2549
Comment:
|
3512
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
== 2017-08-28 == | == 2017-11-27 == * --(Bring SR2 into tunnel.)-- * --(Bring spare mirror box into tunnel.)-- * --(Bring 6 L-brackets for chassis boxes into tunnel.)-- * --(Bring cleaned parts from near ultrasonic cleaner into tunnel.)-- * --(Move SR2 rack into position.)-- * Set up SR2 rack * --(Add L-brackets to new whitening filter and two HPCDs (one in BS rack).)-- * Get ADC/DAC/DIO cards. * Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc. * Get cables/cards for SR2: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 2 DSub-9 FF gender benders (for LVDTs) * BNC-LEMO adapter (for LVDT sig gen) * --(Screw boxes into rack.)-- * --(Update SR2 suspension items doc.)-- * Run cables to assembly frame. * Find and attach feedthroughs. * --(Transfer spare mirror to spare mirror box.)-- * --(Transfer SR2 to good mirror box.)-- * Find mirror gluing items: * Prism micrometer stages * Prism jigs * Lenses for inspecting scribe lines * Procedure document. * Do mirror gluing. == 2017-12-04 == * Assemble SR2 IP. * Set up for testing IP with BS pico driver. * Make pico cable. * Assemble IP. * Test IP picos. * Adjust verticality of assembly frame; center and immobilize optical table. |
Line 24: | Line 59: |
== SR Prep Tasks == | == SR Prep Tasks - To Be Scheduled == * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). * Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done. * Design final SF ballast masses (Fabian). * Get safety bars moved. * Get air hose connection moved. |
Line 26: | Line 67: |
* Do rough mass budget for SR2/SR3/SRM. * Design SR assembly frame. * Design final SF ballast masses (Fabian). |
* Lots of stuff - see Hirata-san's spreadsheet. |
Line 37: | Line 76: |
* SUS wires(3 types) for the LBB * Change the length -> Orderd. delivery date:10/ |
|
Line 44: | Line 81: |
* SR assembly frame -> Ordered. delivery date:9/27-29 * Mark is checking the design from Fabian * We should order the parts necessary to modify the BS assembly frame to the SR2 assembly frame |
|
Line 66: | Line 100: |
* Get cables/cards for SR3: * 5 DSub-37 cables (tent) * 5 DSub-15M to DSub-9M adapter cables (tent) * 3 DIO cards (tent) * 2 DSub-9 FF gender benders (for LVDTs) * extra ADC card(s)? * extra DAC card(s)? * BNC-LEMO adapter (for LVDTs) * etc |
VIS Type B SR Near Term To-Do List
Preparation for SR Installation
Every Week
Facilities
- Vacuum and roll floor.
- Wipe ladders.
- Tidy tools, parts.
Get stuff from ../WishList
2017-11-27
Bring SR2 into tunnel.
Bring spare mirror box into tunnel.
Bring 6 L-brackets for chassis boxes into tunnel.
Bring cleaned parts from near ultrasonic cleaner into tunnel.
Move SR2 rack into position.
- Set up SR2 rack
Add L-brackets to new whitening filter and two HPCDs (one in BS rack).
- Get ADC/DAC/DIO cards.
- Get Miyakawa/Yamamoto to connect rack to DC power, Internet, etc.
- Get cables/cards for SR2:
- 5 DSub-37 cables (tent)
- 5 DSub-15M to DSub-9M adapter cables (tent)
- 2 DSub-9 FF gender benders (for LVDTs)
- BNC-LEMO adapter (for LVDT sig gen)
Screw boxes into rack.
Update SR2 suspension items doc.
- Run cables to assembly frame.
- Find and attach feedthroughs.
Transfer spare mirror to spare mirror box.
Transfer SR2 to good mirror box.
- Find mirror gluing items:
- Prism micrometer stages
- Prism jigs
- Lenses for inspecting scribe lines
- Procedure document.
- Do mirror gluing.
2017-12-04
- Assemble SR2 IP.
- Set up for testing IP with BS pico driver.
- Make pico cable.
- Assemble IP.
- Test IP picos.
- Adjust verticality of assembly frame; center and immobilize optical table.
SR Prep Tasks - To Be Scheduled
- Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).
- Finish mass budget for SR2/SR3/SRM (Fabian) - mostly done.
- Design final SF ballast masses (Fabian).
- Get safety bars moved.
- Get air hose connection moved.
Design/Purchasing
- Lots of stuff - see Hirata-san's spreadsheet.
Order now
Bread boards for SR -> Orderd. delivery date:10/18-20
- Include installation work in the contract
- Total budget = 5MJPY
PEEK collet for "Small hexagon"(cable clamp) -> need modification.
Need simple design changes
- Receptacles for Bread board damper
- There is a mistake in the PROMEC drawing.
- Hirata-san will make a new 2D drawing
- IM wire clamps for SR
Need to change the height -> watiting second quote.
Need Fabian's input
Cable clamps for BF,SF and PI -> 方式を決める
- Design change for the PI clamps, because the SR PIs are NIKHEF ones.
- Ballast masses for BF and SF
- 製作に2週間程度
- 10月頭にTop Filterの最適荷重を実測。それに合わせて発注。それまでにデザインは用意しておく。
測定に必要な物品の準備 -> 月曜日に高橋さんと相談
Need more discussion/checks
- Blade spring assembly for LBB
- Check the load of the LBB and decide the design load of the springs
- Correct the length
Scale the width of the current blades to design the new blades -> 高橋さんと相談
- SR用LBBの重さを確認
- Bread board damper rings
Need to check whether we can put a full ring into the chamber from the side flanges or not. -> need modification