Line 13: Line 13:
=== Facilities === ==== Facilities ====
Line 20: Line 20:
== Coming Weeks ==
Line 21: Line 22:
== 2017-12-11 ==
 * Double check prism heights.
 * Do mirror gluing.
 * Assemble SR2 IP.
  * Set up for testing IP with BS pico driver.
  * Make pico cable.
  * Assemble IP.
  * Test IP picos.
 * Weigh BF.
  * Find accessories.
  * Do weighing.
 * Find in-vac cables:
  * 2 x Type 3-6m
  * 1 x Type 3-2m
  * 4 x Type 4-1.5m
  * 5 x Type 1-2m
  * 7 x Type 2-2m
 * Set up SR2 rack
  * Get ADC/DAC/DIO cards. (Done?)
  * Hassle Miyo-kun for pico and stepper drivers.
  * Hassle Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.
  * Get cables/cards for SR2. (Done?)
  * Find and attach feedthroughs.
 * Do inventory of ballast masses.
 * Adjust verticality of assembly frame; center and immobilize optical table.
 * Find circuit boards for geophones
  * Check if they have sockets soldered on.
  * Check if they come with hex posts.
 * Find out (from Takahashi-san) specifications for geophone pod items:
  * Screws for pod (cap-neck and neck-body).
  * Cu O-rings for pod (two sizes)
  * Hex posts and screws for circuit board (if needed).
  * Sockets for circuit board (if needed).
  * Viton O-ring for under geophone.
  * Screws for immobilizing geophone (M4?).
  * Screws for geophone to ingterface plate.
  * Screws for interface plate to PI.
 * Find or order geophone items.

=== 2018-06-18 ===
==== Main Sequence ====
 * Tweak BF total trim masses.
 * SF/... TFs.
 * Add budgeted ballast mass to SF (or remove stuff!).
 * Cable, test SF FR.
 * Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
 * Check JGWDoc electronic item lists are up to date.

==== F0/LBB Stuff ====
 * Finish tuning F0 in PI #3.
 * Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
 * Characterize more blades?
 * Park PI #1 in SR3 AF.
 * Crane PI #3 behind SR3.
 * Crane PI #1 to factory area.

==== Software ====
 * Review/improve macro file fixes for split models; write klog; submit changes to SVN.
 * --(Install AC bandpass filters in SR3 WD filters.)--
 * Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
 * Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
 * Fix link to SUS_CUS_BSFM_BIO.adl in VIS_CUST_TYPEB_OVERALL.adl.
 * Rename VIS_CUST_BS_BIO.adl screen to VIS_CUST_TYPEB_BIO.adl and adjust links.
 * Fix hardwiring to BS in VIS_CUST_TYPEB_IP_WD_AC_BANDLIM.adl (ACC H2 and ACC H3 sections).

=== 2018-06-25 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
 * Build/tune F0 in PI #1.
 * Finish tuning PI #3.
 * Wrap PI #1.
 * Crane PI #1 to SR2 AF.
 * Crane PI #3 into SR3 AF.
==== Software/Remote ====

=== 2018-07-02 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-09 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-16 ===
==== Main Sequence ====
==== F0/LBB Stuff ====

=== 2018-07-23 ===
==== Main Sequence ====
==== F0/LBB Stuff ====
Line 63: Line 79:
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).
 * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
 * Design final SF ballast masses (Fabian).
 * Get safety bars moved.
 * Get air hose connection moved.
=== Tunnel ===
 * Get independent power supply for SR3 so SR2 can be powered back up.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Check SR2, SR3 TM coil gains for magnet polarity compensation.
 * Calibrate last six IM OSEMs.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * Rebuild filter in PI #1.
 * Install clamps on PI #1.
 * Install geophone plates on PI #3.
 * Install geophone plates on PI #1.
 * Install correct IP in PI #2.
 * Rebuild filter in PI #2.
 * Install clamps on PI #2.
 * Install LBB blade units on PI #2.
 * Install geophone plates on PI #2.
Line 69: Line 95:
=== Design/Purchasing ===
 * Lots of stuff - see Hirata-san's spreadsheet.
=== Mitaka or remotely ===
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
 * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
 * Set up SR2 Guardian.
 * Install damping filters for SR2.
 * Review Shoda-san's Guardian.
 * Review DIO stuff.
 * Review DAC channel requests.
 * Set up SR2 and SR3 Guardian.
 * Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
 * Install damping filters for SR2.
 * Do buoyancy calculation (see LIGO-T1100616).
 * Split SRx real-time models?

=== Ordering ===
See ../WishList .

VIS Type B SR Near Term To-Do List

Archived To-Do Items

Every Week

Coming Weeks

Preparation for SR Installation

Every Week

Facilities

  • Vacuum and roll floor.
  • Wipe ladders.
  • Tidy tools, parts.
  • Get stuff from ../WishList

Coming Weeks

2018-06-18

Main Sequence

  • Tweak BF total trim masses.
  • SF/... TFs.
  • Add budgeted ballast mass to SF (or remove stuff!).
  • Cable, test SF FR.
  • Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
  • Check JGWDoc electronic item lists are up to date.

F0/LBB Stuff

  • Finish tuning F0 in PI #3.
  • Replace ceramic thrust bearing in PI #3 with metal one (do PI #1 as well if time).
  • Characterize more blades?
  • Park PI #1 in SR3 AF.
  • Crane PI #3 behind SR3.
  • Crane PI #1 to factory area.

Software

  • Review/improve macro file fixes for split models; write klog; submit changes to SVN.
  • Install AC bandpass filters in SR3 WD filters.

  • Check coil filter gains for compensation of magnet polarities (confirm SR3 IM, set and confirm SR2 and SR3 TM).
  • Create software stepper drivers for SR3 and SRM and link to from STEP_MASTER.adl screen.
  • Fix link to SUS_CUS_BSFM_BIO.adl in VIS_CUST_TYPEB_OVERALL.adl.
  • Rename VIS_CUST_BS_BIO.adl screen to VIS_CUST_TYPEB_BIO.adl and adjust links.
  • Fix hardwiring to BS in VIS_CUST_TYPEB_IP_WD_AC_BANDLIM.adl (ACC H2 and ACC H3 sections).

2018-06-25

Main Sequence

F0/LBB Stuff

  • Build/tune F0 in PI #1.
  • Finish tuning PI #3.
  • Wrap PI #1.
  • Crane PI #1 to SR2 AF.
  • Crane PI #3 into SR3 AF.

Software/Remote

2018-07-02

Main Sequence

F0/LBB Stuff

2018-07-09

Main Sequence

F0/LBB Stuff

2018-07-16

Main Sequence

F0/LBB Stuff

2018-07-23

Main Sequence

F0/LBB Stuff

SR Prep Tasks - To Be Scheduled

Tunnel

  • Get independent power supply for SR3 so SR2 can be powered back up.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Check SR2, SR3 TM coil gains for magnet polarity compensation.
  • Calibrate last six IM OSEMs.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • Rebuild filter in PI #1.
  • Install clamps on PI #1.
  • Install geophone plates on PI #3.
  • Install geophone plates on PI #1.
  • Install correct IP in PI #2.
  • Rebuild filter in PI #2.
  • Install clamps on PI #2.
  • Install LBB blade units on PI #2.
  • Install geophone plates on PI #2.

Mitaka or remotely

  • Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
  • (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
  • Set up SR2 Guardian.
  • Install damping filters for SR2.
  • Review Shoda-san's Guardian.
  • Review DIO stuff.
  • Review DAC channel requests.
  • Set up SR2 and SR3 Guardian.
  • Create Python drivers for SR3_IM and SR3_BF picos and link to them from Mio-kun's PICO_MASTER.adl MEDM screen.
  • Install damping filters for SR2.
  • Do buoyancy calculation (see LIGO-T1100616).
  • Split SRx real-time models?

Ordering

See ../WishList .

KAGRA/Subgroups/VIS/TypeB/ToDoSR (last edited 2019-01-04 15:25:56 by MarkBarton)