Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-12-11 == * Double check prism heights. * Do mirror gluing. * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Weigh BF. * Find accessories. * Do weighing. * Find in-vac cables: * 2 x Type 3-6m * 1 x Type 3-2m * 4 x Type 4-1.5m * 5 x Type 1-2m * 7 x Type 2-2m * Set up SR2 rack * Get ADC/DAC/DIO cards. (Done?) * Hassle Miyo-kun for pico and stepper drivers. * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Get cables/cards for SR2. (Done?) * Find and attach feedthroughs. * Adjust verticality of assembly frame; center and immobilize optical table. |
=== 2018-11-05 === ==== SRM (top priority) ==== * Etc * --(Solder more cables.)-- * --(Ultrasonically clean more cables.)-- * --(Work out optimum LPCD output resistance; get one box modified.)-- * Work out how to change LPCD watchdog threshold; get one box modified. * LBB * --(Lay out LBB damper ring pieces near tank.)-- * Put magnets on LBB magnet ring. * Move KOACH filters * Put LBB damper rings in tank. * Set tank jacks to nominal height. * Main sequence * --(Run DC power and network to SRM_IP stepper driver.)-- * --(Add all steppers and picos to driver list and MEDM screens.)-- * --(Prepare SF magnet ring.)-- * --(Install #353 poles)-- * --(Move NB-03 jacks down; disassemble top of AF.)-- * --(Crane PI into AF.)-- * --(Install F0-SF rod (#331) and flying saucer.)-- * --(Route SF/... cables up to underside of F0.)-- * --(Install weaker CuBe spring.)-- * --(Add SF trim mass to leave 1.2 kg margin.)-- * --(Tweak BF trim mass to compensate for new cables.)-- * --(Measure bounce frequencies.)-- * Do vertical height budget. ==== SR2 (low priority) ==== * --(Unclamp LBB ring sandwich.)-- * --(Set LBB receptacles to CAD positions.)-- * --(Remove spacers; get LBB hanging.)-- * Set up OL. === 2018-11-12 === ==== SRM ==== * Main sequence * Cable/test IP LVDTs. * Cable/test IP FRs. * Unlock IP and center roughly. * Calibrate IP LVDTs. * Check/adjust alignment of SS. * Add arc weights and geophones (or extra mass equivalent to geophones). * Cable/test geophones. * Improve centering/tuning of IP and SS alignment. |
Line 49: | Line 71: |
* Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Check which LVDT cards are in which boxes. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable PI yaw steppers. * Correct flipped connections in SRM PI LVDTs. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 55: | Line 79: |
=== Design/Purchasing === * Lots of stuff - see Hirata-san's spreadsheet. |
=== Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? |
Line 58: | Line 91: |
==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-05
SRM (top priority)
- Etc
Solder more cables.
Ultrasonically clean more cables.
Work out optimum LPCD output resistance; get one box modified.
- Work out how to change LPCD watchdog threshold; get one box modified.
- LBB
Lay out LBB damper ring pieces near tank.
- Put magnets on LBB magnet ring.
- Move KOACH filters
- Put LBB damper rings in tank.
- Set tank jacks to nominal height.
- Main sequence
Run DC power and network to SRM_IP stepper driver.
Add all steppers and picos to driver list and MEDM screens.
Prepare SF magnet ring.
Install #353 poles
Move NB-03 jacks down; disassemble top of AF.
Crane PI into AF.
Install F0-SF rod (#331) and flying saucer.
Route SF/... cables up to underside of F0.
Install weaker CuBe spring.
Add SF trim mass to leave 1.2 kg margin.
Tweak BF trim mass to compensate for new cables.
Measure bounce frequencies.
- Do vertical height budget.
SR2 (low priority)
Unclamp LBB ring sandwich.
Set LBB receptacles to CAD positions.
Remove spacers; get LBB hanging.
- Set up OL.
2018-11-12
SRM
- Main sequence
- Cable/test IP LVDTs.
- Cable/test IP FRs.
- Unlock IP and center roughly.
- Calibrate IP LVDTs.
- Check/adjust alignment of SS.
- Add arc weights and geophones (or extra mass equivalent to geophones).
- Cable/test geophones.
- Improve centering/tuning of IP and SS alignment.
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .