=== 2018-10-29 === | === 2018-11-05 === |
Line 24: | Line 24: |
* PI * Finalize tuning. * Add more cable clamps. |
* LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. * Main sequence |
Line 28: | Line 30: |
* Main sequence * Cable/test SF LVDT and FR. * Decide and install SF internal ballast mass (probably 1 Promec). * Reinstall SF cap. * Weigh SF/... section. |
|
Line 40: | Line 37: |
* Measure bounce frequencies. | |
Line 41: | Line 39: |
==== SR2 ==== * Set up OL (Terrence). * More TFs * Add more arc weights? * Do control filter design and installation. * Do measurement of yaw torque required for F0 yaw adjustment? |
==== SR2 (low priority) ==== * Set up OL. |
Line 48: | Line 42: |
=== 2018-11-05 === | === 2018-11-12 === |
Line 59: | Line 53: |
* LBB * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. === 2018-11-12 === ==== SRM ==== * |
|
Line 72: | Line 58: |
* Check which LVDT cards are in which boxes. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-05
SRM (top priority)
- LBB
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
- Main sequence
- Prepare SF magnet ring.
- Install #353 poles
- Move NB-03 jacks down.
- Crane PI into AF.
- Install F0-SF rod (#331) and flying saucer.
- Route SF/... cables up to underside of F0.
- Do vertical height budget.
- Adjust SF trim mass for balance and keystone height.
- Measure bounce frequencies.
SR2 (low priority)
- Set up OL.
2018-11-12
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .