Line 13: | Line 13: |
=== Facilities === | ==== Facilities ==== |
Line 15: | Line 15: |
* Wipe ladders. | * Wipe ladders, assembly frame. |
Line 20: | Line 20: |
== Coming Weeks == | |
Line 21: | Line 22: |
== 2017-08-28 == | === 2018-10-01 === ==== Etc ==== * Take SRM LVDT driver out of rack for Lucia. ==== SR2 ==== * Turn off KOACH filters in tank and see if BF keystone rises. * Install shelves in small rack, and put sat amps, drivers, etc inside. * Run power and network to pico drivers and steppers. * Test picos and steppers. * Adjust pitch/roll of IM with picos. * Offload BF GAS LVDT offset with FR stepper. * Add arc weights and geophones. (Might have to reserve one geophone for Fujii-Fun - check.) * Cable geophones. (Might have to reserve one cable for Fujii-kun - check.) * Unlock and center IP. * More TFs. ==== SRM ==== * Add TM OSEM cables. * Set TM pitch and tighten clamps. * Set RM pitch and tighten clamps. * Remove winch system and restore items removed from top of IM. * Suspend and weigh IM/... section. * Add BF crossbars to SS. * Build up SS to BF level. * Suspend IM/... section and adjust ballast/trim masses. * Install feedthroughs on AF (3 available; need to get a 4th). * Arrange power to SRM rack and get it running. * Check the IRIG-B 9999xx fix has been applied (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031||6031]]). ==== SR3 ==== * ''Don't even '''think''' about doing anything with SR3.'' |
Line 24: | Line 56: |
== SR Prep Tasks == === Design/Purchasing === * Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
== SR Prep Tasks - To Be Scheduled == === Tunnel === * Add SR3 LBB ballast mass. * Install SR3 LEN OL. * Rebuild PI #2 F0 for SRM. * Retrieve BNC-Lemo cable from Nakano-kun. * Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function. * Install, cable SR3 PI yaw stepper. * Correct flipped connections in SRM PI LVDTs. * Grab and configure a picomotor driver as SR2_BF 10.68.150.25. * Check SR2, SR3 TM coil gains for magnet polarity compensation. * Rebuild filter in PI #2 for SRM. * Clean/Replace yoke in PI #2 for SRM. * Install clamps on PI #2 for SRM. * Install LBB blade units on PI #2 for SRM. * Install geophone plates on PI #2 for SRM. * Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2. |
Line 30: | Line 74: |
==== Order now ==== * Bread boards for SR -> Orderd. delivery date:10/18-20 * Include installation work in the contract * Total budget = 5MJPY * PEEK collet for "Small hexagon"(cable clamp) -> need modification. |
=== Mitaka or remotely === * Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually). * Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen. * Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?] * (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass. * Set up SR2 Guardian. * Install damping filters for SR2. * Review DAC channel requests. * Set up SR2 Guardian. * Install damping filters for SR2. * Split SRx real-time models? |
Line 36: | Line 86: |
==== Need simple design changes ==== * SUS wires(3 types) for the LBB * Change the length -> Orderd. delivery date:10/ * Receptacles for Bread board damper * There is a mistake in the PROMEC drawing. * Hirata-san will make a new 2D drawing * IM wire clamps for SR * Need to change the height -> watiting second quote. * SR assembly frame -> Ordered. delivery date:9/27-29 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame ==== Need Fabian's input ==== * Cable clamps for BF,SF and PI -> 方式を決める * Design change for the PI clamps, because the SR PIs are NIKHEF ones. * Ballast masses for BF and SF * 製作に2週間程度 * 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。 * 測定に必要な物品の準備 -> 月曜日に高橋さんと相談 ==== Need more discussion/checks ==== * Blade spring assembly for LBB * Check the load of the LBB and decide the design load of the springs * Correct the length * Scale the width of the current blades to design the new blades -> 高橋さんと相談 * SR用LBBの重さを確認 * Bread board damper rings * Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification === Electronics === * Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
=== Ordering === See ../WishList . |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders, assembly frame.
- Tidy tools, parts.
Get stuff from ../WishList
Coming Weeks
2018-10-01
Etc
- Take SRM LVDT driver out of rack for Lucia.
SR2
- Turn off KOACH filters in tank and see if BF keystone rises.
- Install shelves in small rack, and put sat amps, drivers, etc inside.
- Run power and network to pico drivers and steppers.
- Test picos and steppers.
- Adjust pitch/roll of IM with picos.
- Offload BF GAS LVDT offset with FR stepper.
- Add arc weights and geophones. (Might have to reserve one geophone for Fujii-Fun - check.)
- Cable geophones. (Might have to reserve one cable for Fujii-kun - check.)
- Unlock and center IP.
- More TFs.
SRM
- Add TM OSEM cables.
- Set TM pitch and tighten clamps.
- Set RM pitch and tighten clamps.
- Remove winch system and restore items removed from top of IM.
- Suspend and weigh IM/... section.
- Add BF crossbars to SS.
- Build up SS to BF level.
- Suspend IM/... section and adjust ballast/trim masses.
- Install feedthroughs on AF (3 available; need to get a 4th).
- Arrange power to SRM rack and get it running.
Check the IRIG-B 9999xx fix has been applied (klog http://klog.icrr.u-tokyo.ac.jp/osl/index.php?r=6031).
SR3
Don't even think about doing anything with SR3.
SR Prep Tasks - To Be Scheduled
Tunnel
- Add SR3 LBB ballast mass.
- Install SR3 LEN OL.
- Rebuild PI #2 F0 for SRM.
- Retrieve BNC-Lemo cable from Nakano-kun.
- Get at least one BIO Converter chassis fully connected (CONTEC BIO card, WD and stepper motor chassis) for implementation and test of stepper motor reset function.
- Install, cable SR3 PI yaw stepper.
- Correct flipped connections in SRM PI LVDTs.
- Grab and configure a picomotor driver as SR2_BF 10.68.150.25.
- Check SR2, SR3 TM coil gains for magnet polarity compensation.
- Rebuild filter in PI #2 for SRM.
- Clean/Replace yoke in PI #2 for SRM.
- Install clamps on PI #2 for SRM.
- Install LBB blade units on PI #2 for SRM.
- Install geophone plates on PI #2 for SRM.
- Replace chipped magnets (12x12x12 mm) in SR3 IP, H1 and H2.
Mitaka or remotely
- Write generic Type B Guardian; make BS and SR3 inherit from it; make analog WD optional for now (all suspensions will get them eventually).
- Create software stepper drivers for SR3 and SRM and link to them from STEP_MASTER.adl screen.
- Make three in-air stepper splitter cables for SR2, SR3 and SRM. [done?]
- (Continue to) soak the sapphire prisms off the dummy BS for reuse on the SRM metal mass.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Review DAC channel requests.
- Set up SR2 Guardian.
- Install damping filters for SR2.
- Split SRx real-time models?
Ordering
See ../WishList .