== 2017-12-11 == * Double check prism heights. * Do mirror gluing. * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Weigh BF. * Find accessories. * Do weighing. * Find in-vac cables: * 2 x Type 3-6m * 1 x Type 3-2m * 4 x Type 4-1.5m * 5 x Type 1-2m * 7 x Type 2-2m * Set up SR2 rack * Get ADC/DAC/DIO cards. (Done?) * Hassle Miyo-kun for pico and stepper drivers. * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Get cables/cards for SR2. (Done?) * Find and attach feedthroughs. * Adjust verticality of assembly frame; center and immobilize optical table. |
==== Plan for week of 2018-04-16 ==== * Move SF and BF for SRM out of the way. * Check results of gluing. * Build 1xRM * Calibrate OSEMs. * Start SR3 Hang * Reset assembly frame crossbars to correct heights. * Center the optical table. * Align the assembly frame vertically. * Install IM ring and IM. * Hang optic. * Hang RM. * Cable RM OSEMs. ==== Plan for week of 2018-04-23 ==== * Clean parts (cable clamp bases, etc, etc; Hirata-san). * Observe KAGRA Phase 1 operations, assist if problems arise. * Continue SR3 hang. * Top filter disassembly ==== Plan for week of 2018-04-30 ==== * Golden Week! |
Line 49: | Line 47: |
* Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. === Design/Purchasing === * Lots of stuff - see Hirata-san's spreadsheet. ==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. ==== Need simple design changes ==== * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === |
=== Tunnel === * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Get SRM mushroom installed. * Install first set of LBB damper rings in SR2 (or SR3?) tank. * Set up SR2 Guardian. * Install damping filters for SR2. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * Do buoyancy calculation (see LIGO-T1100616). * Set up SR2 Guardian. * Install damping filters for SR2. * Review Shoda-san's Guardian. * Review DIO stuff. * Review DAC channel requests. * Order Cu O-rings for geophone. * Finish half-completed geophones. * Find fourth feedthrough for SR2, 8 more for SR3 and SRM. * Characterize top filter prototype blades. * Decide final top filter blade parameters and order. * Rebuild three top filters. * Do buoyancy calculation (see LIGO-T1100616). |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Plan for week of 2018-04-16
- Move SF and BF for SRM out of the way.
- Check results of gluing.
- Build 1xRM
- Calibrate OSEMs.
- Start SR3 Hang
- Reset assembly frame crossbars to correct heights.
- Center the optical table.
- Align the assembly frame vertically.
- Install IM ring and IM.
- Hang optic.
- Hang RM.
- Cable RM OSEMs.
Plan for week of 2018-04-23
- Clean parts (cable clamp bases, etc, etc; Hirata-san).
- Observe KAGRA Phase 1 operations, assist if problems arise.
- Continue SR3 hang.
- Top filter disassembly
Plan for week of 2018-04-30
- Golden Week!
SR Prep Tasks - To Be Scheduled
Tunnel
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Get SRM mushroom installed.
- Install first set of LBB damper rings in SR2 (or SR3?) tank.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- Do buoyancy calculation (see LIGO-T1100616).
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review Shoda-san's Guardian.
- Review DIO stuff.
- Review DAC channel requests.
- Order Cu O-rings for geophone.
- Finish half-completed geophones.
- Find fourth feedthrough for SR2, 8 more for SR3 and SRM.
- Characterize top filter prototype blades.
- Decide final top filter blade parameters and order.
- Rebuild three top filters.
- Do buoyancy calculation (see LIGO-T1100616).