Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-12-11 == * Double check prism heights. * Do mirror gluing. * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Weigh BF. * Find accessories. * Do weighing. * Find in-vac cables: * 2 x Type 3-6m * 1 x Type 3-2m * 4 x Type 4-1.5m * 5 x Type 1-2m * 7 x Type 2-2m * Set up SR2 rack * Get ADC/DAC/DIO cards. (Done?) * Hassle Miyo-kun for pico and stepper drivers. * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Get cables/cards for SR2. (Done?) * Find and attach feedthroughs. * Adjust verticality of assembly frame; center and immobilize optical table. |
=== 2018-11-12 === ==== SRM ==== * Characterize geophones. * Go/no-go test of all electronics items, especially SF/... section. * Do vertical height budget. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Test geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables. * Crane into tank. ==== SR2 (low priority) ==== * Set up OL pillar, shelf and viewports (with Akutsu-san, Tue evening, 11/20). * Set up OL cabling. * Set up OL. * Assist MIF team with pico cables, LBB ballast. === 2018-11-19 === ==== SRM ==== * Make new geophones. * Cable/test geophones. * Disconnect cables. * Remove crossbars. * Crane suspension into tank. ==== SR2 (not so low priority) ==== * Set up OL pillar and shelf (with Akutsu-san). * Set up OL cabling. * Set up OL. * Add more arc weights and tweak IP centering. * Replace two borrowed geophones. * Remove tape, writing etc on PI and PI items. * Add new feedthrough to lower part of tank (with Izumi-san-tachi). * Install cable for MIF pico on LBB (with Izumi-san-tachi). * Add ballast mass to LBB. * Install manual yaw adjuster. * Get top plate reduced? |
Line 49: | Line 66: |
* Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
=== Tunnel === * Check which LVDT cards are in which boxes. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable PI yaw steppers. * Correct flipped connections in SRM PI LVDTs. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 55: | Line 74: |
=== Design/Purchasing === * Lots of stuff - see Hirata-san's spreadsheet. |
=== Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? |
Line 58: | Line 85: |
==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-12
SRM
- Characterize geophones.
- Go/no-go test of all electronics items, especially SF/... section.
- Do vertical height budget.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Test geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables.
- Crane into tank.
SR2 (low priority)
- Set up OL pillar, shelf and viewports (with Akutsu-san, Tue evening, 11/20).
- Set up OL cabling.
- Set up OL.
- Assist MIF team with pico cables, LBB ballast.
2018-11-19
SRM
- Make new geophones.
- Cable/test geophones.
- Disconnect cables.
- Remove crossbars.
- Crane suspension into tank.
SR2 (not so low priority)
- Set up OL pillar and shelf (with Akutsu-san).
- Set up OL cabling.
- Set up OL.
- Add more arc weights and tweak IP centering.
- Replace two borrowed geophones.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi).
- Install cable for MIF pico on LBB (with Izumi-san-tachi).
- Add ballast mass to LBB.
- Install manual yaw adjuster.
- Get top plate reduced?
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .