Line 41: Line 41:
  * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.   * Hassle Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.
Line 44: Line 44:
 * Do inventory of ballast masses.
Line 45: Line 46:
 * Find circuit boards for geophones
  * Check if they have sockets soldered on.
  * Check if they come with hex posts.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Cu O-rings for pod (two sizes)
  * Hex posts and screws for circuit board (if needed).
  * Sockets for circuit board (if needed).
  * Viton O-ring for under geophone.
  * Screws for immobilizing geophone (M4?).
  * Screws for geophone to ingterface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.
Line 57: Line 71:

==== Order now ====
 * Bread boards for SR -> Orderd. delivery date:10/18-20
 * Include installation work in the contract
 * Total budget = 5MJPY
 * PEEK collet for "Small hexagon"(cable clamp) -> need modification.

==== Need simple design changes ====
 * Receptacles for Bread board damper
  * There is a mistake in the PROMEC drawing.
  * Hirata-san will make a new 2D drawing
 * IM wire clamps for SR
  * Need to change the height -> watiting second quote.

==== Need Fabian's input ====
 * Cable clamps for BF,SF and PI -> 方式を決める
  * Design change for the PI clamps, because the SR PIs are NIKHEF ones.
 * Ballast masses for BF and SF
 * 製作に2週間程度
 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
  * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談

==== Need more discussion/checks ====
 * Blade spring assembly for LBB
  * Check the load of the LBB and decide the design load of the springs
  * Correct the length
  * Scale the width of the current blades to design the new blades -> 高橋さんと相談
   * SR用LBBの重さを確認
 * Bread board damper rings
  * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification

=== Electronics ===

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

2017-12-11

  • Double check prism heights.
  • Do mirror gluing.
  • Assemble SR2 IP.
    • Set up for testing IP with BS pico driver.
    • Make pico cable.
    • Assemble IP.
    • Test IP picos.
  • Weigh BF.
    • Find accessories.
    • Do weighing.
  • Find in-vac cables:
    • 2 x Type 3-6m
    • 1 x Type 3-2m
    • 4 x Type 4-1.5m
    • 5 x Type 1-2m
    • 7 x Type 2-2m
  • Set up SR2 rack
    • Get ADC/DAC/DIO cards. (Done?)
    • Hassle Miyo-kun for pico and stepper drivers.
    • Hassle Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.
    • Get cables/cards for SR2. (Done?)
    • Find and attach feedthroughs.
  • Do inventory of ballast masses.
  • Adjust verticality of assembly frame; center and immobilize optical table.
  • Find circuit boards for geophones
    • Check if they have sockets soldered on.
    • Check if they come with hex posts.
  • Find out (from Takahashi-san) specifications for geophone pod items:
    • Screws for pod (cap-neck and neck-body).
    • Cu O-rings for pod (two sizes)
    • Hex posts and screws for circuit board (if needed).
    • Sockets for circuit board (if needed).
    • Viton O-ring for under geophone.
    • Screws for immobilizing geophone (M4?).
    • Screws for geophone to ingterface plate.
    • Screws for interface plate to PI.
  • Find or order geophone items.

SR Prep Tasks - To Be Scheduled

  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).
  • Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
  • Design final SF ballast masses (Fabian).
  • Get safety bars moved.
  • Get air hose connection moved.

Design/Purchasing

  • Lots of stuff - see Hirata-san's spreadsheet.

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)