Line 22: | Line 22: |
=== 2018-11-12 === | === 2018-11-26 === |
Line 24: | Line 24: |
* Characterize geophones. * Go/no-go test of all electronics items, especially SF/... section. * Do vertical height budget. * Disconnect SS from AF. * Raise PI on jacks. * Remove any remaining cable ties from SRM IP * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. |
* Clear space for SRM swap. * Ultrasonically clean metal parts associated with new SRM (except for solblack-coated ones) and tools. * Install IM-IRM safety bar. * Swap SRM glass mass. * Seal geophones. * Find two geophone cables used by Okutomi-san. * Rewire one geophone cable correctly. * Add extra ≈1 kg to SF cap and adjust tilt. * Center and fasten F0 yoke. * Calibrate F0 GAS LVDT. |
Line 36: | Line 37: |
* Disconnect cables. * Crane into tank. ==== SR2 (low priority) ==== * Set up OL pillar, shelf and viewports (with Akutsu-san, Tue evening, 11/20). * Set up OL cabling. * Set up OL. * Assist MIF team with pico cables, LBB ballast. === 2018-11-19 === ==== SRM ==== * Make new geophones. * Cable/test geophones. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-11-26
SRM
- Clear space for SRM swap.
- Ultrasonically clean metal parts associated with new SRM (except for solblack-coated ones) and tools.
- Install IM-IRM safety bar.
- Swap SRM glass mass.
- Seal geophones.
- Find two geophone cables used by Okutomi-san.
- Rewire one geophone cable correctly.
- Add extra ≈1 kg to SF cap and adjust tilt.
- Center and fasten F0 yoke.
- Calibrate F0 GAS LVDT.
- Add arc weights and geophones.
- Test geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables.
- Remove crossbars.
- Crane suspension into tank.
SR2 (not so low priority)
- Set up OL pillar and shelf (with Akutsu-san).
- Set up OL cabling.
- Set up OL.
- Add more arc weights and tweak IP centering.
- Replace two borrowed geophones.
- Remove tape, writing etc on PI and PI items.
- Add new feedthrough to lower part of tank (with Izumi-san-tachi).
- Install cable for MIF pico on LBB (with Izumi-san-tachi).
- Add ballast mass to LBB.
- Install manual yaw adjuster.
- Get top plate reduced?
SR Prep Tasks - To Be Scheduled
Tunnel
- Check which LVDT cards are in which boxes.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable PI yaw steppers.
- Correct flipped connections in SRM PI LVDTs.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .