== 2017-12-11 == * --(Double check prism heights.)-- * --(Do mirror gluing.)-- * Check mirror gluing. * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Weigh BF. * Find accessories. * Do weighing. * Find in-vac cables: * 2 x Type 3-6m * 1 x Type 3-2m * 4 x Type 4-1.5m * 5 x Type 1-2m * 7 x Type 2-2m * Set up SR2 rack * --(Get ADC/DAC/DIO cards)-- * --(Get cables/cards for SR2)-- * --(Get BIO white cables x 10)-- * Hassle Miyo-kun for pico and stepper drivers. * Hassle Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Find and attach feedthroughs. * Do inventory of ballast masses. * Adjust verticality of assembly frame; center and immobilize optical table. * Find circuit boards for geophones * Check if they have sockets soldered on. * Check if they come with hex posts. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Cu O-rings for pod (two sizes) * Hex posts and screws for circuit board (if needed). * Sockets for circuit board (if needed). * Viton O-ring for under geophone. * Screws for immobilizing geophone (M4?). * Screws for geophone to ingterface plate. * Screws for interface plate to PI. * Find or order geophone items. |
==== Plan for week of 3/5 ==== * --(Grab rack for SRM.)-- * --(See important pump down-related stuff at [[../ToDoBS]].)-- * --(Calibrate SF LVDT.)-- * --(Cable/test SF FR.)-- * --(Add SF cap.)-- * Lift SF/... with LGA and check weight/balance. * Start BF rebuild. ==== Plan for week of 3/12 ==== * Get SRM mushroom installed. * Set up SR3 and SRM racks. * Lay SR3 in-air cabling. |
Line 65: | Line 38: |
* Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). | * Review Shoda-san's Guardian. * Decide if we're really going to renumber IP channels. * Review DIO stuff. * Review SR2 model (especially screens, macro text file). * Review DAC channel requests. * Find out (from Takahashi-san) specifications for geophone pod items: * Screws for pod (cap-neck and neck-body). * Screws for geophone to interface plate. * Screws for interface plate to PI. * Find or order geophone items. * Get geophone circuit boards from Okutomi-san. * Find fourth feedthrough |
Line 70: | Line 54: |
=== Design/Purchasing === * Lots of stuff - see Hirata-san's spreadsheet. |
* Glue SR3. * Set up SR3 rack. * Set up SRM rack. * Rebuild two BFs. * Disassemble two top filters. * Rebuild three top filters. |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
Plan for week of 3/5
Grab rack for SRM.
See important pump down-related stuff at ../ToDoBS.
Calibrate SF LVDT.
Cable/test SF FR.
Add SF cap.
- Lift SF/... with LGA and check weight/balance.
- Start BF rebuild.
Plan for week of 3/12
- Get SRM mushroom installed.
- Set up SR3 and SRM racks.
- Lay SR3 in-air cabling.
SR Prep Tasks - To Be Scheduled
- Review Shoda-san's Guardian.
- Decide if we're really going to renumber IP channels.
- Review DIO stuff.
- Review SR2 model (especially screens, macro text file).
- Review DAC channel requests.
- Find out (from Takahashi-san) specifications for geophone pod items:
- Screws for pod (cap-neck and neck-body).
- Screws for geophone to interface plate.
- Screws for interface plate to PI.
- Find or order geophone items.
- Get geophone circuit boards from Okutomi-san.
- Find fourth feedthrough
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
- Glue SR3.
- Set up SR3 rack.
- Set up SRM rack.
- Rebuild two BFs.
- Disassemble two top filters.
- Rebuild three top filters.