Add more arc weights?
 * Do control filter design and installation.
 * Do measurement of yaw torque required for F0 yaw adjustment.
 * Gather items for SR2 OL.

==== Etc ====
 * Tidy up:
  * Gather all PR/SR gluing tools and clean/label/organize them.
  * Move safety bar stuff to portable cleanroom between SR2 and SR3.
  * Clear space under SR3 stairs.
  * Etc, etc, etc.
 * Monitor AF disassembly.
 * Get SR2 optical table moved to SR3 area (under stairs).
 * Move cables; set up for geophone testing.
 * Make more feedthrough adaptors.
==== SR2 ====
 * Install/test new yaw adjuster.
 * Adjust height.
 * Get top plate reduced?
 * Set up OL cabling.
 * Set up OL.
 * Remove tape, writing etc on PI and PI items.
 * Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
 * Install cable for MIF pico on LBB (with Izumi-san-tachi)?
 * Add ballast mass to LBB.
Line 64: Line 57:
 * Install, cable PI yaw steppers.
 * Correct flipped connections in SRM PI LVDTs.
Line 71: Line 62:
 * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
Line 74: Line 63:
 * Set up SR2 Guardian.
Line 77: Line 65:
 * Set up SR2 Guardian.
 * Install damping filters for SR2.

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders, assembly frame.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-12-17

SRM

  • Install/test new yaw mechanism.
  • Adjust height.
  • Check/adjust optic pitch; release LED to SR2.
  • Install Enomoto-kun's beam target plate (if available).
  • Install extension cord for pico drivers.
  • Find two geophone cables used by Okutomi-san. (I looked in the second floor EXV room but didn't find them - Mark.)
  • Find one geophone cable ordered for SRM but missing.
  • Rearrange miswired geophone cable.
  • Rebuild defective geophone cable.
  • Seal geophones.
  • Install geophones and arc weights.
  • Center IP.

SR3

  • Install/test new yaw mechanism.
  • Adjust height.
  • Realign OL.

SR2

  • Install/test new yaw adjuster.
  • Adjust height.
  • Get top plate reduced?
  • Set up OL cabling.
  • Set up OL.
  • Remove tape, writing etc on PI and PI items.
  • Add new feedthrough to lower part of tank (with Izumi-san-tachi)?
  • Install cable for MIF pico on LBB (with Izumi-san-tachi)?
  • Add ballast mass to LBB.

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.

Mitaka or remotely

  • Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Install damping filters for SR2.
  • Review DAC channel requests.
  • Split SRx real-time models?

Ordering

See ../WishList .