Line 22: | Line 22: |
=== 2018-10-22 === | === 2018-10-29 === |
Line 24: | Line 24: |
* Electronics * More cable soldering? * Get soldered cables ultrasonically cleaned. * Collect unused cables for return to AEL. * PI * Finalize tuning. * Add more cable clamps. * Prepare SF magnet ring. |
|
Line 25: | Line 33: |
* Adjust H2 and H3 OSEMs laterally and in/out. * Weigh BF/... section and adjust trim mass to fix pitch/roll. * Anchor cables to BF cap. * Install SF crossbars. * Build up SS to SF ring. * Bring in SF. * Hook BF/... . * PI * Add more cable clamps. * Wash and install CuBe spring. * Electronics * Scavenge HPCDs from SR2 and SR3. * Organize to get LPCDs modified. ==== SR2 (low priority) ==== |
* Cable/test SF LVDT and FR. * Decide and install SF internal ballast mass (probably 1 Promec). * Reinstall SF cap. * Weigh SF/... section. * Install #353 poles * Move NB-03 jacks down. * Crane PI into AF. * Install F0-SF rod (#331) and flying saucer. * Route SF/... cables up to underside of F0. * Do vertical height budget. * Adjust SF trim mass for balance and keystone height. ==== SR2 ==== * Set up OL (Terrence). |
Line 43: | Line 50: |
* Do measurement of yaw torque required for F0 yaw adjustment. * Gather items for SR2 OL. |
* Do measurement of yaw torque required for F0 yaw adjustment? |
Line 46: | Line 52: |
==== Etc ==== * Tidy up: * Gather all PR/SR gluing tools and clean/label/organize them. * Move safety bar stuff to portable cleanroom between SR2 and SR3. * Clear space under SR3 stairs. * Etc, etc, etc. * Monitor AF disassembly. * Get SR2 optical table moved to SR3 area (under stairs). * Move cables; set up for geophone testing. * Make more feedthrough adaptors. |
=== 2018-11-05 === ==== SRM ==== * Main sequence * Cable/test IP LVDTs. * Cable/test IP FRs. * Unlock IP and center roughly. * Calibrate IP LVDTs. * Check/adjust alignment of SS. * Add arc weights and geophones (or extra mass equivalent to geophones). * Cable/test geophones. * Improve centering/tuning of IP and SS alignment. * LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. === 2018-11-12 === ==== SRM ==== * |
Line 61: | Line 76: |
* Check which LVDT cards are in which boxes. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-10-29
SRM (top priority)
- Electronics
- More cable soldering?
- Get soldered cables ultrasonically cleaned.
- Collect unused cables for return to AEL.
- PI
- Finalize tuning.
- Add more cable clamps.
- Prepare SF magnet ring.
- Main sequence
- Cable/test SF LVDT and FR.
- Decide and install SF internal ballast mass (probably 1 Promec).
- Reinstall SF cap.
- Weigh SF/... section.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
SR2
- Set up OL (Terrence).
- More TFs
- Add more arc weights?
- Do control filter design and installation.
- Do measurement of yaw torque required for F0 yaw adjustment?
2018-11-05
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
2018-11-12
SRM
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?